THESE MINUTES ARE DRAFT UNTIL CONFIRMED AT THE NEXT MONTHLY MEETING OF THIS COUNCIL AND/OR COMMITTEE

 

MINUTES OF Planning Committee Meeting of the

Council of the City of Randwick HELD ON

Tuesday, 13 September 2011 AT 6:23pm

 

Present:

 

The Mayor, Councillor M Matson (East Ward)

 

North Ward                                           -  Councillors K Smith & M Woodsmith

 

South Ward                                          - Councillors R Belleli, C Matthews (arrived 7.44pm)  & A White

 

East Ward                                            - Councillors T Bowen & B Notley-Smith (arrived 7.35pm)

                                                              

West Ward                                           - Councillors B Hughes (Deputy Chairperson), J Procopiadis & S Nash

 

Central Ward                                        - Councillors A Andrews & G Stevenson (arrived 7.22pm)

 

Officers present:

 

General Manager                                             Mr R Brownlee

Director City Services                                      Mr J  Frangoples

Director City Planning                                       Ms S Truuvert

Director Governance & Financial Services             Mr G Banting

Manager Development Assessment                     Mr K Kyriacou

Senior Administrative Coordinator                       Ms J Hartshorn

Communications Manager                                  Mr J Hay

Manager Organisational Staff Services                 Ms F Calabrese

 

Apologies/Granting of Leave of Absences 

 

Apologies were received from Crs Seng and Tracey

 

RESOLVED: (Bowen/Belleli) that the apologies received from Crs Seng and Tracey be accepted and leave of absences from the meeting be granted.

 

Confirmation of the Minutes

 

Confirmation of the Minutes of the Planning Committee Meeting held on Tuesday 9 August 2011

PL119/11

RESOLUTION: (Bowen/Belleli) that the Minutes of the Planning Committee Meeting held on Tuesday 9 August 2011 (copies of which were circulated to all Councillors) be and are hereby confirmed as a correct record of the proceedings of that meeting, subject to the Declarations of Interests on page 2 of the minutes being amended as follows;

c) Cr Bowen declared a non significant non pecuniary interest in Item D96/11 as he knows the applicant and went to school with the applicant’s brother. [The reference to Cr Bowen indicating that he would not take part in the debate/vote on the matter is to be removed as Cr Bowen actually indicated that he would participate in the debate/vote on the matter].

 

Declarations of Pecuniary and Non-Pecuniary Interests

 

a)     Cr Smith declared a pecuniary interest in Item D114/11 and D116/11 as his employer has a business relationship with the applicants. Cr Smith indicated that he would not take part in the debate or the vote on these matters.

b)     Cr Bowen declared a non significant non pecuniary interest in Item D102/11 as he knows one of the objectors.

c)     Cr Bowen declared a non significant non pecuniary interest in Item D112/11 as lived next door to the property in question for some time and knows some of the objectors.

d)     Cr Bowen declared a non significant non pecuniary interest in Item D116/11 as he knows one of the objectors.

e)     Cr Andrews declared a non significant non pecuniary interest in Item D102/11 knows applicant through a previous association with the ALP.

f)       Cr Andrews declared a non significant non pecuniary interest in Item D103/11 as he knows a number of the objectors.

g)     Cr Andrews declared a non significant non pecuniary interest in Item D112/11 as he is aware of a number of objectors including Dominic Sullivan (a former Mayor of Randwick City Council).

h)     Cr Andrews declared a non significant non pecuniary interest in Item D119/11 as he knows the applicant.

i)        Cr Procopiadis declared a non significant non pecuniary interest in Item D118/11 as he knows the applicant.

j)       Cr White declared a non significant non pecuniary interest in Item D116/11 as he knows one of the objectors.

k)      Cr Woodsmith declared a non significant non pecuniary interest in Item D116/11 as she knows one of the objectors.

l)        Cr Procopiadis declared a non significant non pecuniary interest in Item D103/11 as he knows the supporter of the application. Cr Procopiadis indicated that he would not take part in the debate or the vote on the matter.

m)    Cr Notley-Smith declared a non significant non pecuniary interest in Item D101/11 as he knows one of the objectors.

n)     Cr Notley-Smith declared a non significant non pecuniary interest in Item D102/11 as he knows one of the objectors.

o)     Cr Notley-Smith declared a non significant non pecuniary interest in Item D103/11 as he knows one of the supporters.

p)     Cr Notley-Smith declared a non significant non pecuniary interest in Item D112/11 as he knows one of the objectors.

q)     Cr Notley-Smith declared a non significant non pecuniary interest in Item D119/11 as the applicant used to be his landlord.

 


Procedural Motion

D103/11 Development Application Report - 3 Edgecliffe Avenue, South Coogee (DA/1046/2010)

MOTION: (Matson/Woodsmith) that Item D103/11 (3 Edgecliffe Avenue, South Coogee) be brought forward for immediate consideration and be deferred given the concerns raised by a number of objectors in relation to the timing of the meeting notification. LOST.

 

A DIVISION was taken and the names of the Councillors voting FOR and AGAINST were as follows:

 

FOR

AGAINST

Councillor Belleli

Councillor Andrews

Councillor Matson

Councillor Bowen

Councillor Nash

Councillor Hughes

Councillor Woodsmith

Councillor Procopiadis

 

Councillor Smith

 

Councillor White

Total (4)

Total (6)

 

Address of Council by Members of the Public

Prior to consideration of the Agenda by the Committee, deputations were received in respect of the following matters:

D101/11    3 Milford Street, Randwick (DA/1132/2010)

 

Objector             Amos Stark – representing the objectors

 

Applicant           Alison Freeman

 

D102/11    5 Wisdom Street, Coogee (DA/837/2010)

 

Objector             Sharon Baker

 

Applicant           Larissa Ozog – representing the applicant

 

D103/11    3 Edgecliffe Avenue, South Coogee (DA/1046/2010)

 

Objector             Mark Sant – representing the objectors

 

Applicant           Tony Moody - representing the applicant

 

D106/11    22 Powell Street, Coogee (DA/439/2011)

 

Applicant           Stephanie Broke-Malone

 

D107/11    10-20 Anzac Parade, Kensington (DA/161/2011)

 

Applicant           Anthony Betros - representing the applicant

 

D111/11    43 Oswald Street, Randwick (DA/270/2011)

 

Applicant           Wayne Love - representing the applicant

 

D112/11    155-157 Arden Street, Coogee (DA/58/2008/D)

 

Applicant           Gary Chapman - representing the applicant

 

Having declared an interest in Item D114/11 earlier in the meeting, Cr Smith left the meeting at this point (7.30pm).

 

D114/11    508-510 Bunnerong Road, Matraville (DA/449/2011)

 

Objector             Richard Galea

 

Applicant           Chris Chalmer - representing the applicant

 

Cr Smith returned to the meeting (7.33pm).

 

D115/11    24 Cottenham Avenue, Kensington (DA/328/2007/A)

 

Applicant           Dominic Bennett - representing the applicant

 

Having declared an interest in Item D116/11 earlier in the meeting, Cr Smith left the meeting at this point (7.37pm).

 

D116/11    2 St. Marks Road, Randwick (DA/98/2010/A)

 

Objector             Richard Atkinson

 

Cr Smith returned to the meeting (7.41pm).

 

Having declared a prior interest in the following matter, the Director City Planning (Sima Truuvert) left the meeting at 7.41pm.

 

D119/11    13-17 Botany Street, Randwick (DA/850/2008/E)

 

Applicant           Spiro Stavis - representing the applicant

 

The Director City Planning (Sima Truuvert) returned to the meeting (7.44pm).

 

D120/11    34 Yorktown Parade, Maroubra (DA/89/2011)

 

Objector             Simone Ainsworth 

 

Applicant           Anthony Betros - representing the applicant

 

The meeting was adjourned at 7.54pm and was resumed at 8.17pm.

 

Urgent Business

Nil.

 

Development Application Reports

 

D101/11   Development Application Report - 3 Milford Street, Randwick (DA/1132/2010)

PL120/11

RESOLUTION: (Andrews/Mayor, Cr Matson) that Council, as the responsible authority, grant its development consent under Section 80 and 80(A) of the Environmental Planning and Assessment Act 1979 (as amended) to Development Application No. 1132/2010 for alterations and additions to the existing dwelling, including the installation of a swimming pool and pergola within the rear yard at 3 Milford Street, Randwick subject to the following conditions:

 

The following conditions are applied to satisfy the provisions of section 79C of the Environmental Planning & Assessment Act 1979 and to maintain reasonable levels of environmental amenity:

1.       The development must be implemented substantially in accordance with the plans numbered 88091.2, drawing numbers 002B, 004B 005B, 006B, dated  07.04.11 and received by Council on the 8th April 2011, the application form and on any supporting information received with the application, except as may be amended by the following conditions and as may be shown in red on the attached plans:

 

2.       The external materials, colours and finishes of the building are required to match, as closely as possible, the existing building.

 

3.       There must be no encroachment of the structure/s or associated articles onto Council’s road reserve, footway, nature strip or public place.

 

4.       Access to the right of way must not be unreasonably interfered with during building works being undertaken associated with this development.

 

5.       The access roller door in the eastern wall is to be reduced in width to 1.8m and plans accompanying the Construction Certificate amended.

 

6.       Only two window panels to Window 1 in the eastern elevation of the building are to be openable with the remaining window panels fixed. Plans accompanying the Construction Certificate are to be amended.

 

7.       Louvres are to be installed to Window 2 and plans accompanying the Construction Certificate are to be amended.

 

The following condition is imposed to satisfy relevant requirements of the Sydney Water Corporation.

8.       All building, plumbing and drainage work must be carried out in accordance with the requirements of the Sydney Water Corporation.

 

The approved Construction Certificate plans must be submitted to a Sydney Water Quick Check agent or Customer Centre prior to commencing any building or excavation works, to determine whether the development will affect Sydney Water’s sewer and water mains, stormwater drains and/or easements, and if any further requirements need to be met. 

 

If suitable, the plans will be appropriately stamped.  For Quick Check agent details please refer to Sydney Water’s web site at www.sydneywater.com.au and go to the Building, Developing and Plumbing, then Quick Check or Building and Renovating or telephone 13 20 92.

 

The principal certifying authority must ensure that a Quick Check Agent/Sydney Water has appropriately stamped the plans before commencing any works.

 

The following condition is applied to meet additional demands for public facilities;

9.       In accordance with Council’s Section 94A Development Contributions Plan effective from 2 July 2007, based on the development cost of $ 99 000 the following applicable monetary levy must be paid to Council: $ 495.00.

 

The levy must be paid in cash, bank cheque or by credit card prior to a construction certificate being issued for the proposed development. The development is subject to an index to reflect quarterly variations in the Consumer Price Index (CPI) from the date of Council’s determination to the date of payment.

 

Council’s Section 94A Development Contribution Plans may be inspected at the Customer Service Centre, Administrative Centre, 30 Frances Street, Randwick or at www.randwick.nsw.gov.au.

 

The following conditions are imposed to promote ecologically sustainable development and energy efficiency.

10.     In accordance with Section 80A (11) of the Environmental Planning and Assessment Act 1979 and Clause 97A of the Environmental Planning and Assessment Regulation 2000, it is a prescribed condition that all of the required commitments listed in the relevant BASIX Certificate for this development are fulfilled.

 

11.     In accordance with the provisions of the Environmental Planning & Assessment Regulation 2000, a relevant BASIX Certificate and associated documentation must be submitted to the Certifying Authority with the Construction Certificate application for this development.

 

The required commitments listed and identified in the BASIX Certificate are to be included on the plans, specifications and associated documentation for the proposed development, to the satisfaction of the Certifying Authority.

 

The design of the building must not be inconsistent with the development consent and any proposed variations to the building to achieve the BASIX commitments may necessitate a new development consent or amendment to the existing consent to be obtained, prior to a construction certificate being issued.

 

12.     The following provisions are to be implemented in accordance with the relevant BASIX Certificate and details are to be included in the Construction Certificate documentation (as applicable), to the satisfaction of the Certifying Authority:

 

·           Stormwater management (i.e. rainwater tanks)

·           Water efficiency (i.e. triple A rated taps and showers, dual flush toilets and water re-use)

·           Landscaping provisions

·           Thermal comfort (i.e. construction materials, glazing and insulation)

·           Energy efficiency (i.e. cooling & heating provisions and hot water systems)

 

13.     In accordance with Clause 154B of the Environmental Planning & Assessment Regulation 2000, a Certifying Authority must not issue an Occupation Certificate for this development, unless it is satisfied that each of the required BASIX commitments have been fulfilled.

 

Relevant documentary evidence of compliance with the BASIX commitments is to be forwarded to the Council upon issuing an Occupation Certificate.

 

The following group of conditions have been applied to ensure that adequate drainage is provided from the premises and to maintain adequate levels of health and amenity in the locality:

14.     Surface water/stormwater must be drained and discharged to the street gutter or suitably designed absorption pit, to the satisfaction of the Certifying Authority and details are to be included in the construction certificate application for the development.

 

Absorption pits must be located not less than 3m from any adjoining premises and the stormwater must not be directed or flow onto any adjoining premises or cause a nuisance.

 

Details of any works proposed to be carried out in or on a public road/footway are to be submitted to and approved by Council prior to commencement of works.

 

The following conditions are applied to ensure that the development satisfies the provisions of the Environmental Planning and Assessment Act 1979 and Regulations:

15.     The requirements and provisions of the Environmental Planning & Assessment Act 1979 and Environmental Planning & Assessment Regulation 2000, must be fully complied with at all times.

 

Failure to comply with these legislative requirements is an offence and may result in the commencement of legal proceedings, issuing of `on-the-spot` penalty infringements or service of a notice and order by Council.

 

16.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that all building work must be carried out in accordance with the provisions of the Building Code of Australia (BCA).

 

17.     Prior to the commencement of any building works, the following requirements must be complied with:

 

a)    a Construction Certificate must be obtained from the Council or an accredited certifier, in accordance with the provisions of the Environmental Planning & Assessment Act 1979.

 

A copy of the construction certificate, the approved development consent plans and consent conditions must be kept on the site at all times and be made available to the Council officers and all building contractors for assessment.

 

b)    a Principal Certifying Authority (PCA) must be appointed to carry out the necessary building inspections and to issue an occupation certificate; and

 

c)    a principal contractor must be appointed for the building work, or in relation to residential building work, an owner-builder permit may be obtained in accordance with the requirements of the Home Building Act 1989, and the PCA and Council are to be notified accordingly; and

 

d)    the principal contractor must be advised of the required critical stage inspections and other inspections to be carried out, as specified by the Principal Certifying Authority; and

 

e)    at least two days notice must be given to the Council, in writing, prior to commencing building works.

 

18.     The building works must be inspected by the Principal Certifying Authority (or another certifying authority if the Principal Certifying Authority agrees), in accordance with sections 109 E (3) of the Environmental Planning & Assessment Act 1979 and clause 162A of the Environmental Planning & Assessment Regulation 2000, to monitor compliance with the relevant standards of construction, Council’s development consent and the construction certificate.

 

The Principal Certifying Authority must specify the relevant stages of construction to be inspected and a satisfactory inspection must be carried out, to the satisfaction of the Principal Certifying Authority, prior to proceeding to the subsequent stages of construction or finalisation of the works (as applicable).

 

19.     A sign must be erected and maintained in a prominent position on the site for the duration of the works, which contains the following details:

 

·          name, address, contractor licence number and telephone number of the principal contractor, including a telephone number at which the person may be contacted outside working hours, or owner-builder permit details (as applicable);

·          name, address and telephone number of the Principal Certifying Authority; and

·          a statement stating that “unauthorised entry to the work site is prohibited”.

 

20.     The relevant requirements of the Home Building Act 1989 must be complied with, in accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000.

 

Details of the Licensed Building Contractor (and a copy of any relevant Certificate of Insurance) or a copy of the Owner-Builder Permit (as applicable) must be provided to the Principal Certifying Authority and Council prior to commencement of works.

 

21.     The required Long Service Levy payment, under the Building and Construction Industry Long Service Payments Act 1986, is to be forwarded to the Long Service Levy Corporation or the Council, prior to the issuing of a Construction Certificate, in accordance with Section 109F of the Environmental Planning & Assessment Act 1979.

 

At the time of this development consent, Long Service Levy payment is applicable on building work having a value of $25,000 or more, at the rate of 0.35% of the cost of the works.

 

22.     An Occupation Certificate must be obtained from the Principal Certifying Authority prior to any occupation of the building work encompassed in this development consent (including alterations and additions to existing buildings), in accordance with the relevant provisions of the Environmental Planning & Assessment Act 1979.

 

An Occupation Certificate must not be issued for the development if the development is inconsistent with the development consent.  The requirements of the Environmental Planning & Assessment Act 1979 and conditions of development consent must be satisfied prior to the issuing of an occupation certificate.

 

23.     Smoke alarms are required to be installed in each Class 1 building or residential dwelling in accordance with the relevant provisions of Part 3.7.2 of the B.C.A. – Housing Provisions.

 

Smoke alarms must comply with AS3786 – Smoke alarms and be connected to the consumer mains electric power supply and provided with a battery back-up.

 

Details of compliance with the provisions of the Building Code of Australia must be included in the plans/specification for the construction certificate.

 

The following conditions are applied to ensure that the development satisfies relevant standards of construction, and to maintain adequate levels of health, safety and amenity during construction:

24.     Certificate of Adequacy supplied by a professional engineer shall be submitted to the certifying authority (and the Council, if the Council is not the certifying authority) prior to a construction certificate being issued for the development, detailing the design of the new retaining wall to the eastern side boundary and swimming pool design, including any works that are required to maintain the structural stability of the adjoining sites.

 

25.     The demolition of buildings and the removal, storage, handling and disposal of building materials must be carried out in accordance with the relevant requirements of WorkCover NSW, the NSW Department of Environment & Climate Change (formerly EPA) and Randwick City Council policies, including:

 

·          Occupational Health and Safety Act 2000 & Regulations

·          WorkCover NSW Guidelines & Codes of Practice

·          Australian Standard 2601 (2001) – Demolition of Structures

·          The Protection of the Environment Operations Act 1997 and Protection of the Environment Operations (Waste) Regulation 2005

·          Relevant DECC/EPA Guidelines

·          Randwick City Council Asbestos Policy (adopted 13 September 2005)

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development section or a copy can be obtained from Council’s Customer Service Centre.

 

26.     All excavations and backfilling associated with the erection or demolition of a building must be executed safely in accordance with appropriate professional standards and excavations are to be properly guarded and supported to prevent them from being dangerous to life, property or buildings.

 

Retaining walls, shoring or piling must be provided to support land which is excavated in association with the erection or demolition of a building, to prevent the movement of soil and to support the adjacent land and buildings, if the soil conditions require it.  Adequate provisions are also to be made for drainage.

 

Retaining walls, shoring, or piling must be designed and installed in accordance with appropriate professional standards and the relevant requirements of the Building Code of Australia and Australian Standards.  Details of proposed retaining walls, shoring or piling are to be submitted to and approved by the Principal Certifying Authority for the development prior to commencing such excavations or works.

 

27.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 E of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that the adjoining land and buildings located upon the adjoining land must be adequately supported at all times.

 

a)     If the development involves an excavation that extends below the level of the base of the footings of a building on adjoining land, the person having the benefit of the development must, at the person’s own expense:

 

i)      protect and support the adjoining premises from possible damage from the excavation, and

ii)      where necessary, underpin the adjoining premises to prevent any such damage.

 

b)     The condition referred to in subclause 1) does not apply if the person having the benefit of the development consent owns the adjoining land or the owner of the adjoining land has given consent in writing to that condition not applying.

 

28.     A dilapidation report prepared by a professional engineer, building surveyor or other suitably qualified independent person must be submitted to the satisfaction of the Principal Certifying Authority prior to commencement of any demolition, excavation or building works, in the following cases:

 

·           excavations for, additions to dwellings, swimming pools or the like which are proposed to be located within the zone of influence of the footings of any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

·           additions to dwellings sited up to shared property boundaries (e.g. additions to a semi-detached dwelling or a terraced dwelling),

·           excavations for additions to dwellings, swimming pools or the like which are within rock and may result in vibration and or potential damage to any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

·           as otherwise may be required by the Principal Certifying Authority.

 

The report (including photographs) are required to detail the current condition and status of any dwelling, associated garage or other substantial structure located upon the adjoining premises, which may be affected by the subject works.  A copy of the dilapidation report is to be given to the owners of the premises encompassed in the report/s before commencing any works.

 

29.     Except with the written approval of Council’s Manager of Health, Building & Regulatory Services, all building, demolition and associated site works (including site deliveries) must only be carried out between the hours of 7.00am to 5.00pm on Monday to Friday inclusive and between 8.00am to 5.00pm on Saturdays and all building activities are strictly prohibited on Sundays and Public Holidays.

 

In addition, the use of any rock excavation machinery or any mechanical pile drivers or the like, is restricted to the hours of 8.00am to 5.00pm (maximum) on Monday to Friday only, to minimise the noise levels during construction and loss of amenity to nearby residents.

 

30.     Noise and vibration emissions during the construction of the building and associated site works must not result in damage to nearby premises or result in an unreasonable loss of amenity to nearby residents and the relevant requirements of the Protection of the Environment Operations Act 1997 and NSW DECC Guidelines must be satisfied at all times.

 

Noise and vibration from any rock excavation machinery, pile drivers and all plant and equipment must be minimised, by using appropriate plant and equipment, silencers and the implementation of noise management strategies.

 

A Construction Noise Management Plan, is required to be developed and implemented throughout the works, to the satisfaction of the Council.  A copy of the strategy must be provided to the Principal Certifying Authority and Council prior to the commencement of site works.

 

The Construction Noise Management Plan is to be prepared in accordance with the relevant provisions of the DECC Construction Noise Guideline.

 

31.     Public safety must be maintained at all times and public access to the site and building works, materials and equipment on the site is to be restricted, when work is not in progress or the site is unoccupied, to the satisfaction of Council.

 

A temporary safety fence is to be provided to protect the public, located to the perimeter of the site (unless the site is separated from the adjoining land by an existing structurally adequate fence, having a minimum height of 1.5 metres).  Temporary fences are to have a minimum height of 1.8 metres and be constructed of cyclone wire fencing, with geotextile fabric attached to the inside of the fence to provide dust control, or other material approved by Council.

 

If it is proposed to locate any site fencing, hoardings or amenities upon any part of the footpath, nature strip or public place, the written consent from Council’s Building Services section must be obtained beforehand and detailed plans are to be submitted to Council for consideration, together with payment of the weekly charge in accordance with Council’s adopted fees and charges.

 

32.     A Construction Site Management Plan is to be developed and implemented prior to the commencement of any works.  The site management plan must include the following measures, as applicable to the type of development:

 

·       location and construction of protective fencing/hoardings to the perimeter of the site;

·       location of site storage areas/sheds/equipment;

·       location of building materials for construction;

·       provisions for public safety;

·       dust control measures;

·       site access location and construction

·       details of methods of disposal of demolition materials;

·       protective measures for tree preservation;

·       provisions for temporary sanitary facilities;

·       location and size of waste containers/bulk bins;

·       details of proposed sediment and erosion control measures;

·       construction noise and vibration management;

·       construction traffic management details.

 

The site management measures are to be implemented prior to the commencement of any site works and be maintained throughout the works, to maintain reasonable levels of public health, safety and amenity to the satisfaction of Council. 

 

A copy of the Construction Site Management Plan must be provided to the Principal Certifying Authority and Council.  A copy must also be maintained on site and be made available to Council officers upon request.

 

The sediment and erosion control measures are to be in accordance with the manual for Managing Urban Stormwater – Soils and Construction, published by Landcom, to the satisfaction of Council and details are to be provided in the Construction Site Management Plan. 

 

33.     Public safety and convenience must be maintained at all times during demolition, excavation and construction works and the following requirements must be complied with:

 

a)     Building materials, sand, soil, waste materials, construction equipment or other activities must not be placed upon the footpath, roadway or nature strip at any time and the footpath, nature strip and road must be maintained in a clean condition and free from any obstructions, soil and debris at all times.

 

b)     Building operations such as brick cutting, washing tools or equipment and mixing mortar are not permitted on public footpaths, roadways, nature strips, in any public place or any location which may lead to the discharge of materials into the stormwater drainage system.

 

c)     Bulk bins/waste containers must not be located upon the footpath, roadway or nature strip at any time without the prior written approval of the Council.  Applications to place a waste container in a public place can be made to Council’s Health Building and Regulatory Services section.

 

d)     Any part of Council’s road, footway or nature strip which is damaged as a result of the work must be repaired or replaced to Council’s satisfaction.

 

The following conditions are applied to ensure compliance with the Swimming Pools Act 1992 and to maintain public safety and amenity:

34.     Swimming pools are to be provided with childproof fences and self-locking gates, in accordance with the Swimming Pools Act 1992 and regulations.

 

The swimming pool is to be surrounded by a fence having a minimum height of 1.2m, that separates the pool from any residential building situated on the premises and from any place (whether public or private) adjoining the premises; and that is designed, constructed and installed in accordance with AS 1926.1 - 2007.

 

Gates to pool area shall be a maximum width of 1 metre, and be self-closing and latching; the gate is required to open outwards from the pool area and prevent a small child opening the gate or door when the gate or door is closed.

 

Temporary pool safety fencing is to be provided pending the completion of all building work and the pool must not be filled until a fencing inspection has been carried out and approved by the principal certifying authority.

 

A ‘warning notice’ must be erected in a prominent position in the immediate vicinity of the swimming pool, in accordance with the provisions of the Swimming Pools Regulation 2008, detailing pool safety requirements, resuscitation techniques and the importance of the supervision of children at all times.

 

35.     Swimming pools are to be designed, installed and operated in accordance with the following general requirements: -

 

a)    Backwash of the pool filter and other discharge of water is to be drained to the sewer in accordance with the requirements of the Sydney Water Corporation; and

a)    All pool overflow water is to be drained away from the building and adjoining premises, so as not to result in a nuisance or damage to premises; and

b)    Water recirculation and filtrations systems are required to comply with AS 1926.3 – 2003:  Swimming Pool Safety – Water Recirculation and Filtration Systems; and

c)    Pool plant and equipment is to be enclosed in a sound absorbing enclosure or installed within a building, to minimise noise emissions and possible nuisance to nearby residents; and

d)    The pool plant and equipment shall not be operated during the following hours if the noise emitted can be heard within a habitable room in any other residential premises, or, as otherwise specified in relevant Noise Control Regulations:

 

i.      before 8.00am or after 8.00pm on any Sunday or public holiday; or

ii.     before 7.00am or after 8.00pm on any other day.

 

36.     Written notification must be provided to Council advising of the installation and completion of the Swimming Pool (or Spa Pool), to satisfy the requirements of the Swimming Pools Act 1992, prior to issuing an Occupation Certificate.

 

Council’s “Notification & Registration of a Swimming Pool” form must be completed and forwarded to Council prior to any Occupation Certificate being issued for the pool.

 

The following conditions have been applied to ensure that noise emissions from the development satisfy legislative requirements and maintain reasonable levels of amenity to the area:

37.     The operation of all plant and equipment shall not give rise to an ‘offensive noise’ as defined in the Protection of the Environment Operations Act 1997 and Regulations.

 

In this regard, the operation of the plant and equipment shall not give rise to an LAeq, 15 min sound pressure level at any affected premises that exceeds the background LA90, 15 min noise level, measured in the absence of the noise source/s under consideration by more than 5dB(A) in accordance with relevant NSW Department of Environment & Conservation Noise Control Guidelines.

 

38.     The installation of rainwater tanks shall comply with the following noise control requirements:-

 

a)     The operation of all plant and equipment shall not give rise to an ‘offensive noise’ as defined in the Protection of the Environment Operations Act 1997 and Regulations.

 

In this regard, the operation of the plant and equipment shall not give rise to an LAeq, 15 min sound pressure level at any affected premises that exceeds the background LA90, 15 min noise level, measured in the absence of the noise source/s under consideration by more than 5dB(A) in accordance with relevant NSW Department of Environment & Conservation Noise Control Guidelines.

 

b)     Plant and equipment associated with rainwater tank(s) are to be enclosed in a sound absorbing enclosure or installed within a building, to minimise noise emissions and possible nuisance to nearby residents.

 

c)     The operation of plant and equipment associated with the rainwater tank(s) are to be restricted to the following hours if the noise emitted can be heard within a habitable room in any other residential premises:

       

●     before 8.00am or after 8.00pm on weekends or public holiday; or

●     before 7.00am or after 8.00pm on weekdays.

 

The following conditions are applied to provide adequate provisions for access, transport and infrastructure:

39.     The applicant must meet the full cost for Council or a Council approved contractor to repair/replace any damaged sections of Council's footpath, kerb & gutter, nature strip etc which are due to building works being carried out at the above site. This includes the removal of cement slurry from Council's footpath and roadway.

 

40.     All external civil work to be carried out on Council property (including the installation and repair of roads, footpaths, vehicular crossings, kerb and guttering and drainage works), must be carried out in accordance with Council’s Policy for “Vehicular Access and Road and Drainage Works” and the following requirements:

 

a)       All work on Council land must be carried out by Council, unless specific  written approval has been obtained from Council to use non-Council contractors.

 

b)       Details of the proposed civil works to be carried out on Council land must be submitted to Council in a Pre-paid Works Application Form, prior to issuing an occupation certificate, together with payment of the relevant fees.

 

c)       If it is proposed to use non-Council contractors to carry out the civil works on Council land, the work must not commence until the written approval has been obtained from Council and the work must be carried out in accordance with the conditions of consent, Council’s design details and payment of a Council design and supervision fee.

 

d)       The civil works must be completed in accordance with Council’s conditions of consent and approved design and construction documentation, prior to occupation of the development, or as otherwise approved by Council in writing.

 

The following conditions are applied to provide adequate consideration for service authority assets:

41.     The applicant must meet the full cost for telecommunication companies, gas providers, Energy Australia and Sydney Water to adjust/repair/relocate their services as required.  The applicant must make the necessary arrangements with the service authority.

 

The following conditions are applied to provide adequate provisions for landscaping and to maintain reasonable levels of environmental amenity:

42.     That part of the nature-strip upon Council's footway which is damaged during the construction of the proposed works shall be excavated to a depth of 150mm, backfilled with topsoil equivalent with 'Organic Garden Mix' as supplied by Australian Native Landscapes, and re-turfed with Kikuyu turf or similar. Such works shall be completed at the applicant’s expense prior to the issue of a final Occupation Certificate.

 

Tree Removals

43.     39  Approval is granted for removal of the two Syagrus romanzoffianum (Cocos Palms) and Cyathea cooperi (Tree Fern) in the rear yard, close to the rear of the existing dwelling, due both to their insignificance, as well as to accommodate the proposed works as shown

 

Advisory

A1      Demolition, building or excavation work must not be commenced until;

 

·          A Construction Certificate has been obtained from Council or an Accredited Certifier

·          Council or an Accredited Certifier has been appointed as the Principal Certifying Authority for the development

·          Council and the Principal Certifying Authority have been given at least 2 days notice (in writing) prior to commencing any works.

 

Failure to comply with these important requirements is an offence, which renders the responsible person liable to a maximum penalty of $1.1 million under the Environmental Planning & Assessment Act 1979.  Alternatively, Council may issue a penalty infringement notice (for up to $1,500) for each offence.

 

A2      A local approval application must be submitted to and be approved by Council's Building Services section prior to commencing any of the following activities on a footpath, road, nature strip or in any public place:-

 

·          Install or erect any site fencing, hoardings or site structures

·          Operate a crane or hoist goods or materials over a footpath or road

·          Placement of a waste skip (greater than 3m in length) or any container or other article.

 

A3      Specific details of the location of the building/s should be provided in the Construction Certificate to demonstrate that the proposed building work will not encroach onto the adjoining properties, Council’s road reserve or any public place, to the satisfaction of the certifying authority.

 

A4      This determination does not include an assessment of the proposed works under the Building Code of Australia (BCA) and other relevant Standards.  All new building work (including alterations and additions) must comply with the BCA and relevant Standards and you are advised to liaise with your architect, engineer and building consultant prior to lodgement of your construction certificate.

 

A5      The applicant is to advise Council in writing and/or photographs of any signs of existing damage to the Council roadway, footway, or verge prior to the commencement of any building/demolition works

 

MOTION: (Andrews/Mayor, Cr Matson) CARRIED UNANIMOUSLY - SEE RESOLUTION.

 

 

 

D102/11   Development Application Report - 5 Wisdom Street, Coogee (DA/837/2010)

PL121/11

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

PL122/11

 

 

 

 

 

RESOLUTUION: (Notley-Smith/Smith) that the application be deferred for one week to enable a site visit to be organised for Councillors to discuss the original proposal, the current proposal, the impact of the proposed amendments and the objectors’ concerns.

 

MOTION: (Woodsmith/Mayor, Cr Matson) that the application be deferred to enable the submission of amended plans that provide for:

 

-         the proposal being setback an additional metre from the front of the site.

-         the proposed balcony surrounds being opaque glass. LOST.

 

Crs Matthews and Belleli requested an apology from the Mayor for indicating that Councillors were interfering with Council planning staff.

 

The Chairperson (Cr Hughes) indicated that he believed that the Mayor was being misinterpreted.

 

The Chairperson rose and called the Councillors to order for interjecting.

 

After calling the Councillors to order again for continual interjections, the Chairperson adjourned the meeting at 8.40pm (for 5 minutes) in accordance with clause 47 of the Code of Meeting Practice.

 

The meeting was adjourned at 8.40pm and was resumed at 8.45pm.

 

Motion of Dissent

RESOLUTION: (Belleli/Andrews) that the Chairperson’s ruling that the Mayor, Cr Matson’s, statement was misinterpreted and that Cr Matson had nothing to apologise for, be dissented to.

 

The Mayor, Cr Matson, indicated that he had not mentioned any Councillors’ names and was happy to indicate that it was not his intent to make reference to any particular Councillor.

 

Cr Belleli asked Cr Matson again to withdraw his comment that ‘Councillors interfere with planning officers’.

 

Cr Matson withdrew his reference to Councillors ‘interfering’ with planning officers.

 

AMENDMENT: (Notley-Smith/Smith) CARRIED AND BECAME THE MOTION.

 

A DIVISION was taken and the names of the Councillors voting FOR and AGAINST were as follows:

 

FOR

AGAINST

Councillor Belleli

Councillor Andrews

Councillor Hughes

Councillor Bowen

Councillor Matson

Councillor Matthews

Councillor Nash

Councillor Stevenson

Councillor Notley-Smith

Councillor White

Councillor Procopiadis

Councillor Woodsmith

Councillor Smith

 

Total (7)

Total (6)

 

MOTION: (Notley-Smith/Smith) CARRIED – SEE RESOLUTION.

 

A DIVISION was taken and the names of the Councillors voting FOR and AGAINST were as follows:

 

FOR

AGAINST

Councillor Belleli

Councillor Andrews

Councillor Hughes

Councillor Bowen

Councillor Matson

Councillor Matthews

Councillor Nash

Councillor Stevenson

Councillor Notley-Smith

Councillor White

Councillor Procopiadis

 

Councillor Smith

 

Councillor Woodsmith

 

Total (8)

Total (5)

 

 

 

D103/11   Development Application Report - 3 Edgecliffe Avenue, South Coogee (DA/1046/2010)

 

 

 

 

 

PL123/11

Having declared an interest in this matter earlier in the meeting, Cr Procopiadis left the meeting during the debate and the vote on the matter.

 

Cr Stevenson also left the meeting at this point (9.14pm) and did not return.

 

RESOLUTION: (Matthews/White) -

 

A.     That Council supports the objections under State Environmental Planning Policy No. 1 – Development Standard in respect to non-compliance with Clauses 20B of Randwick Local Environmental Plan 1998, relating to Minimum Allotment Sizes, on the grounds that the proposed development complies with the objectives of the above clauses, and will not adversely affect the amenity of the locality, and that the Department of Planning be advised accordingly.

 

B.     That Council, as the consent authority, grants development consent under Sections 80 and 80A of the Environmental Planning and Assessment Act 1979, as amended, to Development Application No. 1046/2010 for the demolition of the existing house and garage and the subdivision of the land in two lots and the erection of two detached dwellings at No. 3 Edgecliffe Avenue, South Coogee, subject to the following conditions:

 

GENERAL CONDITIONS

The development must be carried out in accordance with the following conditions of consent.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of environmental amenity.

 

Approved Plans & Supporting Documentation

1.       The development must be implemented substantially in accordance with the plans and supporting documentation listed below and endorsed with Council’s approved stamp, except where amended by Council in red and/or by other conditions of this consent:

 

Plan

Drawn by

Dated

Received

A1 01a- Site Analysis

Avril Jackson

25/11/10

26/11/10

A1 02b- Lowe Ground Floor Plan

Avril Jackson

15/04/11

15/04/11

A1 03b- Ground Floor Plan

Avril Jackson

15/04/11

15/04/11

A1 04b – First Floor Plan

Avril Jackson

15/04/11

15/04/11

A1 05b – Roof Plan

Avril Jackson

15/04/11

15/04/11

A1 06b – Site Plan

Avril Jackson

15/04/11

15/04/11

A1 07b – North and South Elevations, Sections A-A and B-B

Avril Jackson

15/04/11

15/04/11

A1 08b – East/ West Elevations

Avril Jackson

15/04/11

15/04/11

A1 09a – Subdivision Plan

Avril Jackson

25/11/10

26/11/10

A1 10a – Shadow Diagram

Avril Jackson

25/11/10

26/11/10

 

BASIX Certificate

No.

Dated

Received

85880478

 

26/11/10

26/11/10

 

Amendments of Plans and Documentation

2.       The roof terrace area for both dwellings must be reduced in size such that the trafficable area and the balustrade stand no closer than 1.5 metres from the roof edge.

 

3.       Window W108 to the dining room of the proposed of eastern dwelling must be provided with either a balustrade or fixed pane of glass to ensure that the non-trafficable area directly adjoining the window, which is labelled as “roof” on drawing A1 04b, is not accessible.

 

4.       External Colours, Materials & Finishes

a)   The colours, materials and finishes of the external surfaces are to be compatible with the existing building and adjacent development to maintain the integrity and amenity of the building and the streetscape.

 

External materials, finishes and colours of the building are required to match, as closely as possible, the existing building and any metal roof sheeting is to be pre-painted (e.g. Colourbond) to limit the level of reflection and glare.

 

b)   The sandstone that is currently contained within the existing building on the subject site shall be recycled wherever possible in the proposed development; in particular it should be included in the front facade of the dwellings.

 

c)   Details of the proposed colours, materials and textures (i.e. a schedule and brochure/s or sample board) are to be submitted to and approved by Council’s Manager Development Assessments prior to issuing a construction certificate for the development.

 

5.       Street and unit numbering must be provided to the premises in a prominent position, in accordance with the Australia Post guidelines and AS/NZS 4819 (2003) to the satisfaction of Council, prior to an occupation certificate being issued for the development.

 

In this regard, an Application must be submitted to and approved by Council’s Director of City Planning, together with the required fee, for the allocation of appropriate street and unit numbers for the development, prior to issuing an occupation certificate.

 

REQUIREMENTS BEFORE A CONSTRUCTION CERTIFICATE CAN BE ISSUED

The following conditions of consent must be complied with before a ‘Construction Certificate’ is issued by either an Accredited Certifier or Randwick City Council.  All necessary information to demonstrate compliance with the following conditions of consent must be included in the documentation for the construction certificate.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent conditions and to achieve reasonable levels of environmental amenity.

 

Consent Requirements

6.       The requirements and amendments detailed in the ‘General Conditions’ must be complied with and be included in the construction certificate plans and associated documentation.

 

Section 94A Development Contributions

7.       In accordance with Council’s Section 94A Development Contributions Plan effective from 2 July 2007, a Quantity Surveyor’s Report that calculates the estimated cost of the approved development must be submitted to Council for approval prior to the issuing of a construction certificate. A monetary levy of 1% based on the cost of works in the approved Quality Surveyor’s Report, must be paid in cash, bank cheque or by credit card prior to a construction certificate being issued for the proposed development.  The development is subject to an index to reflect quarterly variations in the Consumer Price Index (CPI) from the date of Council’s determination to the date of payment.

 

Council’s Section 94A Development Contribution Plans may be inspected at the Customer Service Centre, Administrative Centre, 30 Frances Street, Randwick or at www.randwick.nsw.gov.au.

 

8.       Prior to release of the Plan of Subdivision the applicant shall provide Council with a subdivider/developer certificate for the proposed lots.  The certificate is obtained from Sydney Water.

 

9.       A formal subdivision certificate application must be submitted to Council for approval of the subdivision of subject site and the two proposed lots must be registered with the Land and Property Management Authority, prior to the issuing of a construction certificate for the works relating to the construction of the new dwellings.

 

Compliance with the Building Code of Australia

10.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that all building work must be carried out in accordance with the provisions of the Building Code of Australia (BCA).  Details of compliance with the BCA are to be included in the construction certificate application.

 

Structural Adequacy

11.     Certificate of Adequacy supplied by a professional engineer shall be submitted to the certifying authority (and the Council, if the Council is not the certifying authority), certifying the structural adequacy of the existing structure to support the upper floor addition.

 

Long Service Levy Payments

12.     The required Long Service Levy payment, under the Building and Construction Industry Long Service Payments Act 1986, must be forwarded to the Long Service Levy Corporation or the Council, in accordance with Section 109F of the Environmental Planning & Assessment Act 1979.

 

At the time of this development consent, Long Service Levy payment is applicable on building work having a value of $25,000 or more, at the rate of 0.35% of the cost of the works.

 

BASIX Requirements

13.     In accordance with section 80A(11) of the Environmental Planning & Assessment Act 1979 and clause 97A of the Environmental Planning & Assessment Regulation 2000, the requirements and commitments contained in the relevant BASIX Certificate must be complied with.

 

The required commitments listed and identified in the BASIX Certificate must be included on the construction certificate plans, specifications and associated documentation, to the satisfaction of the Certifying Authority.

 

The design of the building must not be inconsistent with the development consent and any proposed variations to the building to achieve the BASIX commitments may necessitate a new development consent or amendment to the existing consent to be obtained, prior to a construction certificate being issued.

 

Smoke Alarms

14.     Smoke alarms are required to be installed in each Class 1 building or dwelling in accordance with the relevant provisions of Part 3.7.2 of the B.C.A. – Housing Provisions.

 

Smoke alarms must comply with AS3786 – Smoke alarms and be connected to the consumer mains electric power supply and provided with a battery back-up. Details of compliance are to be included in the construction certificate.

 

15.     The chimney flue is to extend no less than 600mm above the ridgeline to comply with the relevant AS/NZS 2918.2001, Domestic Solid Fuel Burning.

 

The following conditions are applied to provide adequate security against damage to Council’s infrastructure:

16.     The following damage / civil works security deposit requirement is to be complied with prior to a construction certificate being issued for the development, as security for making good any damage caused to the roadway, footway, verge or any public place; or as security for completing any public work; and for remedying any defect on such public works, in accordance with section 80A(6) of the Environmental Planning and Assessment Act 1979:

 

a)   $5000.00   -      Damage / Civil Works Security Deposit

 

The damage/civil works security deposit may be provided by way of a cash or cheque with the Council and is refundable upon:

 

§  A satisfactory inspection by Council that no damage has occurred to the Council assets such as roadway, kerb, guttering, drainage pits footway, or verge; and

§  Completion of the civil works as conditioned in this development consent by Council.

 

The applicant is to advise Council, in writing, of the completion of all building works and/or obtaining an occupation certificate, if required.

 

The following conditions are applied to provide adequate provisions for access, transport and infrastructure:

17.     All external civil work to be carried out on Council property (including the installation and repair of roads, footpaths, vehicular crossings, kerb and guttering and drainage works), must be carried out in accordance with Council’s Policy for “Vehicular Access and Road and Drainage Works” and the following requirements:

 

a)   All work on Council land must be carried out by Council, unless specific written approval has been obtained from Council to use non-Council contractors.

 

b)   Details of the proposed civil works to be carried out on Council land must be submitted to Council in a Pre-paid Works Application Form, prior to issuing an occupation certificate, together with payment of the relevant fees.

 

c)   If it is proposed to use non-Council contractors to carry out the civil works on Council land, the work must not commence until the written approval has been obtained from Council and the work must be carried out in accordance with the conditions of consent, Council’s design details and payment of a Council design and supervision fee.

 

d)   The civil works must be completed in accordance with Council’s conditions of consent and approved design and construction documentation, prior to occupation of the development, or as otherwise approved by Council in writing.

 

The following conditions are applied to provide adequate consideration for service authority assets:

 

18.     A public utility impact assessment must be carried out on all public utility services on the site, roadway, nature strip, footpath, public reserve or any public areas associated with and/or adjacent to the development/building works and include relevant information from public utility authorities and exploratory trenching or pot-holing, if necessary, to determine the position and level of service.

 

19.     The applicant must meet the full cost for telecommunication companies, gas providers, Energy Australia and Sydney Water to adjust/repair/relocate their services as required.  The applicant must make the necessary arrangements with the service authority.

 

20.     A Section 73 Compliance Certificate under the Sydney water Act 1994 must be obtained from Sydney Water Corporation.

 

Application must be made through an authorised Water Servicing Coordinator. Please refer to the Building Developing and Plumbing section of the website www.sydneywater.com.au then refer to “Water Servicing Coordinator” under Developing Your Land” or telephone 13 20 92 for assistance.

 

Following application a “Notice of Requirements” will advise of water and sewer infrastructure to be built and charges to be paid. Please make early contact with the Coordinator, since building of water/sewer infrastructure can be time consuming and may impact on other services and building, driveway or landscape design.

 

The Notice must be issued to the Principal Certifying Authority prior to the construction certificate being issued.

The Section 73 Certificate must be submitted to the Principal Certifying Authority prior to occupation of the development.

 

The following conditions are applied to provide adequate provisions for drainage and associated infrastructure:

21.     Generally all site stormwater shall be piped to a sediment/silt arrester pit that drains to an infiltration area with a minimum 5 m2 base area. An overflow pipe shall be provided from the silt arrestor pit that drains to Council's kerb and gutter.

 

The location and details of the proposed internal stormwater pipelines, silt arrestor pit and the infiltration area shall be submitted to and approved by the certifying authority prior to a construction certificate being issued for the development. A copy of the plans shall be forwarded to Council, prior to a construction certificate being issued, if Council is not the certifying authority.

 

Notes:

 

a.   The sediment/silt arrestor pit shall be constructed:

 

i.        within the site at or near the street boundary.

i.        with a child proof and corrosion resistant fastening system (e.g. spring loaded jay-bolt).

ii.       with a minimum of 4 x 90 mm diameter weep holes (preferably located in the walls of the pit at the floor level) and with a suitable geotextile material with a high filtration rating located around the weep holes.

iii.       with the pit floor being a minimum 300mm below the invert level of the outlet pipelines.

iv.      with a galvanised heavy duty screen (Lysaght RH3030 Maximesh or similar) located over the outlet pipes draining to the infiltration pit and the kerb. (Similar to a Mascot GRC stormwater discharge control pit, product code DS3SDC).

 

b.     The infiltration/rubble pit shall:

  

i.   have a minimum 300 mm of soil cover (600 mm where the pit is located under a garden/landscaping area).

 

ii.   be located a minimum of 3.0 metres from the dwelling or other structure (closer if a structural engineer certifies that the infiltration area will not adversely affect the structure) and 2.1 metres from the adjacent side or rear boundaries.

 

iii.  be constructed with a minimum 200 mm thick layer of 20 mm basalt/blue metal (or similar) that is wrapped in a suitable geotextile material covering with a high filtration rating (Geofabrics Bidim "A" range of filtration fabrics or equivalent). A suitable means of dispersing the stormwater over the area of infiltration is to be constructed.

 

Note:  other equivalent methods of infiltration may be adopted.

 

iv.  have a minimum base area of  5.0 square metres (m2).

 

The outlet from the silt arrestor pit to the infiltration area shall be located at least 50 mm below the outlet from the silt arrestor pit to the kerb and gutter.

 

c.     The requirement for an infiltration/rubble pit will not be enforced should the underground soil conditions preclude the construction of the infiltration pit (eg rock is located within 300 mm of the base of the infiltration area). If the infiltration/rubble pit is not constructed then all site stormwater shall be discharged to the kerb and gutter via a sediment/silt arrestor pit (as detailed in note a. above).

 

All works shall be to the satisfaction of the certifying authority.

 

d.     The overflow pipe/s from any rainwater tank/s shall be directed into the infiltration area.

 

22.     The infiltration areas/Absorption Trenches must be designed in accordance with "Section 8.5 ABSORPTION TRENCHES" as stipulated in Randwick City Council's Private Stormwater Code.

 

23.     As the above site may encounter groundwater/seepage water within the depth of the basement excavation, the basement carpark or similar structures are to be suitably tanked and waterproofed. A Structural Engineer\Geotechnical Engineer shall certify the tanking & waterproofing has been carried out to an acceptable standard, to the satisfaction of the certifying authority. A copy of the certification is to be forwarded to Council.

 

Notes:

a)  Any subsoil drainage (from planter boxes etc) is to be disposed of within the site and is not to be discharged to Council’s kerb & gutter and/or underground drainage system.

 

b)  Adequate provision is to be made for the ground water to drain around the basement carpark (to ensure that the basement will not dam or slow the movement of the ground water through the development site).

 

24.      Any seepage water must be drained directly into an absorption pit within the site. Seepage water must not be drained from the site.

 

The following conditions are applied to provide adequate provisions for landscaping and to maintain reasonable levels of environmental amenity:

25.      Landscaping shall be provided to the site to enhance its amenity and reduce the impact of the development upon neighbouring properties. A landscape plan shall be submitted to and approved by the Director of Planning & Community Development, in accordance with section 80A (2) of the Environmental Planning and Assessment Act 1979, prior to a construction certificate being issued.

 

26.     Landscaped areas must contain a predominance of species that require minimal watering once established or species with water needs that match rainfall and drainage conditions.

 

27.     The landscaping shall be installed in accordance with the approved documentation prior to the issue of a final occupation certificate and shall be maintained in accordance with those plans.

 

28.     The naturestrip upon Council's footway shall be excavated to a depth of 150mm, backfilled with topsoil equivalent with 'Organic Garden Mix' as supplied by Australian Native Landscapes, and re-turfed with Kikuyu Turf or similar. Such works shall be installed prior to the issue of a final Occupation Certificate.

 

29.     The naturestrip upon Council's footway shall be maintained by the applicant in accordance with Council guidelines. Such maintenance shall include, but not be limited to, watering, mowing, fertilising, and the removal of weeds.

 

30.     In order to visually 'soften' the expanses of hard pavement, brick unit pavers, stencilled concrete or similar shall be used throughout the driveway areas on the site. Such details shall be shown on the detailed engineering documentation and shall include all structural design details including pavement/subgrade thickness.

 

Street Trees

31.     The applicant must remove and dispose of (at their own cost) the two small Phoenix canariensis (Canary Island Date Palms) on Council’s Edgecliffe Avenue nature strip, during excavations associated with the proposed vehicle crossings as shown, and must satisfy themselves as to the location of all site services, prior to the commencement of any works on public property.

 

32.     The applicant shall also submit a total payment of $214.50 (including GST) to Council, being the cost for Council to supply and install 2 x 25 litre street trees, Banksia integrifolia (Coastal Banksia’s) being one each in line with both the eastern and western site boundaries.

 

The contribution shall be paid into Tree Amenity Income at the Cashier on the Ground Floor of the Administrative Centre, prior to a Construction Certificate being issued for the development.

 

The applicant shall contact Council’s Landscape Development Officer on 9399-0613, giving at least four working weeks notice to arrange for the replacement street trees upon completion of all site works.

 

REQUIREMENTS PRIOR TO THE COMMENCEMENT OF ANY WORKS

The following conditions of consent must be complied with prior to the commencement of any works on the site.  The necessary documentation and information must be provided to the Council or the ‘Principal Certifying Authority’, as applicable.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of public health, safety and environmental amenity.

 

Construction Certificate, Principal Certifying Authority & Commencement of Works

33.     Prior to the commencement of any building works, the following requirements must be complied with:

 

a)     a Construction Certificate must be obtained from the Council or an accredited certifier, in accordance with the provisions of the Environmental Planning & Assessment Act 1979.

 

A copy of the construction certificate, the approved development consent plans and consent conditions must be kept on the site at all times and be made available to the Council officers and all building contractors for assessment.

 

b)     a Principal Certifying Authority (PCA) must be appointed to carry out the necessary building inspections and to issue an occupation certificate; and

 

c)     a principal contractor must be appointed for the building work, or in relation to residential building work, an owner-builder permit may be obtained in accordance with the requirements of the Home Building Act 1989, and the PCA and Council are to be notified accordingly; and

 

d)     the principal contractor must be advised of the required critical stage inspections and other inspections to be carried out, as specified by the Principal Certifying Authority; and

 

e)     at least two days notice must be given to the Council, in writing, prior to commencing any works.

 

In relation to residential building work, the principal contractor must be the holder of a contractor licence, in accordance with the provisions of the Home Building Act 1989.

The following conditions are applied to provide adequate provisions for future civil works in the road reserve:

34.     The Council’s Department of Asset & Infrastructure Services has inspected the above site and have determined that the design alignment level at the property boundary for driveways, access ramps and pathways or the like, must be as follows:

 

Western Dwelling Levels:

Western Pedestrian Entrance - RL 47.95

Eastern Pedestrian Entrance – RL 47.15

 

Driveway Entrance – Western Edge – RL 47.70

Eastern Edge – RL 47.35

 

Eastern Dwelling Levels:

Western Pedestrian Entrance – RL 47.10

Eastern Pedestrian Entrance – RL 46.35

 

Driveway Entrance – Western Edge – RL 46.90

Eastern Edge – RL 46.60

 

Note: Garage slab level at proposed roller door location is to be lowered to RL 46.80

 

Refer to Dwg No 02 Rev- a, dated 25.11.2010 by Avril Jackson for B.M on kerb (RL 45.75)

 

35.     The design alignment levels issued by Council must be indicated on the building plans for the construction certificate. The design alignment level at the street boundary, as issued by the Council, must be strictly adhered to.

 

36.     The above alignment levels and the site inspection by Council’s Development Engineering Section have been issued at a prescribed fee of $1075.00 calculated at $44.00 (inclusive of GST) per metre of site frontage. This amount is to be paid to Council prior to a construction certificate being issued for the development.

 

37.     The top of footings of any structures constructed on the boundary alignment must be at least 150mm below the alignment level as specified above. 

 

Home Building Act 1989

38.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, the requirements of the Home Building Act 1989 must be complied with.

 

Details of the Licensed Building Contractor and a copy of the relevant Certificate of Home Warranty Insurance or a copy of the Owner-Builder Permit (as applicable) must be provided to the Principal Certifying Authority and Council, in writing.

 

Dilapidation Reports

39.     A dilapidation report prepared by a professional engineer, building surveyor or other suitably qualified independent person must be submitted to the satisfaction of the Principal Certifying Authority prior to commencement of any demolition, excavation or building works, in the following cases:

 

§  excavations for new dwellings, additions to dwellings, swimming pools or the like which are proposed to be located within the zone of influence of the footings of any dwelling, associated garage or other substantial structure located upon an adjoining premises,

§  new dwellings or additions to dwellings sited up to shared property boundaries (e.g. additions to a semi-detached dwelling or terraced dwellings),

§  excavations for new dwellings, additions to dwellings, swimming pools or the like which are within rock and may result in vibration and or potential damage to any dwelling, associated garage or other substantial structure located upon an adjoining premises, as otherwise may be required by the Principal Certifying Authority.

 

The report (including photographs) are required to detail the current condition and status of any dwelling, associated garage or other substantial structure located upon the adjoining premises, which may be affected by the subject works.  A copy of the dilapidation report is to be given to the owners of the premises encompassed in the report/s before commencing any works.

 

Construction Site Management Plan

40.     A Construction Site Management Plan must be developed and implemented prior to the commencement of any works. The construction site management plan must include the following measures, as applicable to the type of development:

 

§  location and construction of protective fencing / hoardings to the perimeter of the site;

§  location of site storage areas/sheds/equipment;

§  location of building materials for construction;

§  provisions for public safety;

§  dust control measures;

§  site access location and construction

§  details of methods of disposal of demolition materials;

§  protective measures for tree preservation;

§  provisions for temporary sanitary facilities;

§  location and size of waste containers/bulk bins;

§  details of proposed sediment and erosion control measures;

§  provisions for temporary stormwater drainage;

§  construction noise and vibration management;

§ construction traffic management details.

 

The site management measures must be implemented prior to the commencement of any site works and be maintained throughout the works, to the satisfaction of Council.

 

A copy of the Construction Site Management Plan must be provided to the Principal Certifying Authority and Council prior to commencing site works.  A copy must also be maintained on site and be made available to Council officers upon request.

 

Construction Noise & Vibration Management Plan

41.     Noise and vibration emissions during the construction of the building and associated site works must not result in damage to nearby premises or result in an unreasonable loss of amenity to nearby residents and the relevant requirements of the Protection of the Environment Operations Act 1997 and NSW DECC Guidelines must be satisfied at all times.

 

Noise and vibration from any rock excavation machinery, pile drivers and all plant and equipment must be minimised, by using appropriate plant and equipment, silencers and the implementation of noise management strategies.

 

A Construction Noise Management Plan, prepared in accordance with the NSW DECC Construction Noise Guideline by a suitably qualified person, is to be implemented throughout the works.  A copy of the strategy must be provided to the Principal Certifying Authority and Council prior to the commencement of works.

 

Temporary Site Fencing

42.     Temporary site safety fencing must be provided to the perimeter of the site (unless the site is separated from the adjoining land by an existing structurally adequate fence, having a minimum height of 1.5 metres).  Temporary site fences are to have a minimum height of 1.8 metres and be constructed of cyclone wire fencing, with geotextile fabric attached to the inside of the fence to provide dust control, or other material approved by Council.

 

Temporary site fences are to be structurally adequate, safe and be constructed in a professional manner and the use of poor quality materials or steel reinforcement mesh as fencing is not permissible.

 

Temporary fences must be in place prior to the commencement of any demolition, excavation or building works and be maintained throughout construction.

 

If it is proposed to locate any site fencing, hoardings or amenities upon any part of the footpath, nature strip or public place, a Local Approval application must be submitted to and approved by Council’s Health, Building & Regulatory Services before placing any item or article on the road, footpath or nature strip.

 

Sydney Water

43.     All building, plumbing and drainage work must be carried out in accordance with the requirements of the Sydney Water Corporation.

 

Prior to the commencement of excavation or building works, the approved Construction Certificate plans must be submitted to a Sydney Water Quick Check agent or Customer Centre, to determine whether the development will affect Sydney Water’s sewer and water mains, stormwater drains and/or easements, and if any further requirements need to be met. 

 

If suitable, the plans will be appropriately stamped. For Quick Check agent details please refer to Sydney Water’s web site at www.sydneywater.com.au and go to the Building, Developing and Plumbing, then Quick Check or Building and Renovating or telephone 13 20 92.

 

The principal certifying authority must ensure that a Quick Check Agent/Sydney Water has appropriately stamped the plans before commencing works.

 

Demolition Work Plan

44.     A Demolition Work Plan must be prepared for the development in accordance with Australian Standard AS2601-2001, Demolition of Structures and relevant environmental/occupational health and safety requirements.

 

The Demolition Work Plan must include the following information (as applicable):

 

§  The name, address, contact details and licence number of the Demolisher /Asbestos Removal Contractor

§  Details of hazardous materials (including asbestos)

§  Method/s of demolition (including removal of any asbestos)

§  Measures and processes to be implemented to ensure the health & safety of workers and community

§  Measures to be implemented to minimise any airborne dust and asbestos

§  Methods and location of disposal of any hazardous materials

§  Other relevant details, measures and requirements to be implemented

§  Date the demolition works will commence

§  Recycling, reuse and waste disposal of remediation materials

 

The Demolition Work Plan must be submitted to the Principal Certifying Authority (PCA), not less than two (2) working days before commencing any demolition work.  A copy of the Demolition Work Plan must be maintained on site and be made available to Council officers upon request.

 

If the work involves asbestos products or materials, a copy of the Demolition Work Plan must also be provided to Council not less than 2 days before commencing those works.

 

Notes:

 

It is the responsibility of the persons undertaking demolition work to obtain the relevant WorkCover licences and permits.

 

Refer to the conditions within the “Requirements During Construction & Site Work”, for further details and requirements relating to demolition work, removal of any asbestos and public safety.

 

REQUIREMENTS DURING CONSTRUCTION & SITE WORK

The following conditions of consent must be complied with during the demolition, excavation and construction of the development.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of public health, safety and environmental amenity during construction.

 

Demolition Work Requirements

45.     The proposed works and the removal, storage, handling and disposal of building materials must be carried out in accordance with the relevant requirements of WorkCover NSW, the NSW Department of Environment, Climate Change & Water and Randwick City Council policies, including:

 

§  Occupational Health & Safety Act 2000 & Regulations

§  WorkCover NSW Code of Practice for the Safe Removal of Asbestos

§  WorkCover NSW Guidelines and Codes of Practice

§  Australian Standard 2601 (2001) – Demolition of Structures

§  The Protection of the Environment Operations Act 1997 and Protection of the Environment Operations (Waste) Regulation 2005

§  Relevant DECCW/EPA Guidelines

§  Randwick City Council Asbestos Policy

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development section or a copy can be obtained from Council’s Customer Service Centre.

 

Removal of Asbestos Materials

46.     Any work involving the demolition, storage or disposal of asbestos products and materials must be carried out in accordance with the following requirements:

 

§  Relevant Occupational Health & Safety legislation and WorkCover NSW requirements

§  Randwick City Council’s Asbestos Policy

§  A WorkCover licensed demolition or asbestos removal contractor must undertake removal of more than 10m2 of bonded asbestos (or as otherwise specified by WorkCover or relevant legislation).  Removal of friable asbestos material must only be undertaken by contractor that holds a current friable asbestos removal licence. A copy of the relevant licence must be provided to the Principal Certifying Authority.

§  On sites involving the removal of asbestos, a sign must be clearly displayed in a prominent visible position at the front of the site, containing the words ‘DANGER ASBESTOS REMOVAL IN PROGRESS’ and include details of the licensed contractor.

§  Asbestos waste must be stored, transported and disposed of in compliance with the Protection of the Environment Operations Act 1997 and the Protection of the Environment Operations (Waste) Regulation 2005. Details of the landfill site (which must be lawfully able to receive asbestos materials) must be provided to the Principal Certifying Authority.

§  A Clearance Certificate or Statement, prepared by a suitably qualified person (ie an occupational hygienist, licensed asbestos removal contractor, building consultant, architect or experienced licensed building contractor), must be provided to Council and the Principal certifying authority upon completion of the asbestos related works which confirms that the asbestos material have been removed appropriately and the relevant conditions of consent have been satisfied.

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development Section or a copy can be obtained from Council’s Customer Service Centre.

 

Site Signage

47.     A sign must be erected and maintained in a prominent position on the site for the duration of the works, which contains the following details:

 

§  name, address, contractor licence number and telephone number of the principal contractor, including a telephone number at which the person may be contacted outside working hours, or owner-builder permit details (as applicable)

§  name, address and telephone number of the Principal Certifying Authority,

§  a statement stating that “unauthorised entry to the work site is prohibited”.

 

Sediment & Erosion Control

48.     Sediment and erosion control measures, must be implemented throughout the site works in accordance with the manual for Managing Urban Stormwater – Soils and Construction, published by Landcom, to Council’s satisfaction.  Details are to be included in the Construction Site Management Plan.

 

Public Safety & Site Management

49.     Public safety and convenience must be maintained at all times during demolition, excavation and construction works and the following requirements must be complied with:

 

a)     Building materials, sand, soil, waste materials, construction equipment or other activities must not be placed upon the footpath, roadway or nature strip at any time and the footpath, nature strip and road must be maintained in a clean condition and free from any obstructions, soil and debris at all times.

 

b)     Stockpiles of soil, sand, aggregate or other materials must not be located on any footpath, roadway, nature strip, drainage line or any public place and the stockpiles must be protected with adequate sediment control measures.

 

c)     Building operations such as brick cutting, washing tools or equipment and mixing mortar are not permitted on public footpaths, roadways, nature strips, in any public place or any location which may lead to the discharge of materials into the stormwater drainage system.

 

d)     Bulk bins/waste containers must not be located upon the footpath, roadway or nature strip at any time without the prior written approval of the Council.  Applications to place a waste container in a public place can be made to Council’s Health, Building and Regulatory Services department.

 

e)     Any part of Council’s road, footway or nature strip which is damaged as a result of the work must be repaired or replaced to Council’s satisfaction.

 

f)     Temporary safety fencing is to be provided to any swimming pools under construction, pending the completion of all building work and the pool must not be filled until a fencing inspection has been carried out and approved by the principal certifying authority.

 

Excavations, Back-filling & Retaining Walls

50.     All excavations and backfilling associated with the proposed works must be executed safely in accordance with appropriate professional standards and excavations must be properly guarded and supported to prevent them from being dangerous to life, property or buildings.

 

Retaining walls, shoring or piling must be provided to support land which is excavated in association with the erection or demolition of a building, to prevent the movement of soil and to support the adjacent land and buildings, if the soil conditions require it.  Adequate provisions are also to be made for drainage.

 

Details of proposed retaining walls, shoring or piling are to be submitted to and approved by the Principal Certifying Authority for the development prior to commencing such excavations or works.

 

Support of Adjoining Land

51.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 E of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that the adjoining land and buildings located upon the adjoining land must be adequately supported at all times.

 

a)    If the development involves an excavation that extends below the level of the base of the footings of a building on adjoining land, the person having the benefit of the development must, at the person’s own expense:

 

i)     protect and support the adjoining premises from possible damage from the excavation, and

ii)     where necessary, underpin the adjoining premises to prevent any such damage.

 

b)    The condition referred to in subclause a) does not apply if the person having the benefit of the development consent owns the adjoining land or the owner of the adjoining land has given consent in writing to that condition not applying.

 

52.     Prior to undertaking any demolition, excavation or building work in the following circumstances, a report must be obtained from a professional engineer which details the methods of support for the dwelling or associated structure on the adjoining land, to the satisfaction of the Principal Certifying Authority:

 

§  when undertaking excavation or building work within the zone of influence of the footings of a dwelling or associated structure that is located on the adjoining land;

§  when undertaking demolition work to a wall of a dwelling that is built to a common or shared boundary (eg. semi-detached or terrace dwelling);

§  when constructing a wall to a dwelling or associated structure that is located within 900mm of a dwelling located on the adjoining land.

 

The demolition, excavation and building work and the provision of support to the dwelling or associated structure on the adjoining land, must also be carried out in accordance with the abovementioned report, to the satisfaction of the Principal Certifying Authority.

 

Restriction on Working Hours

53.     Building, demolition and associated site works must be carried out in accordance with the following requirements:

 

Activity

Permitted working hours

All building, demolition and site work, including site deliveries (except as detailed below)

 Monday to Friday - 7.00am to 5.00pm

Saturday - 8.00am to 5.00pm

Sunday & public holidays - No work permitted

Excavating of rock, use of jack-hammers, pile-drivers, vibratory rollers/compactors or the like

 Monday to Friday - 8.00am to 5.00pm

 Saturday - No work permitted

Sunday & public holidays - No work permitted

 

An application to vary the abovementioned hours may be submitted to Council’s Manager Health, Building & Regulatory Services for consideration and approval to vary the specified hours may be granted in exceptional circumstances and for limited occasions (e.g. for public safety, traffic management or road safety reasons).  Any applications are to be made on the standard application form and include payment of the relevant fees and supporting information.  Applications must be made at least 10 days prior to the date of the proposed work and the prior written approval of Council must be obtained to vary the standard permitted working hours.

 

Inspections During Construction

54.     The building works must be inspected by the Principal Certifying Authority, in accordance with sections 109 E (3) of the Environmental Planning & Assessment Act 1979 and clause 162A of the Environmental Planning & Assessment Regulation 2000, to monitor compliance with the relevant standards of construction, Council’s development consent and the construction certificate.

 

The Principal Certifying Authority must specify the relevant stages of construction to be inspected and a satisfactory inspection must be carried out, to the satisfaction of the Principal Certifying Authority, prior to proceeding to the subsequent stages of construction or finalisation of the works (as applicable).

 

REQUIREMENTS PRIOR TO THE ISSUE OF AN OCCUPATION CERTIFICATE

The following conditions of consent must be complied with prior to the ‘Principal Certifying Authority’ issuing an ‘Occupation Certificate’.

 

Note:  For the purpose of this consent, any reference to ‘occupation certificate’ shall also be taken to mean ‘interim occupation certificate’ unless otherwise stated.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent and to maintain reasonable levels of public health, safety and amenity.

 

Occupation Certificate Requirements

55.     An Occupation Certificate must be obtained from the Principal Certifying Authority prior to any occupation of the building work encompassed in this development consent (including alterations and additions to existing buildings), in accordance with the relevant provisions of the Environmental Planning & Assessment Act 1979.

 

An Occupation Certificate must not be issued for the development if the development is inconsistent with the development consent.  The relevant requirements of the Environmental Planning & Assessment Act 1979 and conditions of development consent must be satisfied prior to the issuing of an occupation certificate.

 

The following conditions are applied to provide adequate provisions for access, transport and infrastructure:

56.     Prior to the issuing of an Occupation Certificate the applicant must meet the full cost for Council or a Council approved contractor to:

 

a)   Construct new concrete vehicular crossings and laybacks at kerb opposite the new vehicular entrances to the sites.

 

b)   Remove any redundant concrete vehicular crossing and layback and to reinstate the area with concrete footpath, turf and integral kerb and gutter to Council's specification.

 

c)   Construct a concrete footpath along the l site frontage.  Any unpaved areas on the nature strip must be turfed and landscaped to Council’s specification.

 

57.     The applicant must meet the full cost for Council or a Council approved contractor to repair/replace any damaged sections of Council's footpath, kerb & gutter, nature strip etc which are due to building works being carried out at the above site. This includes the removal of cement slurry from Council's footpath and roadway.

 

58.     The applicant shall meet all costs associated with removing the Council nature strip and timber retaining wall along the site frontage and construction of a new block retaining wall opposite the eastern side boundary to, Council’s satisfaction, with any necessary guardrails, to a qualified structural engineers details. This shall include the cost to relocate any public utility services.

 

Note:  Plans submitted for the construction certificate are to show the location of the block retaining wall as mentioned above as well as its structural details.

 

The following conditions are applied to provide adequate consideration ofor service authority assets:

59.     The applicant shall meet the full cost of the overhead power lines and telecommunication cables located in the vicinity of the development site to be relocated underground and all redundant power poles to be removed. The applicant shall liaise directly with the relevant service utility authorities to organise for the wires/cables to be relocated. All wires cables must be relocated underground to the satisfaction of the relevant service utility authority prior to the issuing of an occupation certificate for the development.

 

Road/Asset Opening Permit

60.     A Road / Asset Opening Permit must be obtained from Council prior to carrying out any works within or upon a road, footpath, nature strip or in any public place, in accordance with section 138 of the Roads Act 1993 and all of the conditions and requirements contained in the Road / Asset Opening Permit must be complied with.

 

The owner/builder must ensure that all works within or upon the road reserve, footpath, nature strip or other public place are completed to the satisfaction of Council, prior to the issuing of a final occupation certificate for the development.

 

For further information, please contact Councils Road / Asset Opening Officer on 9399 0691 or 9399 0999.

 

The following conditions are applied to provide adequate provisions for waste management:

61.     Prior to the Principal Certifying Authority issuing an occupation certificate for the proposed development the applicant is to contact Council’s Manager of Waste in regards to meeting Council’s requirements for waste services to the two new residences.

 

The following conditions are applied to satisfy the provisions of Council’s environmental plans, policies and codes for subdivision works:

62.     The conditions of development consent must be satisfied and all public roads and reserves must be satisfactorily restored prior to the finalisation of the subdivision.

 

Tree Management

63.     The applicant shall submit a total payment of $379.50 to Council,

 

a.       Being the cost for Council to supply and install 2 x 45 litre street trees (Banksia integrifolia, Coastal Banksia’s) on the eastern side of the proposed driveway at the completion of all works ($345.00 + GST)

 

The contribution shall be paid at the Cashier on the Ground Floor of the Administrative Centre prior to an occupation certificate being issued for the development.

 

64.     The following trees shall be removed as part of the proposal, subject to the planting of 2 x 45 litre broad canopied replacement trees (not palms) within the site, comprising one within each proposed dwelling. The species selected shall be those that will attain a minimum height of 6 metres at maturity.

 

a.   Two Phoenix canariensis (Canary Island Date Palms) on the nature strip

 

b.   Three Archontophoenix cunninghamiana (Bangalow Palms) along the northern boundary

Advisory Conditions

The applicant is to advise Council in writing and/or photographs of any signs of existing damage to the Council roadway, footway, or verge prior to the commencement of any building/demolition works.

 

MOTION: (Smith/Woodsmith) -

 

A.     That Council does not support the objections under State Environmental Planning Policy No. 1 – Development Standard in respect to non-compliance with Clauses 20B of Randwick Local Environmental Plan 1998, relating to Minimum Allotment Sizes, on the grounds that the proposed development does not comply with the objectives of the above clauses, and will adversely affect the amenity of the locality, and that the Department of Planning be advised accordingly.

 

B.     That Council, as the consent authority, refuses development consent under Sections 80 and 80A of the Environmental Planning and Assessment Act 1979, as amended, to Development Application No. 1046/2010 for the demolition of the existing house and garage and the subdivision of the land in two lots and the erection of two detached dwellings at No. 3 Edgecliffe Avenue, South Coogee, for the following reasons:

 

1.     the minimum allotment size does not comply with the objectives of the LEP.

 

2.             the proposal does not comply with the DCP, LEP and development standards in relation to;

 

·                building setback;

·                site setback;

·                driveway width;

·                the proposed location of the garage and carport in front of the building line;

·                proposed frontages; and

·                the proposed 60% occupation of the site (by the driveways, parking spaces and structures) which is 24% more than the development standard. LOST.

 

A DIVISION was taken and the names of the Councillors voting FOR and AGAINST were as follows:

 

FOR

AGAINST

Councillor Matson

Councillor Andrews

Councillor Notley-Smith

Councillor Belleli

Councillor Smith

Councillor Bowen

Councillor Woodsmith

Councillor Hughes

 

Councillor Matthews

 

Councillor Nash

 

Councillor White

Total (4)

Total (7)

 

MOTION: (Matthews/White) CARRIED – SEE RESOLUTION.

 

A DIVISION was taken and the names of the Councillors voting FOR and AGAINST were as follows:

 

FOR

AGAINST

Councillor Andrews

Councillor Matson

Councillor Belleli

Councillor Notley-Smith

Councillor Bowen

Councillor Smith

Councillor Hughes

Councillor Woodsmith

Councillor Matthews

 

Councillor Nash

 

Councillor White

 

Total (7)

Total (4)

 

Cr Procopiadis returned to the meeting (9.22pm).

 

 

D104/11   Development Application Report - 6 Sully Street, Coogee (DA/359/2011)

PL124/11

RESOLUTION: (Andrews/Mayor, Cr Matson) -

 

A.     That Council supports the objections under State Environmental Planning Policy No. 1 – Development Standards in respect to non-compliance with Clauses 20G of Randwick Local Environmental Plan 1998, relating to external wall height, on the grounds that the proposed development complies with the objectives of the above clauses, and will not adversely affect the amenity of the locality, and that the Department of Planning be advised accordingly.

 

B.     That Council, as the consent authority, grants development consent under Sections 80 and 80A of the Environmental Planning and Assessment Act 1979, as amended, to Development Application No. DA/359/2011 to carry out alterations and new first floor addition to the existing semi-detached dwelling house at 6 Sully Street, Randwick, subject to the following conditions:

 

DEVELOPMENT CONSENT CONDITIONS

 

GENERAL CONDITIONS

The development must be carried out in accordance with the following conditions of consent.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of environmental amenity.

 

Approved Plans & Supporting Documentation

1.       The development must be implemented substantially in accordance with the plans and supporting documentation listed below and endorsed with Council’s approved stamp, except where amended by Council in red and/or by other conditions of this consent:

 

Plan

Drawn by

Dated

Received

Job No: 7297/11 1 of 7

Cape Cod

13 July 2011

19 July 2011

Job No: 7297/11 2 of 7

Cape Cod

13 July 2011

19 July 2011

Job No: 7297/11 3 of 7

Cape Cod

13 July 2011

19 July 2011

Job No: 7297/11 4 of 7

Cape Cod

13 July 2011

19 July 2011

Job No: 7297/11 5 of 7

Cape Cod

13 July 2011

19 July 2011

Job No: 7297/11 6 of 7

Cape Cod

13 July 2011

19 July 2011

Job No: 7297/11 7 of 7

Cape Cod

13 July 2011

19 July 2011

 

BASIX Certificate

No.

Dated

Received

 

A112108

6 May 2011

17 May 2011

 

Amendment of Plans & Documentation

2.       The approved plans and documents must be amended in accordance with the following requirements:

 

a.       A privacy screen having a height of 1.8m above floor level must be provided to eastern and western sides of the upper level rear balcony.  The privacy screen must be constructed of metal or timber and the total area of any openings within the privacy screen must not exceed 25% of the area of the screen.  Alternatively, the privacy screen may be constructed with translucent, obscured, frosted or sandblasted glazing in a suitable frame.

 

b.       The following window must have a minimum sill height of 1.5m above floor level, or alternatively, the window is to be fixed and be provided with translucent, obscured, frosted or sandblasted glazing below this specified height:

 

·    The west facing part of the first floor bedroom window (W4). An amended BASIX certificate may be required.

 

REQUIREMENTS PRIOR TO THE ISSUE OF A CONSTRUCTION CERTIFICATE

The following conditions of consent must be complied with prior to the issue of a ‘Construction Certificate’ by either Randwick City Council or an Accredited Certifier.  All necessary information to demonstrate compliance with the following conditions of consent must be submitted with the construction certificate application.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent conditions and to achieve reasonable levels of environmental amenity.

 

Consent Requirements

3.       The requirements and amendments detailed in the ‘General Conditions’ must be complied with and be included in the construction certificate plans and associated documentation.

 

External Colours, Materials & Finishes

4.       The colours, materials and finishes of the external surfaces are to be consistent with the colour scheme received by Council on 17 May 2011 and be compatible with the adjacent development to maintain the integrity and amenity of the building and the surrounding developments.

 

Section 94A Development Contributions

5.       In accordance with Council’s Section 94A Development Contributions Plan effective from 2 July 2007, based on the development cost of $199,202.00 the following applicable monetary levy must be paid to Council:   $996.00.

       

The levy must be paid in cash, bank cheque or by credit card prior to a construction certificate being issued for the proposed development. The development is subject to an index to reflect quarterly variations in the Consumer Price Index (CPI) from the date of Council’s determination to the date of payment.

 

Council’s Section 94A Development Contribution Plans may be inspected at the Customer Service Centre, Administrative Centre, 30 Frances Street, Randwick or at www.randwick.nsw.gov.au.

 

Compliance with the Building Code of Australia

6.       In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that all building work must be carried out in accordance with the provisions of the Building Code of Australia (BCA).  Details of compliance with the BCA are to be included in the construction certificate application.

 

Structural Adequacy

7.       Certificate of Adequacy supplied by a professional engineer shall be submitted to the certifying authority, certifying the structural adequacy of the existing structure to support the additional storey/upper floor addition.

 

Long Service Levy Payments

8.       The required Long Service Levy payment, under the Building and Construction Industry Long Service Payments Act 1986, must be forwarded to the Long Service Levy Corporation or the Council, in accordance with Section 109F of the Environmental Planning & Assessment Act 1979.

 

At the time of this development consent, Long Service Levy payment is applicable on building work having a value of $25,000 or more, at the rate of 0.35% of the cost of the works.

Security Deposits

9.       The following damage / civil works security deposit requirement must be complied with prior to a construction certificate being issued for the development, as security for making good any damage caused to the roadway, footway, verge or any public place; and as security for completing any public work; and for remedying any defect on such public works, in accordance with section 80A(6) of the Environmental Planning and Assessment Act 1979:

 

·           $600.00     -      Damage / Civil Works Security Deposit

 

The damage/civil works security deposit may be provided by way of a cash, cheque or credit card payment and is refundable upon a satisfactory inspection by Council upon the completion of the civil works which confirms that there has been no damage to Council's infrastructure.

 

The owner/builder is also requested to advise Council in writing and/or photographs of any signs of existing damage to the Council roadway, footway, or verge prior to the commencement of any building/demolition works.

 

To obtain a refund of relevant deposits, a Security Deposit Refund Form is to be forwarded to Council’s Director of City Services upon issuing of an occupation certificate or completion of the civil works.

 

Stormwater Drainage

10.     A surface water/stormwater drainage system must be provided in accordance with the following requirements, to the satisfaction of the Certifying Authority and details are to be included in the construction certificate:-

 

a)    Surface water/stormwater drainage systems must be provided in accordance with Part 3.1.2 of the Building Code of Australia (Volume 2);

 

b)    The surface water/stormwater must be drained and discharged to the street gutter or, subject to site suitability, the stormwater may be drained to a suitably designed absorption pit;

 

c)    Any absorption pits or soaker wells should be located not less than 3m from any adjoining premises and the stormwater must not be directed to any adjoining premises or cause a nuisance;

 

d)    External paths and ground surfaces are to be constructed at appropriate levels and be graded and drained away from the building and adjoining premises, so as not to result in the entry of water into the building, or cause a nuisance or damage to the adjoining premises;

 

e)    Details of any proposed drainage systems or works to be carried out in the road, footpath or nature strip must be submitted to and approved by Council before commencing these works.

 

BASIX Requirements

11.     In accordance with section 80A(11) of the Environmental Planning & Assessment Act 1979 and clause 97A of the Environmental Planning & Assessment Regulation 2000, the requirements and commitments contained in the relevant BASIX Certificate must be complied with.

 

The required commitments listed and identified in the BASIX Certificate must be included on the construction certificate plans, specifications and associated documentation, to the satisfaction of the Certifying Authority.

 

The design of the building must not be inconsistent with the development consent and any proposed variations to the building to achieve the BASIX commitments may necessitate a new development consent or amendment to the existing consent to be obtained, prior to a construction certificate being issued.

 

Energy & Water Efficiency

12.     The following energy efficiency and water saving measures are to be implemented in all new and upgraded building work and details included in the construction certificate:

 

a)    The consumption of water shall be minimised by the use of triple A rated water efficient plumbing fixtures (taps and shower roses) and water efficient dual flush toilets.

 

b)    New external timber or metal framed and brick veneer walls and roofs are to be provided with insulation (i.e. bulk insulation and a reflective building membrane/reflective sarking/foil insulation), having a minimum total thermal resistance R–value of 3.0 in roofs and 1.5 in external walls.  The insulation and reflective building membrane is to be installed in accordance with the relevant requirements of the Building Code of Australia and the manufacturers details.

 

c)    New hot water service pipes are to be provided with insulation and must also satisfy any relevant requirements of Building Code of Australia and AS 3500.

 

Smoke Alarms

13.     Smoke alarms are required to be installed in each Class 1 building or dwelling in accordance with the relevant provisions of Part 3.7.2 of the B.C.A. – Housing Provisions.

 

Smoke alarms must comply with AS3786 – Smoke alarms and be connected to the consumer mains electric power supply and provided with a battery back-up.  Details of compliance are to be included in the construction certificate.

 

REQUIREMENTS PRIOR TO THE COMMENCEMENT OF ANY WORKS

The following conditions of consent must be complied with prior to the commencement of any works on the site.  The necessary documentation and information must be provided to the Council or the ‘Principal Certifying Authority’, as applicable.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of public health, safety and environmental amenity.

 

Construction Certificate, Principal Certifying Authority & Commencement of Works

14.     Prior to the commencement of any building works, the following requirements must be complied with:

 

a)       a Construction Certificate must be obtained from the Council or an accredited certifier, in accordance with the provisions of the Environmental Planning & Assessment Act 1979.

 

A copy of the construction certificate, the approved development consent plans and consent conditions must be kept on the site at all times and be made available to the Council officers and all building contractors for assessment.

 

b)       a Principal Certifying Authority (PCA) must be appointed to carry out the necessary building inspections and to issue an occupation certificate; and

 

c)       a principal contractor must be appointed for the building work, or in relation to residential building work, an owner-builder permit may be obtained in accordance with the requirements of the Home Building Act 1989, and the PCA and Council are to be notified accordingly; and

 

d)       the principal contractor must be advised of the required critical stage inspections and other inspections to be carried out, as specified by the Principal Certifying Authority; and

 

e)       at least two days notice must be given to the Council, in writing, prior to commencing any works.

 

In relation to residential building work, the principal contractor must be the holder of a contractor licence, in accordance with the provisions of the Home Building Act 1989.

Home Building Act 1989

15.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, the requirements of the Home Building Act 1989 must be complied with.

 

Details of the Licensed Building Contractor and a copy of the relevant Certificate of Home Warranty Insurance or a copy of the Owner-Builder Permit (as applicable) must be provided to the Principal Certifying Authority and Council, in writing.

 

Dilapidation Reports

16.     A dilapidation report prepared by a professional engineer, building surveyor or other suitably qualified independent person must be submitted to the satisfaction of the Principal Certifying Authority prior to commencement of any demolition, excavation or building works, in the following cases:

 

·              excavations for new dwellings, additions to dwellings, swimming pools or the like which are proposed to be located within the zone of influence of the footings of any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

·              new dwellings or additions to dwellings sited up to shared property boundaries (e.g.  additions to a semi-detached dwelling or terraced dwellings),

·              excavations for new dwellings, additions to dwellings, swimming pools or the like which are within rock and may result in vibration and or potential damage to any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

·              as otherwise may be required by the Principal Certifying Authority.

 

The report (including photographs) are required to detail the current condition and status of any dwelling, associated garage or other substantial structure located upon the adjoining premises, which may be affected by the subject works.  A copy of the dilapidation report is to be given to the owners of the premises encompassed in the report/s before commencing any works.

 

Construction Noise & Vibration Management Plan

17.     Noise and vibration emissions during the construction of the building and associated site works must not result in damage to nearby premises or result in an unreasonable loss of amenity to nearby residents and the relevant requirements of the Protection of the Environment Operations Act 1997 and NSW DECC Guidelines must be satisfied at all times.

 

Noise and vibration from any rock excavation machinery, pile drivers and all plant and equipment must be minimised, by using appropriate plant and equipment, silencers and the implementation of noise management strategies.

 

A Construction Noise Management Plan, prepared in accordance with the NSW DECC Construction Noise Guideline by a suitably qualified person, is to be implemented throughout the works.  A copy of the strategy must be provided to the Principal Certifying Authority and Council prior to the commencement of works.

 

Temporary Site Fencing

18.     Temporary site safety fencing must be provided to the perimeter of the site (unless the site is separated from the adjoining land by an existing structurally adequate fence, having a minimum height of 1.5 metres).  Temporary site fences are to have a minimum height of 1.8 metres and be constructed of cyclone wire fencing, with geotextile fabric attached to the inside of the fence to provide dust control, or other material approved by Council.

 

Temporary site fences are to be structurally adequate, safe and be constructed in a professional manner and the use of poor quality materials or steel reinforcement mesh as fencing is not permissible.

 

Temporary fences must be in place prior to the commencement of any demolition, excavation or building works and be maintained throughout construction.

 

If it is proposed to locate any site fencing, hoardings or amenities upon any part of the footpath, nature strip or public place, a Local Approval application must be submitted to and approved by Council’s Health, Building & Regulatory Services before placing any item or article on the road, footpath or nature strip.

 

Construction Site Management Plan

19.     A Construction Site Management Plan must be developed and implemented prior to the commencement of any works. The construction site management plan must include the following measures, as applicable to the type of development:

 

·          location and construction of protective fencing / hoardings to the perimeter of the site;

·          location of site storage areas/sheds/equipment;

·          location of building materials for construction;

·          provisions for public safety;

·          dust control measures;

·          site access location and construction

·          details of methods of disposal of demolition materials;

·          protective measures for tree preservation;

·          provisions for temporary sanitary facilities;

·          location and size of waste containers/bulk bins;

·          details of proposed sediment and erosion control measures;

·          provisions for temporary stormwater drainage;

·          construction noise and vibration management;

·          construction traffic management details.

 

The site management measures must be implemented prior to the commencement of any site works and be maintained throughout the works, to the satisfaction of Council.

 

A copy of the Construction Site Management Plan must be provided to the Principal Certifying Authority and Council prior to commencing site works.  A copy must also be maintained on site and be made available to Council officers upon request.

 

Demolition Work Plan

20.     A Demolition Work Plan must be prepared for the development in accordance with Australian Standard AS2601-2001, Demolition of Structures and relevant environmental/occupational health and safety requirements.

 

The Demolition Work Plan must include the following information (as applicable):

·          The name, address, contact details and licence number of the Demolisher /Asbestos Removal Contractor

·          Details of hazardous materials (including asbestos)

·          Method/s of demolition (including removal of any asbestos)

·          Measures and processes to be implemented to ensure the health & safety of workers and community

·          Measures to be implemented to minimise any airborne dust and asbestos

·          Methods and location of disposal of any hazardous materials

·          Other relevant details, measures and requirements to be implemented

·          Date the demolition works will commence

·          Recycling, reuse and waste disposal of remediation materials

 

The Demolition Work Plan must be submitted to the Principal Certifying Authority (PCA), not less than two (2) working days before commencing any demolition work.  A copy of the Demolition Work Plan must be maintained on site and be made available to Council officers upon request.

 

If the work involves asbestos products or materials, a copy of the Demolition Work Plan must also be provided to Council not less than 2 days before commencing those works.

 

Notes

§  It is the responsibility of the persons undertaking demolition work to obtain the relevant WorkCover licences and permits.

§  Refer to the conditions within the “Requirements During Construction & Site Work”, for further details and requirements relating to demolition work, removal of any asbestos and public safety.

 

Sydney Water

21.     All building, plumbing and drainage work must be carried out in accordance with the requirements of the Sydney Water Corporation.

 

Prior to the commencement of excavation or building works, the approved Construction Certificate plans must be submitted to a Sydney Water Quick Check agent or Customer Centre, to determine whether the development will affect Sydney Water’s sewer and water mains, stormwater drains and/or easements, and if any further requirements need to be met. 

 

If suitable, the plans will be appropriately stamped.  For Quick Check agent details please refer to Sydney Water’s web site at www.sydneywater.com.au and go to the Building, Developing and Plumbing, then Quick Check or Building and Renovating or telephone 13 20 92.

 

The principal certifying authority must ensure that a Quick Check Agent/Sydney Water has appropriately stamped the plans before commencing works.

 

Public Utilities

22.     A Public Utility Impact Assessment must be carried out to identify all public utility services located on the site, roadway, nature strip, footpath, public reserve or any public areas associated with and/or adjacent to the building works.

 

Documentary evidence from the relevant public utility authorities confirming that their requirements have been or are able to be satisfied, must be submitted to the Principal Certifying Authority prior to the commencement of any works.

 

The owner/builder must make the necessary arrangements and meet the full cost for telecommunication companies, gas providers, Energy Australia, Sydney Water and other authorities to adjust, repair or relocate their services as required.

 

REQUIREMENTS DURING CONSTRUCTION & SITE WORK

The following conditions of consent must be complied with during the demolition, excavation and construction of the development.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of public health, safety and environmental amenity during construction.

 

Demolition Work Requirements

23.     The demolition of buildings and the removal, storage, handling and disposal of building materials must be carried out in accordance with the relevant requirements of WorkCover NSW, the NSW Department of Environment, Climate Change & Water and Randwick City Council policies, including:

 

·          Occupational Health & Safety Act 2000 & Regulations

·          WorkCover NSW Code of Practice for the Safe Removal of Asbestos

·          WorkCover NSW Guidelines and Codes of Practice

·          Australian Standard 2601 (2001) – Demolition of Structures

·          The Protection of the Environment Operations Act 1997 and Protection of the Environment Operations (Waste) Regulation 2005

·          Relevant DECCW/EPA Guidelines

·          Randwick City Council Asbestos Policy

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development section or a copy can be obtained from Council’s Customer Service Centre.

 

Removal of Asbestos Materials

24.     Any work involving the demolition, storage or disposal of asbestos products and materials must be carried out in accordance with the following requirements:

 

·          Relevant Occupational Health & Safety legislation and WorkCover NSW requirements

 

·          Randwick City Council’s Asbestos Policy

 

·          A WorkCover licensed demolition or asbestos removal contractor must undertake removal of more than 10m2 of bonded asbestos (or as otherwise specified by WorkCover or relevant legislation).  Removal of friable asbestos material must only be undertaken by contractor that holds a current friable asbestos removal licence.  A copy of the relevant licence must be provided to the Principal Certifying Authority.

 

·          On sites involving the removal of asbestos, a sign must be clearly displayed in a prominent visible position at the front of the site, containing the words ‘DANGER ASBESTOS REMOVAL IN PROGRESS’ and include details of the licensed contractor.

 

·          Asbestos waste must be stored, transported and disposed of in compliance with the Protection of the Environment Operations Act 1997 and the Protection of the Environment Operations (Waste) Regulation 2005.  Details of the landfill site (which must be lawfully able to receive asbestos materials) must be provided to the Principal Certifying Authority.

 

·          A Clearance Certificate or Statement, prepared by a suitably qualified person (ie an occupational hygienist, licensed asbestos removal contractor, building consultant, architect or experienced licensed building contractor), must be provided to Council and the Principal certifying authority upon completion of the asbestos related works which confirms that the asbestos material have been removed appropriately and the relevant conditions of consent have been satisfied.

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development Section or a copy can be obtained from Council’s Customer Service Centre.

 

Site Signage

25.     A sign must be erected and maintained in a prominent position on the site for the duration of the works, which contains the following details:

 

·          name, address, contractor licence number and telephone number of the principal contractor, including a telephone number at which the person may be contacted outside working hours, or owner-builder permit details (as applicable)

·          name, address and telephone number of the Principal Certifying Authority,

·          a statement stating that “unauthorised entry to the work site is prohibited”.

 

Sediment & Erosion Control

26.     Sediment and erosion control measures, must be implemented throughout the site works in accordance with the manual for Managing Urban Stormwater – Soils and Construction, published by Landcom, to Council’s satisfaction.  Details are to be included in the Construction Site Management Plan.

 

Public Safety & Site Management

27.     Public safety and convenience must be maintained at all times during demolition, excavation and construction works and the following requirements must be complied with:

 

a)   Building materials, sand, soil, waste materials, construction equipment or other activities must not be placed upon the footpath, roadway or nature strip at any time and the footpath, nature strip and road must be maintained in a clean condition and free from any obstructions, soil and debris at all times.

 

b)   Stockpiles of soil, sand, aggregate or other materials must not be located on any footpath, roadway, nature strip, drainage line or any public place and the stockpiles must be protected with adequate sediment control measures.

 

c)   Building operations such as brick cutting, washing tools or equipment and mixing mortar are not permitted on public footpaths, roadways, nature strips, in any public place or any location which may lead to the discharge of materials into the stormwater drainage system.

 

d)   Bulk bins/waste containers must not be located upon the footpath, roadway or nature strip at any time without the prior written approval of the Council.  Applications to place a waste container in a public place can be made to Council’s Health, Building and Regulatory Services department.

 

e)   Any part of Council’s road, footway or nature strip which is damaged as a result of the work must be repaired or replaced to Council’s satisfaction.

 

f)    Temporary safety fencing is to be provided to any swimming pools under construction, pending the completion of all building work and the pool must not be filled until a fencing inspection has been carried out and approved by the principal certifying authority.

 

Excavations, Back-filling & Retaining Walls

28.     All excavations and backfilling associated with the erection or demolition of a building must be executed safely in accordance with appropriate professional standards and excavations must be properly guarded and supported to prevent them from being dangerous to life, property or buildings.

 

Retaining walls, shoring or piling must be provided to support land which is excavated in association with the erection or demolition of a building, to prevent the movement of soil and to support the adjacent land and buildings, if the soil conditions require it.  Adequate provisions are also to be made for drainage.

 

Details of proposed retaining walls, shoring or piling are to be submitted to and approved by the Principal Certifying Authority for the development prior to commencing such excavations or works.

 

Support of Adjoining Land

29.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 E of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that the adjoining land and buildings located upon the adjoining land must be adequately supported at all times.

 

a)    If the development involves an excavation that extends below the level of the base of the footings of a building on adjoining land, the person having the benefit of the development must, at the person’s own expense:

i)     protect and support the adjoining premises from possible damage from the excavation, and

ii)     where necessary, underpin the adjoining premises to prevent any such damage.

b)    The condition referred to in subclause a) does not apply if the person having the benefit of the development consent owns the adjoining land or the owner of the adjoining land has given consent in writing to that condition not applying.

30.     Prior to undertaking any demolition, excavation or building work in the following circumstances, a report must be obtained from a professional engineer which details the methods of support for the dwelling or associated structure on the adjoining land, to the satisfaction of the Principal Certifying Authority:

 

·          when undertaking excavation or building work within the zone of influence of the footings of a dwelling or associated structure that is located on the adjoining land;

·          when undertaking demolition work to a wall of a dwelling that is built to a common or shared boundary (eg. semi-detached or terrace dwelling);

·          when constructing a wall to a dwelling or associated structure that is located within 900mm of a dwelling located on the adjoining land.

 

The demolition, excavation and building work and the provision of support to the dwelling or associated structure on the adjoining land, must also be carried out in accordance with the abovementioned report, to the satisfaction of the Principal Certifying Authority.

 

Restriction on Working Hours

31.     Building, demolition and associated site works must be carried out in accordance with the following requirements:

 

Activity

Permitted working hours

All building, demolition and site work, including site deliveries (except as detailed below)

·   Monday to Friday - 7.00am to 5.00pm

·   Saturday - 8.00am to 5.00pm

·   Sunday & public holidays - No work permitted

Excavating of rock, use of jack-hammers, pile-drivers, vibratory rollers/compactors or the like

·   Monday to Friday - 8.00am to 5.00pm

·   Saturday - No work permitted

·   Sunday & public holidays - No work permitted

 

An application to vary the abovementioned hours may be submitted to Council’s Manager Health, Building & Regulatory Services for consideration and approval to vary the specified hours may be granted in exceptional circumstances and for limited occasions (e.g. for public safety, traffic management or road safety reasons).  Any applications are to be made on the standard application form and include payment of the relevant fees and supporting information.  Applications must be made at least 10 days prior to the date of the proposed work and the prior written approval of Council must be obtained to vary the standard permitted working hours.

 

Inspections During Construction

32.     The building works must be inspected by the Principal Certifying Authority, in accordance with sections 109 E (3) of the Environmental Planning & Assessment Act 1979 and clause 162A of the Environmental Planning & Assessment Regulation 2000, to monitor compliance with the relevant standards of construction, Council’s development consent and the construction certificate.

 

The Principal Certifying Authority must specify the relevant stages of construction to be inspected and a satisfactory inspection must be carried out, to the satisfaction of the Principal Certifying Authority, prior to proceeding to the subsequent stages of construction or finalisation of the works (as applicable).

 

Building Encroachments

33.     There must be no encroachment of any structures or building work onto Council’s road reserve, footway, nature strip or public place.

 

Road/Asset Opening Permit

34.     A Road / Asset Opening Permit must be obtained from Council prior to commencing any excavations or works within or upon a road, footpath, nature strip or in any public place, in accordance with section 138 of the Roads Act 1993 and all of the conditions and requirements contained in the Road / Asset Opening Permit must be complied with.

 

For further information, please contact Council’s Road / Asset Opening Officer on 9399 0691 or 9399 0999.

 

REQUIREMENTS PRIOR TO THE ISSUE OF AN OCCUPATION CERTIFICATE

The following conditions of consent must be complied with prior to the ‘Principal Certifying Authority’ issuing an ‘Occupation Certificate’.

 

Note:        For the purpose of this consent, any reference to ‘occupation certificate’ shall also be taken to mean ‘interim occupation certificate’ unless otherwise stated.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent and to maintain reasonable levels of public health, safety and amenity.

 

Occupation Certificate Requirements

35.     An Occupation Certificate must be obtained from the Principal Certifying Authority prior to any occupation of the building work encompassed in this development consent (including alterations and additions to existing buildings), in accordance with the relevant provisions of the Environmental Planning & Assessment Act 1979.

 

An Occupation Certificate must not be issued for the development if the development is inconsistent with the development consent.  The relevant requirements of the Environmental Planning & Assessment Act 1979 and conditions of development consent must be satisfied prior to the issuing of an occupation certificate.

 

BASIX Requirements

36.     In accordance with Clause 154B of the Environmental Planning & Assessment Regulation 2000, a Certifying Authority must not issue an Occupation Certificate for this development, unless it is satisfied that each of the required BASIX commitments have been fulfilled.

 

Relevant documentary evidence of compliance with the BASIX commitments is to be forwarded to the Council upon issuing an Occupation Certificate.

 

Occupant Safety

37.     Openable windows to a room, corridor, stairway or the like with a floor level more than 4m above the external ground/surface level, must be designed and constructed to reduce the likelihood of a child accessing and falling through the window opening.

 

Options may include one or more of the following measures:

 

·          The window having a minimum sill height of 1.5m above the internal floor level,

·          Providing a window locking device at least 1.5m above the internal floor level,

·          Fixing or securing the window (e.g. by screws or a window locking device) to restrict or to be able to secure the extent of the opening to a maximum width of 125mm,

·          Installing a fixed heavy-duty gauge metal screen over the opening (e.g. A metal security screen or metal security mesh and frame system, but not standard fly-screen material),

·          Other appropriate effective safety measures or barrier.

 

OPERATIONAL CONDITIONS

The following operational conditions must be complied with at all times, throughout the use and operation of the development.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent and to maintain reasonable levels of public health and environmental amenity.

 

Use of premises

38.     The premises must only be used as a single residential dwelling and must not be used for dual or multi-occupancy purposes.

 

External Lighting

39.     External lighting to the premises must be designed and located so as to minimise light-spill beyond the property boundary or cause a public nuisance.

 

Protection of the Environment Operations Act 1997 – Rainwater Tanks

40.     The operation of all plant and equipment shall not give rise to an ‘offensive noise’ as defined in the Protection of the Environment Operations Act 1997 and Regulations.

 

In this regard, the operation of the plant and equipment shall not give rise to an LAeq, 15 min sound pressure level at any affected premises that exceeds the background LA90, 15 min noise level, measured in the absence of the noise source/s under consideration by more than 5dB(A) in accordance with relevant NSW Department of Environment & Conservation Noise Control Guidelines.

 

Rainwater Tank Requirements

41.     The installation of rainwater tanks shall comply with the following noise control requirements:

 

a)    The operation of all plant and equipment shall not give rise to an ‘offensive noise’ as defined in the Protection of the Environment Operations Act 1997 and Regulations.

 

       In this regard, the operation of the plant and equipment shall not give rise to an LAeq, 15 min sound pressure level at any affected premises that exceeds the background LA90, 15 min noise level, measured in the absence of the noise source/s under consideration by more than 5dB(A) in accordance with relevant NSW Department of Environment & Conservation Noise Control Guidelines.

b)    Plant and equipment associated with rainwater tanks are to be enclosed in a sound absorbing enclosure or installed within a building, to minimise noise emissions and possible nuisance to nearby residents.

c)    The operation of plant and equipment associated with rainwater tanks are to be restricted to the following hours if the noise emitted can be heard within a habitable room in any other residential premises:

·      before 8.00am or after 8.00pm on weekends or public holiday; or

·      before 7.00am or after 8.00pm on weekdays.

 

ADVISORY NOTES

The following information is provided for your assistance to ensure compliance with the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, or other relevant legislation and Council’s policies.  This information does not form part of the conditions of development consent pursuant to Section 80A of the Act.

 

·          The requirements and provisions of the Environmental Planning & Assessment Act 1979 and Environmental Planning & Assessment Regulation 2000, must be fully complied with at all times.

 

Failure to comply with these requirements is an offence, which renders the responsible person liable to a maximum penalty of $1.1 million.  Alternatively, Council may issue a penalty infringement notice (for up to $1,500) for each offence.  Council may also issue notices and orders to demolish unauthorised or non-complying building work, or to comply with the requirements of Council’s development consent.

 

·          Demolition, building or excavation work must not be commenced until;

 

§  A Construction Certificate has been obtained from Council or an Accredited Certifier

§  Council or an Accredited Certifier has been appointed as the Principal Certifying Authority for the development

§  Council and the Principal Certifying Authority have been given at least 2 days notice (in writing) prior to commencing any works.

 

Council’s Building Approvals & Certification team can issue Construction Certificates and be your Principal Certifying Authority for the development, to undertake inspections and ensure compliance with the development consent, relevant building regulations and standards of construction.  For further details contact Council’s Building Approvals & Certification team on 9399 0944.

 

·          This determination does not include an assessment of the proposed works under the Building Code of Australia (BCA) and other relevant Standards.  All new building work (including alterations and additions) must comply with the BCA and relevant Standards and you are advised to liaise with your architect, engineer and building consultant prior to lodgement of your construction certificate.

 

·          A Local Approval application must be submitted to and be approved by Council's Building Approvals & Certification team prior to commencing any of the following activities on a footpath, road, nature strip or in any public place:-

§  Install or erect any site fencing, hoardings or site structures

§  Operate a crane or hoist goods or materials over a footpath or road

§  Placement of a waste skip or any other container or article.

 

For further information please contact Council’s Building Approvals & Certification team on 9399 0944.

 

·          Specific details of the location of the building/s should be provided in the Construction Certificate to demonstrate that the proposed building work will not encroach onto the adjoining properties, Council’s road reserve or any public place, to the satisfaction of the Certifying Authority.

 

·          Prior to commencing any works, the owner/builder should contact Dial Before You Dig on 1100 or www.dialbeforeyoudig.com.au and relevant Service Authorities, for information on potential underground pipes and cables within the vicinity of the development site.

 

MOTION: (Andrews/Mayor, Cr Matson) CARRIED UNANIMOUSLY - SEE RESOLUTION.

 

 

 

D105/11   Development Application Report - 20 Chester Avenue, Maroubra (DA/341/2011)

PL125/11

RESOLUTION: (Andrews/Mayor, Cr Matson) that Council, as the consent authority, grants development consent under Sections 80 and 80A of the Environmental Planning and Assessment Act 1979, as amended, to Development Application No. DA/341/2011 for alterations and additions to the existing semi detached dwelling, site fencing and landscaped setting (including the removal of 2 trees, changes to existing paving and demolition of the existing garage), at No. 20 Chester Ave, Maroubra, subject to the following conditions:

 

The following conditions are applied to satisfy the provisions of section 79C of the Environmental Planning and Assessment Act 1979 and to maintain reasonable levels of environmental amenity:

 

1.       The development must be implemented substantially in accordance with the following plans, the application form and on any supporting information received with the application, except as may be amended by the following conditions and as may be shown in red on the attached plans:

 

-    Site, Ground and First Floor Plan: Drawing No. 1003/A.01 Rev C dated 12.07.2011 and prepared by JDC Design

-    Elevations and sections: Drawing No. 1003/A.02 Rev C dated 12.07.2011 and prepared by JDC Design.

-    BASIX Certificate Number 117552 issued on 11 July, 2011

 

2.       Street numbering must be provided to the premises in a prominent position, in accordance with the Australia Post guidelines and AS/NZS 4819 (2003) to the satisfaction of Council, prior to an occupation certificate being issued for the development.

 

3.       The finished ground levels external to the building are to be consistent with the development consent and are not to be raised (other than for the provision of approved paving or the like on the ground) without the written consent of Council.

 

4.       External lighting shall be provided on the front elevation, preferably at the front entry.  It shall be located and designed so as not to cause a nuisance to nearby residents.

 

5.       Open-able windows to a room, corridor, stairway or the like with a floor level more than 4m above the external ground/surface level, must be designed and constructed to reduce the likelihood of a child accessing and falling through the window opening.

 

Options may include one or more of the following measures:

 

i)        The window having a minimum sill height of 1.5m above the internal floor level,

ii)       Providing a window locking device at least 1.5m above the internal floor level,

iii)       Fixing or securing the window (e.g. by screws or a window locking device) to restrict or to be able to secure the extent of the opening to a maximum of 125mm,

iv)      Installing a fixed heavy-duty gauge metal screen over the opening (e.g. A metal security screen or metal security mesh and frame system, but not standard fly-screen material),

v)       Other appropriate effective safety measures or barrier.

 

6.       The Bedroom 1 window on the north side elevation shall have a raised sill height of 1.5m or more or fixed obscure glazing at least below that height.  Details shall be indicated on final Construction Certificate plans to the satisfaction of the accredited certifier.

 

7.       Details of the proposed southern side boundary fencing forward of the building line are to be submitted to and approved by Council’s Director of City Planning prior to a construction certificate being issued for the relevant building works.  The fencing shall meet any engineering requirements for overland flow paths.

 

8.       Details of the proposed colours, materials and textures (i.e. a schedule and brochure/s or sample board, including those of the new front fencing and carport) are to be submitted to and approved by Council’s Director of City Planning, in accordance with section 80A (2) of the Environmental Planning and Assessment Act 1979 prior to a construction certificate being issued for the relevant building works.  The colours, materials and textures of the carport and new front fencing must match that of the finished dwelling.

 

9.       A minimum 700mm side setback to the southern side boundary shall be provided for the rear dwelling extension, including the rear deck, BBQ structure and side cladding.  The solar hot water system and bin store shall be relocated to ensure a clearance of at least 700mm from the side fencing to the facilities is provided.  Details are to be submitted to and approved by Council’s Director of City Planning prior to a construction certificate being issued for the relevant building works.

 

10.     There must be no encroachment of the structure/s onto any adjoining premises or onto Council’s road reserve, footway or public place, unless permission has been obtained from the owner/s of the adjoining land accordingly.

 

11.     The new gates must be fitted in such a manner so that they will not open over the footway or public place.

 

12.     Permission is granted for the selective pruning of the mature Eucalyptus robusta (located in the rear yard and adjacent to the northern side boundary), to improve its structure and avoid conflict with the approved works.  Prior to pruning, details of proposed pruning shall be submitted and approved by Council’s landscape officer.  All pruning must be undertaken by a qualified Arborist, with suitable qualifications in Arboriculture and to Australian Standard AS 4373-1996 'Pruning of Amenity Trees.’

 

The following conditions are applied to ensure that adequate provisions are made for the management of waste from the development:

 

13.     A waste/recycling cupboard/bin, capable of holding a single days waste with separate storage areas for recyclable and non-recyclable wastes, shall be provided in the dwelling, preferably under the kitchen sink. 

 

A bin storage area for garbage, recycling and gardening waste bins shall be allocated on the site with convenient access to and from the kerb-side collection area and clear of any landscaped areas.  It must not obstruct a continuous access way from the front to the rear of the property, along the southern side boundary, of at least 700mm in width. 

 

Details are to be submitted to and approved by Council’s Director of City Planning prior to a construction certificate being issued for the relevant building works.

 

14.     A demolition and construction Waste Management Plan (WMP) must be development and implemented for the development, to the satisfaction of Council, prior to the commencement of works.

 

The Waste Management Plan must provide details of the type and quantities of demolition and construction waste materials, proposed re-use and recycling of materials, methods of disposal and details of recycling outlets and land fill sites.

 

Where practicable waste materials must be re-used or recycled, rather than disposed and further details of Council's requirements including relevant guidelines and pro-forma WMP forms can be obtained from Council's Customer Service Centre or by telephoning Council on 9399 0999.

 

Details and receipts verifying the recycling and disposal of materials must be kept on site at all times and presented to Council officers upon request.

 

The following condition/s are imposed to satisfy the requirements of the Sydney Water Corporation.

 

15.     All building, plumbing and drainage work must be carried out in accordance with the requirements of the Sydney Water Corporation.

 

The approved Construction Certificate plans must be submitted to a Sydney Water Quick Check agent or Customer Centre prior to commencing any building or excavation works, to determine whether the development will affect Sydney Water’s sewer and water mains, stormwater drains and/or easements, and if any further requirements need to be met. 

 

If suitable, the plans will be appropriately stamped.  For Quick Check agent details please refer to Sydney Water’s web site at www.sydneywater.com.au and go to the Building, Developing and Plumbing, then Quick Check or Building and Renovating or telephone 13 20 92.

 

The principal certifying authority must ensure that a Quick Check Agent/Sydney Water has appropriately stamped the plans before commencing any works.

 

Section 94A Development Contributions applicable to all applications lodged from 2 July 2007:

 

The following condition is applied to meet additional demands for public facilities;

 

16.     In accordance with Council’s Section 94A Development Contributions Plan effective from 2 July 2007, based on the development cost of $192, 500, the following applicable monetary levy must be paid to Council: $1,925.

       

The levy must be paid in cash, bank cheque or by credit card prior to

 

a)   a construction certificate being issued

b)   a subdivision certificate being issued

 

for the proposed development. The development is subject to an index to reflect quarterly variations in the Consumer Price Index (CPI) from the date of Council’s determination to the date of payment.

 

Council’s Section 94A Development Contribution Plans may be inspected at the Customer Service Centre, Administrative Centre, 30 Frances Street, Randwick or at www.randwick.nsw.gov.au.

 

The following conditions are imposed to promote ecologically sustainable development and energy efficiency.

 

17.     In accordance with Section 80A (11) of the Environmental Planning and Assessment Act 1979 and Clause 97A of the Environmental Planning and Assessment Regulation 2000, it is a prescribed condition that all of the required commitments listed in the relevant BASIX Certificate for this development are fulfilled.

 

18.     In accordance with the provisions of the Environmental Planning & Assessment Regulation 2000, a relevant BASIX Certificate and associated documentation must be submitted to the Certifying Authority with the Construction Certificate application for this development.

 

The required commitments listed and identified in the BASIX Certificate are to be included on the approved plans, specifications and associated documentation for a Construction Certificate, to the satisfaction of the Certifying Authority.

 

The design of the building must not be inconsistent with the development consent and any proposed variations to the building to achieve the BASIX commitments may necessitate a new development consent or amendment to the existing consent to be obtained, prior to a construction certificate being issued.

 

19.     The following provisions are to be implemented in accordance with the relevant BASIX Certificate and details are to be included in the Construction Certificate documentation (as applicable), to the satisfaction of the Certifying Authority:

 

·           Stormwater management Water efficiency (i.e. triple A rated taps and showers, dual flush toilets and water re-use)

·           Landscaping provisions

·           Thermal comfort (i.e. construction materials, glazing and insulation)

·           Energy efficiency (i.e. cooling & heating provisions and solar hot water system)

 

20.     In accordance with Clause 154B of the Environmental Planning & Assessment Regulation 2000, a Certifying Authority must not issue an Occupation Certificate for this development, unless it is satisfied that each of the required BASIX commitments have been fulfilled.

 

Relevant documentary evidence of compliance with the BASIX commitments is to be forwarded to the Council upon issuing an Occupation Certificate.

 

The following conditions are applied to ensure that the development satisfies the provisions of the Environmental Planning and Assessment Act 1979 and Regulations:

 

21.     The requirements and provisions of the Environmental Planning & Assessment Act 1979 and Environmental Planning & Assessment Regulation 2000, must be fully complied with at all times.

 

Failure to comply with these legislative requirements is an offence and may result in the commencement of legal proceedings, issuing of `on-the-spot` penalty infringements or service of a notice and order by Council.

 

22.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that all building work must be carried out in accordance with the provisions of the Building Code of Australia (BCA).

 

23.     Prior to the commencement of any building works, the following requirements must be complied with:

 

a)    a Construction Certificate must be obtained from the Council or an accredited certifier, in accordance with the provisions of the Environmental Planning & Assessment Act 1979.

 

A copy of the construction certificate, the approved development consent plans and consent conditions must be kept on the site at all times and be made available to the Council officers and all building contractors for assessment.

 

b)    a Principal Certifying Authority (PCA) must be appointed to carry out the necessary building inspections and to issue an occupation certificate; and

 

c)    a principal contractor must be appointed for the building work, or in relation to residential building work, an owner-builder permit may be obtained in accordance with the requirements of the Home Building Act 1989, and the PCA and Council are to be notified accordingly; and

 

d)    the principal contractor must be advised of the required critical stage inspections and other inspections to be carried out, as specified by the Principal Certifying Authority; and

 

e)    at least two days notice must be given to the Council, in writing, prior to commencing building works.

 

In relation to residential building work, the principal contractor must be the holder of a contractor licence, in accordance with the provisions of the Home Building Act 1989.

 

24.     The building works must be inspected by the Principal Certifying Authority (or other certifying authority if the Principal Certifying Authority agrees), in accordance with sections 109 E (3) of the Environmental Planning & Assessment Act 1979 and clause 162A of the Environmental Planning & Assessment Regulation 2000, to monitor compliance with the relevant standards of construction, Council’s development consent and the construction certificate.

 

The Principal Certifying Authority must specify the relevant stages of construction to be inspected and a satisfactory inspection must be carried out, to the satisfaction of the Principal Certifying Authority, prior to proceeding to the subsequent stages of construction or finalisation of the works (as applicable).

 

25.     A sign must be erected and maintained in a prominent position on the site for the duration of the works, which contains the following details:

 

·        name, address, contractor licence number and telephone number of the principal contractor, including a telephone number at which the person may be contacted outside working hours, or owner-builder permit details (as applicable)

·        name, address and telephone number of the Principal Certifying Authority,

·        a statement stating that “unauthorised entry to the work site is prohibited”.

 

26.     The relevant requirements of the Home Building Act 1989 must be complied with, in accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000.

 

Details of the Licensed Building Contractor (and a copy of any relevant Certificate of Insurance) or a copy of the Owner-Builder Permit (as applicable) must be provided to the Principal Certifying Authority and Council prior to commencement of works.

 

27.     The required Long Service Levy payment, under the Building and Construction Industry Long Service Payments Act 1986, is to be forwarded to the Long Service Levy Corporation or the Council, prior to the issuing of a Construction Certificate, in accordance with Section 109F of the Environmental Planning & Assessment Act 1979.

 

At the time of this development consent, Long Service Levy payment is applicable on building work having a value of $25,000 or more, at the rate of 0.35% of the cost of the works.

 

28.     An Occupation Certificate must be obtained from the Principal Certifying Authority prior to any occupation of the building work encompassed in this development consent (including alterations and additions to existing buildings), in accordance with the relevant provisions of the Environmental Planning & Assessment Act 1979.

 

An Occupation Certificate must not be issued for the development if the development is inconsistent with the development consent.  The relevant requirements of the Environmental Planning & Assessment Act 1979 and conditions of development consent must be satisfied prior to the issuing of an occupation certificate.

 

29.     Prior to the issuing of an interim or final occupation certificate, a statement is required to be obtained from the Principal Certifying Authority or other suitably qualified person, which confirms that the development is not inconsistent with the development consent and the relevant conditions of development consent have been satisfied.

 

30.     Smoke alarms must be installed in each Class 1 building or residential dwelling in accordance with the relevant provisions of Part 3.7.2 of the B.C.A. – Housing Provisions.

 

Smoke alarms must comply with AS3786 – Smoke alarms and be connected to the consumer mains electric power supply and provided with a battery back-up.  Details of compliance with the provisions of the Building Code of Australia must be included in the plans / specification for the construction certificate.

 

The following conditions are applied to ensure that the development satisfies relevant standards of construction, and to maintain adequate levels of health, safety and amenity during construction:

 

31.     The demolition of buildings and the removal, storage, handling and disposal of building materials must be carried out in accordance with the relevant requirements of WorkCover NSW, the NSW Department of Environment & Climate Change and Randwick City Council policies, including:

 

·          Occupational Health & Safety Act 2000 & Regulations

·          WorkCover NSW Code of Practice for the Safe Removal of Asbestos

·          WorkCover NSW Guidelines and Codes of Practice

·          Australian Standard 2601 (2001) – Demolition of Structures

·          The Protection of the Environment Operations Act 1997 and Protection of the Environment Operations (Waste) Regulation 2005

·          Relevant DECC/EPA Guidelines

·          Randwick City Council Asbestos Policy (adopted 13 September 2005)

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development section or a copy can be obtained from Council’s Customer Service Centre.

 

32.     A Demolition Work Plan must be prepared for the development in accordance with Australian Standard AS2601-2001, Demolition of Structures.

 

The Demolition Work Plan must include the following information (as applicable):

·          The name, address, contact details and licence number of the Demolisher /Asbestos Removal Contractor

·          Details of hazardous materials (including asbestos)

·          Method/s of demolition (including removal of any asbestos)

·          Measures and processes to be implemented to ensure the health & safety of workers and community

·          Measures to be implemented to minimise any airborne dust and asbestos

·          Methods and location of disposal of any hazardous materials

·          Other relevant details, measures and requirements to be implemented

·          Date the demolition works will commence

 

The Demolition Work Plan must be submitted to the Principal Certifying Authority (PCA), not less than two (2) working days before commencing any demolition work.  A copy of the Demolition Work Plan must be maintained on site and be made available to Council officers upon request.

 

If the work involves asbestos products or materials, a copy of the Demolition Work Plan must also be provided to Council not less than 2 days before commencing those works.

 

Note it is the responsibility of the persons undertaking demolition work to obtain the relevant WorkCover licences and permits.

 

33.     Any work involving the demolition, storage or disposal of asbestos products and materials must be carried out in accordance with the following requirements:

 

·          Relevant Occupational Health & Safety legislation and WorkCover NSW requirements

 

·          Randwick City Council’s Asbestos Policy (adopted 13 September 2005)

 

·          A WorkCover licensed demolition or asbestos removal contractor must undertake removal of more than 10m2 of bonded asbestos (or as otherwise specified by WorkCover or relevant legislation).  Removal of friable asbestos material must only be undertaken by contractor that holds a current friable asbestos removal licence.

 

·          On sites involving the removal of asbestos, a sign must be clearly displayed in a prominent visible position at the front of the site, containing the words ‘DANGER ASBESTOS REMOVAL IN PROGRESS’ and include details of the licensed contractor.

 

·          Asbestos waste must be stored, transported and disposed of in compliance with the Protection of the Environment Operations Act 1997 and the Protection of the Environment Operations (Waste) Regulation 2005.

 

·          A Clearance Certificate or Statement, prepared by a suitably qualified person (ie an occupational hygienist, licensed asbestos removal contractor, building consultant, architect or experienced licensed building contractor), must be provided to Council and the Principal certifying authority upon completion of the asbestos related works which confirms that the asbestos material have been removed appropriately and the relevant conditions of consent have been satisfied.

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development Section or a copy can be obtained from Council’s Customer Service Centre.

 

34.     The removal, cleaning and disposal of any lead-based paints must be carried out in accordance with the relevant provisions of AS2601-2001, Demolition of Structures, The Protection of the Environment Operations Act 1997 and the requirements and guidelines of the Environmental Protection Authority.

 

35.     A dilapidation report prepared by a professional engineer, building surveyor or other suitably qualified independent person must be submitted to the satisfaction of the Principal Certifying Authority prior to commencement of any demolition, excavation or building works, in the following cases:

 

·          excavations for new dwellings, additions to dwellings, swimming pools or the like which are proposed to be located within the zone of influence of the footings of any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

·          new dwellings or additions to dwellings sited up to shared property boundaries (e.g.  additions to a semi-detached dwelling or terraced dwellings),

·          excavations for new dwellings, additions to dwellings, swimming pools or the like which are within rock and may result in vibration and or potential damage to any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

·          as otherwise may be required by the Principal Certifying Authority.

 

The report (including photographs) are required to detail the current condition and status of any dwelling, associated garage or other substantial structure located upon the adjoining premises, which may be affected by the subject works.  A copy of the dilapidation report is to be given to the owners of the premises encompassed in the report/s before commencing any works.

 

36.     All excavations and backfilling associated with the erection or demolition of a building must be executed safely in accordance with appropriate professional standards and excavations are to be properly guarded and supported to prevent them from being dangerous to life, property or buildings.

 

Retaining walls, shoring or piling must be provided to support land which is excavated in association with the erection or demolition of a building, to prevent the movement of soil and to support the adjacent land and buildings, if the soil conditions require it.  Adequate provisions are also to be made for drainage.

 

Details of proposed retaining walls, shoring or piling are to be submitted to and approved by the Principal Certifying Authority for the development prior to commencing such excavations or works.

 

37.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 E of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that the adjoining land and buildings located upon the adjoining land must be adequately supported at all times.

 

a)     If the development involves an excavation that extends below the level of the base of the footings of a building on adjoining land, the person having the benefit of the development must, at the person’s own expense:

 

i)      protect and support the adjoining premises from possible damage from the excavation, and

ii)      where necessary, underpin the adjoining premises to prevent any such damage.

 

b)     The condition referred to in subclause 1) does not apply if the person having the benefit of the development consent owns the adjoining land or the owner of the adjoining land has given consent in writing to that condition not applying.

 

38.     Except with the written approval of Council’s Manager of Health, Building & Regulatory Services, all building, demolition and associated site works (including site deliveries) must only be carried out between the hours of 7.00am to 5.00pm on Monday to Friday inclusive and between 8.00am to 5.00pm on Saturdays and all building activities are strictly prohibited on Sundays and Public Holidays.

 

In addition, the use of any rock excavation machinery or any mechanical pile drivers or the like, is restricted to the hours of 8.00am to 5.00pm (maximum) on Monday to Friday only, to minimise the noise levels during construction and loss of amenity to nearby residents.

 

39.     Noise and vibration emissions during the construction of the building and associated site works must not result in damage to nearby premises or result in an unreasonable loss of amenity to nearby residents and the relevant requirements of the Protection of the Environment Operations Act 1997 and NSW DECC Guidelines must be satisfied at all times.

 

Noise and vibration from any rock excavation machinery, pile drivers and all plant and equipment must be minimised, by using appropriate plant and equipment, silencers and the implementation of noise management strategies.

 

A Construction Noise Management Plan, prepared by a suitably qualified person is to be implemented throughout the works, to the satisfaction of the Council.  A copy of the strategy must be provided to the Principal Certifying Authority and Council prior to the commencement of works.

 

The Construction Noise Management Plan is to be prepared in accordance with the NSW DECC Construction Noise Guideline.

 

40.     A Registered Surveyor’s check survey certificate or compliance certificate is to be obtained at the following stage/s of construction to demonstrate compliance with the approved setbacks, levels, layout and height of the building to the satisfaction of the Principal Certifying Authority:

 

·        prior to construction of the footings or first completed floor slab (prior to the pouring of concrete),

 

·        upon completion of the building, prior to issuing an occupation certificate.

 

The survey documentation must be forwarded to the Principal Certifying Authority and a copy is to be forwarded to the Council, if the Council is not the principal certifying authority.  

 

41.     Temporary toilet facilities are to be provided, at or in the vicinity of the work site throughout the course of demolition and construction, to the satisfaction of WorkCover NSW and the toilet facilities must be connected to a public sewer or other sewage management facility approved by Council.

 

42.     Public safety must be maintained at all times and public access to the site and building works, materials and equipment on the site is to be restricted, when work is not in progress or the site is unoccupied, to the satisfaction of Council.

 

A temporary safety fence is to be provided to protect the public, located to the perimeter of the site (unless the site is separated from the adjoining land by an existing structurally adequate fence, having a minimum height of 1.5 metres).  Temporary fences are to have a minimum height of 1.8 metres and be constructed of cyclone wire fencing, with geotextile fabric attached to the inside of the fence to provide dust control, or other material approved by Council.

 

Temporary site fences are to be structurally adequate, safe and be constructed in a professional manner and the use of poor quality materials or steel reinforcement mesh as fencing is not permissible.

 

The public safety provisions and temporary fences must be in place prior to the commencement of any demolition, excavation or building works and be maintained throughout construction.

 

If it is proposed to locate any site fencing, hoardings or amenities upon any part of the footpath, nature strip or public place, the written consent from Council’s Building Services section must be obtained beforehand and detailed plans are to be submitted to Council for consideration, together with payment of the weekly charge in accordance with Council’s adopted fees and charges.

 

43.     A Construction Site Management Plan is to be developed and implemented prior to the commencement of any works. The site management plan must include the following measures, as applicable to the type of development:

 

·      location and construction of protective fencing / hoardings to the perimeter of the site;

·      location of site storage areas/sheds/equipment;

·      location of building materials for construction;

·      provisions for public safety;

·      dust control measures;

·      site access location and construction

·      details of methods of disposal of demolition materials;

·      protective measures for tree preservation;

·      provisions for temporary sanitary facilities;

·      location and size of waste containers/bulk bins;

·      details of proposed sediment and erosion control measures;

·      construction noise and vibration management;

·      construction traffic management details.

 

The site management measures are to be implemented prior to the commencement of any site works and be maintained throughout the works, to maintain reasonable levels of public health, safety and amenity to the satisfaction of Council.  A copy of the Construction Site Management Plan must be provided to the Principal Certifying Authority and Council.  A copy must also be maintained on site and be made available to Council officers upon request.

 

44.     Sediment and erosion control measures must be provided in accordance with the manual for Managing Urban Stormwater – Soils and Construction, published by Landcom, to Council’s satisfaction.

 

Details of proposed sediment and erosion control measures shall include; a site plan; indicating the slope of land, access points & access control measures, location and type of sediment & erosion controls, location of existing vegetation to be retained, location of material stockpiles and storage areas, location of building operations and equipment, methods of sediment control, details of drainage systems and details of existing and proposed vegetation.

 

45.     Public safety and convenience must be maintained at all times during demolition, excavation and construction works and the following requirements must be complied with:

 

a)       Building materials, sand, soil, waste materials, construction equipment or5 other activities must not be placed upon the footpath, roadway or nature strip at any time and the footpath, nature strip and road must be maintained in a clean condition and free from any obstructions, soil and debris at all times.

 

b)       Stockpiles of soil, sand, aggregate or other materials must not be located on any footpath, roadway, nature strip, drainage line or any public place and the stockpiles must be protected with adequate sediment control measures.

 

c)       Building operations such as brick cutting, washing tools or equipment and mixing mortar are not permitted on public footpaths, roadways, nature strips, in any public place or any location which may lead to the discharge of materials into the stormwater drainage system.

 

d)       Bulk bins/waste containers must not be located upon the footpath, roadway or nature strip at any time without the prior written approval of the Council.  Applications to place a waste container in a public place can be made to Council’s Health Building and Regulatory Services section.

 

e)       Any part of Council’s road, footway or nature strip which is damaged as a result of the work must be repaired or replaced to Council’s satisfaction.

 

The following conditions have been applied to ensure that adequate security provisions are made for vehicular access, parking and public infrastructure:

 

46.     The owner/builder must meet the full cost for Council or a Council approved contractor to install vehicular crossings and to repair/replace any damaged sections of Council's footpath, kerb & gutter, nature strip etc which are due to building works being carried out at the above site. This includes the removal of cement slurry from Council's footpath and roadway.

 

47.     The following damage / civil works security deposit requirement is to be complied with prior to a construction certificate being issued for the development, as security for making good any damage caused to the roadway, footway, verge or any public place; and as security for completing any public work; and for remedying any defect on such public works, in accordance with section 80A(6) of the Environmental Planning and Assessment Act 1979:

 

Damage / Civil Works Security Deposit

 

The damage/civil works security deposit may be provided by way of a cash, cheque or credit card payment and is refundable upon a satisfactory inspection by Council upon the completion of the civil works which confirms that there has been no damage to Council's infrastructure.

The owner/builder is also requested to advise Council in writing and/or photographs of any signs of existing damage to the Council roadway, footway, or verge prior to the commencement of any building/demolition works.

To obtain a refund of relevant deposits, a Security Deposit Refund Form is to be forwarded to Council’s Director of City Services upon issuing of an occupation certificate or completion of the civil works.

 

48.     A public utility impact assessment must be carried out on all public utility services located on the site, roadway, nature strip, footpath, public reserve or any public areas associated with and/or adjacent to the building works.  The assessment should include relevant information from public utility authorities and if necessary, exploratory trenching or pot-holing to determine the position and level of services.

 

Documentary evidence from the relevant public utility authorities confirming that their requirements have been or are able to be satisfied, must be submitted to the principal certifying authority prior to the commencement of any demolition, excavation or building works.

 

The owner/builder must meet the full cost for telecommunication companies, gas providers, Energy Australia and Sydney Water to adjust/repair/relocate their services as required.  The applicant must make the necessary arrangements with the service authorities.

 

Design Alignment levels

49.     The design alignment level (the finished level of concrete, paving or the like) at the property boundary for driveways, access ramps and pathways or the like, must match the back of the existing footpath along the full site frontage.

 

The design alignment level/s at the property boundary as issued by Council and their relationship to the footpath must be indicated on the building plans for the construction certificate. The design alignment level at the street boundary, as issued by the Council, must be strictly adhered to.

 

Any enquiries regarding this matter should be directed to Council’s Development Engineer on 9399 0881.

 

Stormwater Drainage

50.     Stormwater runoff from the redeveloped portion of the site shall be discharged to the kerb and gutter along the site frontage by gravity (preferably without the use of a charged system).

 

51.     Should a charged system be required to drain any portion of the site, the charged system must be designed with suitable clear-outs/inspection points at pipe bends and junctions.

 

Provision for Flooding

52.     Plans submitted for the construction certificate shall demonstrate the new gate across the vehicular access being of a free and open form or indicate a minimum ground clearance of 250mm to the bottom of the gate to allow for passage of overland flow during major storm events.

 

53.     Plans submitted for the construction certificate shall increase the setback of the proposed BBQ & deck from the southern side boundary to a minimum of 700mm so as to allow for passage of overland flow during major storm events.

 

Protection of tree in rear yard

54.     In order to ensure retention of the mature Eucalyptus robusta (Swamp Mahogany) located in the rear yard, about halfway along the length of the northern boundary in good health, the following measures are to be undertaken:

 

a.  All documentation submitted for the Construction Certificate application must show the retention of this tree, with the position and diameter of both its trunk and canopy to be clearly and accurately shown on all drawings.

 

b.     All physical parts of the proposed ground floor awning (post, gutter, eave, fascia or similar) must be setback a minimum distance of 2300mm from this tree, measured off its outside edge at ground level.

 

c.       The timber deck must be constructed on localised pad footings/isolated piers, with all initial excavations within 3.5m of its trunk to be dug by hand, to a minimum depth of 600mm, where any roots with a diameter of less than 75mm that are encountered can be cut cleanly by hand and the affected area backfilled with clean site soil as soon as practically possible, with any roots measuring 75mm or more to be preserved, and footings positioned around them.

 

d.       Any new services, pipes, stormwater systems or similar that need to be installed in the rear yard must be setback a minimum distance of 3.5 metres off its trunk at ground level.

 

e.       This tree is to be physically protected by the installation of 1.8 metre high steel mesh/chainwire fencing, which shall be located a minimum distance of 3.5 metres to its south and west (measured off the outside edge of its trunk at ground level), matching up with the northern site boundary and proposed ground floor deck/awning, in order to completely enclose this tree for the duration of works.

 

f.        This fencing shall be installed prior to the commencement of demolition and construction works and shall remain in place until all works are completed, to which signage containing the following words shall be clearly displayed and permanently attached: “TREE PROTECTION ZONE (TPZ), DO NOT REMOVE/ENTER".

 

g.       Within the TPZ, there is to be no storage of materials, machinery or site office/sheds, nor is cement to be mixed or chemicals spilt/disposed of and no stockpiling of soil or rubble, with all Site Management Plans needing to acknowledge these requirements.

 

Public Utilities

55.     A Public Utility Impact Assessment must be carried out on all public utility services on the site, roadway, nature strip, footpath, public reserve or any public areas associated with and/or adjacent to the development/building works and include relevant information from public utility authorities and exploratory trenching or pot-holing, if necessary, to determine the position and level of service.

 

56.     The applicant must meet the full cost for telecommunication companies, gas providers, Energy Australia and Sydney Water to adjust/repair/relocate their services as required.  The applicant must make the necessary arrangements with the service authority.

 

Tree Removals

57.     Approval is granted for removal of the following trees:

 

a)       The large and mature Agonis flexuosa (Willow Myrtle) in the front yard, against the eastern boundary, halfway across the width of the site, due both to its poor form and condition arising from basal decay, as well as to accommodate the new front masonry fence as shown;

b)       The Banksia integrifolia (Coastal Banksia) in the rear yard, along the northern boundary, due to its inappropriate location close to the northwest corner of the existing dwelling, as well as to accommodate the ground floor extension and first floor addition as shown.

 

Pruning

58.     Any dead and dying wood throughout the canopy of the Eucalyptus robusta (Swamp Mahogany), located in the rear yard, about halfway along the length of the northern boundary, shall be removed, with any stubs left from past storm damage also to be pruned back to either the nearest branch collar or main trunk.

 

59.     Any further pruning required in order to either avoid damage to the tree, or, interference during construction of the proposed ground or first floor, shall be minimal and selective in nature, and only where they need to be pruned due to being in direct conflict with the proposed works, and must not adversely affect it habit and form.

 

60.     All pruning must be undertaken by an Arborist who holds a minimum of AQF Level V in Arboriculture, and to the requirements of Australian Standard AS 4373-2007 'Pruning of Amenity Trees,’ and NSW Work Cover Code of Practice for the Amenity Tree Industry (1998).

 

Council’s Infrastructure, Vehicular Crossings, street verge

61.     Prior to the issuing of an occupation certificate the applicant must meet the full cost for Council or a Council approved contractor to:

 

a)       Construct a concrete vehicular crossing and layback at kerb opposite the vehicular entrance to the site.

 

b)       Remove the redundant concrete vehicular crossing and layback and to reinstate the area with concrete footpath, turf and integral kerb and gutter to Council's specification.

 

62.     The applicant must meet the full cost for Council or a Council approved contractor to repair/replace any damaged sections of Council's footpath, kerb & gutter, nature strip etc which are due to building works being carried out at the above site. This includes the removal of cement slurry from Council's footpath and roadway.

 

63.     All external civil work to be carried out on Council property (including the installation and repair of roads, footpaths, vehicular crossings, kerb and guttering and drainage works), must be carried out in accordance with Council's Policy for "Vehicular Access and Road and Drainage Works" and the following requirements:

 

a)     All work on Council land must be carried out by Council, unless specific written approval has been obtained from Council to use non-Council contractors.

 

b)     Details of the proposed civil works to be carried out on Council land must be submitted to Council in a Pre-paid Works Application Form, prior to issuing an occupation certificate, together with payment of the relevant fees.

 

c)     If it is proposed to use non-Council contractors to carry out the civil works on Council land, the work must not commence until the written approval has been obtained from Council and the work must be carried out in accordance with the conditions of consent, Council’s design details and payment of a Council design and supervision fee.

 

d)     The civil works must be completed in accordance with Council’s conditions of consent and approved design and construction documentation, prior to occupation of the development, or as otherwise approved by Council in writing.

 

64.     That part of the nature-strip upon Council's footway which is damaged during the construction of the proposed works shall be excavated to a depth of 150mm, backfilled with topsoil equivalent with 'Organic Garden Mix' as supplied by Australian Native Landscapes, and re-turfed with Kikuyu turf or similar. Such works shall be completed at the applicant’s expense prior to the issue of a final Occupation Certificate.

 

Flooding

65.     The portion of the site between the southern side boundary and the dwelling shall be kept clear of any obstructions which may inhibit the movement of overland flow path during major storm events.

 

ADVISORY MATTERS:

 

A1      Demolition, building or excavation work must not be commenced until;

 

·          A Construction Certificate has been obtained from Council or an Accredited Certifier

·          Council or an Accredited Certifier has been appointed as the Principal Certifying Authority for the development

·          Council and the Principal Certifying Authority have been given at least 2 days notice (in writing) prior to commencing any works.

 

Failure to comply with these important requirements is an offence, which renders the responsible person liable to a maximum penalty of $1.1 million under the Environmental Planning & Assessment Act 1979.  Alternatively, Council may issue a penalty infringement notice (for up to $1,500) for each offence.

 

A2      A local approval application must be submitted to and be approved by Council's Building Certification Services section prior to commencing any of the following activities on a footpath, road, nature strip or in any public place:-

 

·          Install or erect any site fencing, hoardings or site structures

·          Operate a crane or hoist goods or materials over a footpath or road

·          Placement of a waste skip or any other container or article.

 

For further information please contact Council’s Building Certification Services on 9399 0944.

 

A3      Specific details of the location of the building/s should be provided in the Construction Certificate to demonstrate that the proposed building work will not encroach onto the adjoining properties, Council’s road reserve or any public place, to the satisfaction of the Certifying Authority.

 

A4      Prior to commencing any works, the owner/builder should contact Dial Before You Dig on 1100 or www.dialbeforeyoudig.com.au and relevant Service Authorities, for information on potential underground pipes and cables within the vicinity of the development site.

 

A5      The applicant is to advise Council in writing and/or photographs of any signs of existing damage to the Council roadway, footway, or verge prior to the commencement of any building/demolition works.

 

This determination does not include an assessment of the proposed works under the Building Code of Australia (BCA) and other relevant Standards.  All new building work (including alterations and additions) must comply with the BCA and relevant Standards and you are advised to liaise with your architect, engineer and building consultant prior to lodgement of your construction certificate.

 

MOTION: (Andrews/Mayor, Cr Matson) CARRIED UNANIMOUSLY - SEE RESOLUTION.

 

 

 

D106/11   Development Application Report - 22 Powell Street, Coogee (DA/439/2011)

PL126/11

RESOLUTION: (Andrews/Mayor, Cr Matson) that Council, as the consent authority, grants development consent under Sections 80 and 80A of the Environmental Planning and Assessment Act 1979, as amended, to Development Application No. 439/2011 for alterations and additions to the existing outbuilding to provide a secondary dwelling (commonly known as a granny flat) under State Environmental Planning Policy (Affordable Rental Housing) 2009, at No. 22 Powell Street, Coogee, subject to the following conditions:

 

DEVELOPMENT CONSENT CONDITIONS

 

GENERAL CONDITIONS

The development must be carried out in accordance with the following conditions of consent.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of environmental amenity.

 

Approved Plans & Supporting Documentation

1.       The development must be implemented substantially in accordance with the plans and supporting documentation listed below and endorsed with Council’s approved stamp, except where amended by Council in red and/or by other conditions of this consent:

 

Plan

Drawn by

Dated

Received

Site Analysis Plan 1122 1 of 6

Design Solutions – Todd Maguire

June 2011

15 June 2011

Elevations 1122-2

Design Solutions – Todd Maguire

June 2011

15 June 2011

Plan 1 1122-3

Design Solutions – Todd Maguire

June 2011

15 June 2011

Plan 2 1122-4

Design Solutions – Todd Maguire

June 2011

15 June 2011

Plan 3 1122-5

Design Solutions – Todd Maguire

June 2011

15 June 2011

Sections 1122-6

Design Solutions – Todd Maguire

June 2011

15 June 2011

Survey Plan

Geosurv

3 June 2011

15 June 2011

Shadows 1122 S1 of 3

Design Solutions – Todd Maguire

June 2011

15 June 2011

Shadows 1122 S2

Design Solutions – Todd Maguire

June 2011

15 June 2011

Shadows 1122 S3

Design Solutions – Todd Maguire

June 2011

15 June 2011

Statement of Environmental Effects

Design Solutions – Todd Maguire

undated

15 June 2011

 

BASIX Certificate

No.

Dated

Received

Certificate No.

381052S

8 June 2011

15 June 2011

 

Amendment of Plans & Documentation

2.       The approved plans and documents must be amended in accordance with the following requirements:

 

a.   The ‘wash’ and ‘tub’ must be relocated to the northern side of the car space to ensure the space maintains the minimum dimensions of 5.5m x 3.2m.

 

REQUIREMENTS PRIOR TO THE ISSUE OF A CONSTRUCTION CERTIFICATE

The following conditions of consent must be complied with prior to the issue of a ‘Construction Certificate’ by either Randwick City Council or an Accredited Certifier.  All necessary information to demonstrate compliance with the following conditions of consent must be submitted with the construction certificate application.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, and Council’s development consent conditions and to achieve reasonable levels of environmental amenity.

 

Consent Requirements

3.       The requirements and amendments detailed in the ‘General Conditions’ must be complied with and be included in the construction certificate plans and associated documentation.

 

External Colours, Materials & Finishes

4.       a)    The colours, materials and finishes of the external surfaces are to be compatible with the existing dwelling on the site and adjacent development to maintain the integrity and amenity of the building and the streetscape.

 

Any metal roof sheeting is to be pre-painted (e.g. Colourbond) to limit the level of reflection and glare.

 

b)    Details of the proposed colours, materials and textures (i.e. a schedule and brochure/s or sample board) are to be submitted to and approved by the Certifying Authority prior to issuing a construction certificate for the development.

 

c)    No rainforest timbers or timbers cut from old growth forests are to be used.

 

Safety and Security

5.       The doors on the east elevation shall be lockable. 

 

Car Access / Manoeuvring

6.       The garage width must be generally in accordance with Australian Standard 2890.1.  Details (including any relevant vehicle manoeuvring diagrams) are to be submitted to and approved by the Certifying Authority with the Construction Certificate.

 

Waste Storage - Ongoing

7.       The secondary dwelling must have a waste storage cupboard in or adjacent to the kitchen capable of holding at least a single day’s waste and source separation of garbage, recyclable and compostable material, to the satisfaction of the certifying authority.

 

Demolition & Construction Waste

8.       A demolition and construction Waste Management Plan (WMP) must be development and implemented for the development, to the satisfaction of Council, prior to the issuing of a construction certificate.

 

The Waste Management Plan must provide details of the type and quantities of demolition and construction waste materials, proposed re-use and recycling of materials, methods of disposal and details of recycling outlets and land fill sites.

 

Where practicable waste materials must be re-used or recycled, rather than disposed and further details of Council's requirements including relevant guidelines and pro-forma WMP forms can be obtained from Council's Customer Service Centre or by telephoning Council on 9399 0999.

 

9.       Details and receipts verifying the recycling and disposal of materials must be kept on site at all times and presented to Council officers upon request.

 

The levy must be paid in cash, bank cheque or by credit card prior to a construction certificate [or subdivision certificate] being issued for the proposed development.  The development is subject to an index to reflect quarterly variations in the Consumer Price Index (CPI) from the date of Council’s determination to the date of payment.

 

Council’s Section 94A Development Contribution Plans may be inspected at the Customer Service Centre, Administrative Centre, 30 Frances Street, Randwick or at www.randwick.nsw.gov.au.

 

Compliance with the Building Code of Australia

10.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that all building work must be carried out in accordance with the provisions of the Building Code of Australia (BCA).  Details of compliance with the BCA are to be included in the construction certificate application.

 

Structural Adequacy

11.     Certificate of Adequacy supplied by a professional engineer shall be submitted to the certifying authority (and the Council, if the Council is not the certifying authority), certifying the structural adequacy of the existing structure to support the upper floor addition.

 

Long Service Levy Payments

12.     The required Long Service Levy payment, under the Building and Construction Industry Long Service Payments Act 1986, must be forwarded to the Long Service Levy Corporation or the Council, in accordance with Section 109F of the Environmental Planning & Assessment Act 1979.

 

At the time of this development consent, Long Service Levy payment is applicable on building work having a value of $25,000 or more, at the rate of 0.35% of the cost of the works.

 

Security Deposits

13.     The following damage / civil works security deposit requirement must be complied with prior to a construction certificate being issued for the development, as security for making good any damage caused to the roadway, footway, verge or any public place; and as security for completing any public work; and for remedying any defect on such public works, in accordance with section 80A(6) of the Environmental Planning and Assessment Act 1979:

 

·           $600.00     -      Damage / Civil Works Security Deposit

 

The damage/civil works security deposit may be provided by way of a cash, cheque or credit card payment and is refundable upon a satisfactory inspection by Council upon the completion of the civil works which confirms that there has been no damage to Council's infrastructure.

 

The owner/builder is also requested to advise Council in writing and/or photographs of any signs of existing damage to the Council roadway, footway, or verge prior to the commencement of any building/demolition works.

 

To obtain a refund of relevant deposits, a Security Deposit Refund Form is to be forwarded to Council’s Director of City Services upon issuing of an occupation certificate or completion of the civil works.

 

Design Alignment levels

14.     The design alignment level (the finished level of concrete, paving or the like) at the property boundary for driveways, access ramps and pathways or the like, must match the back of the existing footpath along the full site frontage.

 

The design alignment level/s at the property boundary as issued by Council and their relationship to the roadway/kerb/footpath must be indicated on the building plans for the construction certificate. The design alignment level at the street boundary, as issued by the Council, must be strictly adhered to.

 

Any enquiries regarding this matter should be directed to Council’s Development Engineer on 9399 0923.

 

Stormwater Drainage

15.     A surface water/stormwater drainage system must be provided in accordance with the following requirements, to the satisfaction of the Certifying Authority and details are to be included in the construction certificate:-

 

a)    Surface water/stormwater drainage systems must be provided in accordance with Part 3.1.2 of the Building Code of Australia (Volume 2);

 

b)    The surface water/stormwater must be drained and discharged to the street gutter or, subject to site suitability, the stormwater may be drained to a suitably designed absorption pit;

 

c)    Any absorption pits or soaker wells should be located not less than 3m from any adjoining premises and the stormwater must not be directed to any adjoining premises or cause a nuisance;

 

d)    External paths and ground surfaces are to be constructed at appropriate levels and be graded and drained away from the building and adjoining premises, so as not to result in the entry of water into the building, or cause a nuisance or damage to the adjoining premises;

 

e)    Details of any proposed drainage systems or works to be carried out in the road, footpath or nature strip must be submitted to and approved by Council before commencing these works.

 

BASIX Requirements

16.     In accordance with section 80A(11) of the Environmental Planning & Assessment Act 1979 and clause 97A of the Environmental Planning & Assessment Regulation 2000, the requirements and commitments contained in the relevant BASIX Certificate must be complied with.

 

The required commitments listed and identified in the BASIX Certificate must be included on the construction certificate plans, specifications and associated documentation, to the satisfaction of the Certifying Authority.

 

The design of the building must not be inconsistent with the development consent and any proposed variations to the building to achieve the BASIX commitments may necessitate a new development consent or amendment to the existing consent to be obtained, prior to a construction certificate being issued.

 

Smoke Alarms

17.     Smoke alarms are required to be installed in each Class 1 building or dwelling in accordance with the relevant provisions of Part 3.7.2 of the B.C.A. – Housing Provisions.

 

Smoke alarms must comply with AS3786 – Smoke alarms and be connected to the consumer mains electric power supply and provided with a battery back-up.  Details of compliance are to be included in the construction certificate.

 

REQUIREMENTS PRIOR TO THE COMMENCEMENT OF ANY WORKS

The following conditions of consent must be complied with prior to the commencement of any works on the site.  The necessary documentation and information must be provided to the Council or the ‘Principal Certifying Authority’, as applicable.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of public health, safety and environmental amenity.

 

Construction Certificate, Principal Certifying Authority & Commencement of Works

18.     Prior to the commencement of any building works, the following requirements must be complied with:

 

a)       a Construction Certificate must be obtained from the Council or an accredited certifier, in accordance with the provisions of the Environmental Planning & Assessment Act 1979.

 

A copy of the construction certificate, the approved development consent plans and consent conditions must be kept on the site at all times and be made available to the Council officers and all building contractors for assessment.

 

b)       a Principal Certifying Authority (PCA) must be appointed to carry out the necessary building inspections and to issue an occupation certificate; and

 

c)       a principal contractor must be appointed for the building work, or in relation to residential building work, an owner-builder permit may be obtained in accordance with the requirements of the Home Building Act 1989, and the PCA and Council are to be notified accordingly; and

 

d)       the principal contractor must be advised of the required critical stage inspections and other inspections to be carried out, as specified by the Principal Certifying Authority; and

 

e)       at least two days notice must be given to the Council, in writing, prior to commencing any works.

 

In relation to residential building work, the principal contractor must be the holder of a contractor licence, in accordance with the provisions of the Home Building Act 1989.

 

Home Building Act 1989

19.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, the requirements of the Home Building Act 1989 must be complied with.

 

Details of the Licensed Building Contractor and a copy of the relevant Certificate of Home Warranty Insurance or a copy of the Owner-Builder Permit (as applicable) must be provided to the Principal Certifying Authority and Council, in writing.

 

Dilapidation Reports

20.     A dilapidation report prepared by a professional engineer, building surveyor or other suitably qualified independent person must be submitted to the satisfaction of the Principal Certifying Authority prior to commencement of any demolition, excavation or building works, in the following cases:

 

·           excavations for new dwellings, additions to dwellings, swimming pools or the like which are proposed to be located within the zone of influence of the footings of any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

 

·           new dwellings or additions to dwellings sited up to shared property boundaries (e.g.  additions to a semi-detached dwelling or terraced dwellings),

 

·           excavations for new dwellings, additions to dwellings, swimming pools or the like which are within rock and may result in vibration and or potential damage to any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

 

·           as otherwise may be required by the Principal Certifying Authority.

 

The report (including photographs) are required to detail the current condition and status of any dwelling, associated garage or other substantial structure located upon the adjoining premises, which may be affected by the subject works.  A copy of the dilapidation report is to be given to the owners of the premises encompassed in the report/s before commencing any works.

 

Construction Noise & Vibration Management Plan

21.     Noise and vibration emissions during the construction of the building and associated site works must not result in damage to nearby premises or result in an unreasonable loss of amenity to nearby residents and the relevant requirements of the Protection of the Environment Operations Act 1997 and NSW DECC Guidelines must be satisfied at all times.

 

Noise and vibration from any rock excavation machinery, pile drivers and all plant and equipment must be minimised, by using appropriate plant and equipment, silencers and the implementation of noise management strategies.

 

A Construction Noise Management Plan, prepared in accordance with the NSW DECC Construction Noise Guideline by a suitably qualified person, is to be implemented throughout the works.  A copy of the strategy must be provided to the Principal Certifying Authority and Council prior to the commencement of works.

 

Temporary Site Fencing

22.     Temporary site safety fencing must be provided to the perimeter of the site (unless the site is separated from the adjoining land by an existing structurally adequate fence, having a minimum height of 1.5 metres).  Temporary site fences are to have a minimum height of 1.8 metres and be constructed of cyclone wire fencing, with geotextile fabric attached to the inside of the fence to provide dust control, or other material approved by Council.

 

Temporary site fences are to be structurally adequate, safe and be constructed in a professional manner and the use of poor quality materials or steel reinforcement mesh as fencing is not permissible.

 

Temporary fences must be in place prior to the commencement of any demolition, excavation or building works and be maintained throughout construction.

 

If it is proposed to locate any site fencing, hoardings or amenities upon any part of the footpath, nature strip or public place, a Local Approval application must be submitted to and approved by Council’s Health, Building & Regulatory Services before placing any item or article on the road, footpath or nature strip.

 

Construction Site Management Plan

23.     A Construction Site Management Plan must be developed and implemented prior to the commencement of any works. The construction site management plan must include the following measures, as applicable to the type of development:

 

·          location and construction of protective fencing / hoardings to the perimeter of the site;

·          location of site storage areas/sheds/equipment;

·          location of building materials for construction;

·          provisions for public safety;

·          dust control measures;

·          site access location and construction

·          details of methods of disposal of demolition materials;

·          protective measures for tree preservation;

·          provisions for temporary sanitary facilities;

·          location and size of waste containers/bulk bins;

·          details of proposed sediment and erosion control measures;

·          provisions for temporary stormwater drainage;

·          construction noise and vibration management;

·          construction traffic management details.

 

The site management measures must be implemented prior to the commencement of any site works and be maintained throughout the works, to the satisfaction of Council.

 

A copy of the Construction Site Management Plan must be provided to the Principal Certifying Authority and Council prior to commencing site works.  A copy must also be maintained on site and be made available to Council officers upon request.

 

Demolition Work Plan

24.     A Demolition Work Plan must be prepared for the development in accordance with Australian Standard AS2601-2001, Demolition of Structures and relevant environmental/occupational health and safety requirements.

 

The Demolition Work Plan must include the following information (as applicable):

·          The name, address, contact details and licence number of the Demolisher /Asbestos Removal Contractor

·          Details of hazardous materials (including asbestos)

·          Method/s of demolition (including removal of any asbestos)

·          Measures and processes to be implemented to ensure the health & safety of workers and community

·          Measures to be implemented to minimise any airborne dust and asbestos

·          Methods and location of disposal of any hazardous materials

·          Other relevant details, measures and requirements to be implemented

·          Date the demolition works will commence

·          Recycling, reuse and waste disposal of remediation materials

 

The Demolition Work Plan must be submitted to the Principal Certifying Authority (PCA), not less than two (2) working days before commencing any demolition work.  A copy of the Demolition Work Plan must be maintained on site and be made available to Council officers upon request.

 

If the work involves asbestos products or materials, a copy of the Demolition Work Plan must also be provided to Council not less than 2 days before commencing those works.

 

Notes

§  It is the responsibility of the persons undertaking demolition work to obtain the relevant WorkCover licences and permits.

§  Refer to the conditions within the “Requirements During Construction & Site Work”, for further details and requirements relating to demolition work, removal of any asbestos and public safety.

 

Sydney Water

25.     All building, plumbing and drainage work must be carried out in accordance with the requirements of the Sydney Water Corporation.

 

Prior to the commencement of excavation or building works, the approved Construction Certificate plans must be submitted to a Sydney Water Quick Check agent or Customer Centre, to determine whether the development will affect Sydney Water’s sewer and water mains, stormwater drains and/or easements, and if any further requirements need to be met. 

 

If suitable, the plans will be appropriately stamped.  For Quick Check agent details please refer to Sydney Water’s web site at www.sydneywater.com.au and go to the Building, Developing and Plumbing, then Quick Check or Building and Renovating or telephone 13 20 92.

 

The principal certifying authority must ensure that a Quick Check Agent/Sydney Water has appropriately stamped the plans before commencing works.

 

Public Utilities

26.     A Public Utility Impact Assessment must be carried out to identify all public utility services located on the site, roadway, nature strip, footpath, public reserve or any public areas associated with and/or adjacent to the building works.

 

Documentary evidence from the relevant public utility authorities confirming that their requirements have been or are able to be satisfied, must be submitted to the Principal Certifying Authority prior to the commencement of any works.

 

The owner/builder must make the necessary arrangements and meet the full cost for telecommunication companies, gas providers, Energy Australia, Sydney Water and other authorities to adjust, repair or relocate their services as required.

 

REQUIREMENTS DURING CONSTRUCTION & SITE WORK

The following conditions of consent must be complied with during the demolition, excavation and construction of the development.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of public health, safety and environmental amenity during construction.

 

Demolition Work Requirements

27.     The demolition of buildings and the removal, storage, handling and disposal of building materials must be carried out in accordance with the relevant requirements of WorkCover NSW, the NSW Department of Environment, Climate Change & Water and Randwick City Council policies, including:

 

·          Occupational Health & Safety Act 2000 & Regulations

·          WorkCover NSW Code of Practice for the Safe Removal of Asbestos

·          WorkCover NSW Guidelines and Codes of Practice

·          Australian Standard 2601 (2001) – Demolition of Structures

·          The Protection of the Environment Operations Act 1997 and Protection of the Environment Operations (Waste) Regulation 2005

·          Relevant DECCW/EPA Guidelines

·          Randwick City Council Asbestos Policy

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development section or a copy can be obtained from Council’s Customer Service Centre.

 

Removal of Asbestos Materials

28.     Any work involving the demolition, storage or disposal of asbestos products and materials must be carried out in accordance with the following requirements:

 

·          Relevant Occupational Health & Safety legislation and WorkCover NSW requirements

 

·          Randwick City Council’s Asbestos Policy

 

·          A WorkCover licensed demolition or asbestos removal contractor must undertake removal of more than 10m2 of bonded asbestos (or as otherwise specified by WorkCover or relevant legislation).  Removal of friable asbestos material must only be undertaken by contractor that holds a current friable asbestos removal licence.  A copy of the relevant licence must be provided to the Principal Certifying Authority.

 

·          On sites involving the removal of asbestos, a sign must be clearly displayed in a prominent visible position at the front of the site, containing the words ‘DANGER ASBESTOS REMOVAL IN PROGRESS’ and include details of the licensed contractor.

 

·          Asbestos waste must be stored, transported and disposed of in compliance with the Protection of the Environment Operations Act 1997 and the Protection of the Environment Operations (Waste) Regulation 2005.  Details of the landfill site (which must be lawfully able to receive asbestos materials) must be provided to the Principal Certifying Authority.

 

·          A Clearance Certificate or Statement, prepared by a suitably qualified person (ie an occupational hygienist, licensed asbestos removal contractor, building consultant, architect or experienced licensed building contractor), must be provided to Council and the Principal certifying authority upon completion of the asbestos related works which confirms that the asbestos material have been removed appropriately and the relevant conditions of consent have been satisfied.

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development Section or a copy can be obtained from Council’s Customer Service Centre.

 

Site Signage

29.     A sign must be erected and maintained in a prominent position on the site for the duration of the works, which contains the following details:

 

·          name, address, contractor licence number and telephone number of the principal contractor, including a telephone number at which the person may be contacted outside working hours, or owner-builder permit details (as applicable)

·           name, address and telephone number of the Principal Certifying Authority,

·          a statement stating that “unauthorised entry to the work site is prohibited”.

 

Sediment & Erosion Control

30.     Sediment and erosion control measures, must be implemented throughout the site works in accordance with the manual for Managing Urban Stormwater – Soils and Construction, published by Landcom, to Council’s satisfaction.  Details are to be included in the Construction Site Management Plan.

 

Public Safety & Site Management

31.     Public safety and convenience must be maintained at all times during demolition, excavation and construction works and the following requirements must be complied with:

 

a)     Building materials, sand, soil, waste materials, construction equipment or other activities must not be placed upon the footpath, roadway or nature strip at any time and the footpath, nature strip and road must be maintained in a clean condition and free from any obstructions, soil and debris at all times.

 

b)     Stockpiles of soil, sand, aggregate or other materials must not be located on any footpath, roadway, nature strip, drainage line or any public place and the stockpiles must be protected with adequate sediment control measures.

 

c)     Building operations such as brick cutting, washing tools or equipment and mixing mortar are not permitted on public footpaths, roadways, nature strips, in any public place or any location which may lead to the discharge of materials into the stormwater drainage system.

 

d)     Bulk bins/waste containers must not be located upon the footpath, roadway or nature strip at any time without the prior written approval of the Council.  Applications to place a waste container in a public place can be made to Council’s Health, Building and Regulatory Services department.

 

e)     Any part of Council’s road, footway or nature strip which is damaged as a result of the work must be repaired or replaced to Council’s satisfaction.

 

f)     Temporary safety fencing is to be provided to any swimming pools under construction, pending the completion of all building work and the pool must not be filled until a fencing inspection has been carried out and approved by the principal certifying authority.

 

Support of Adjoining Land

32.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 E of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that the adjoining land and buildings located upon the adjoining land must be adequately supported at all times.

 

a)    If the development involves an excavation that extends below the level of the base of the footings of a building on adjoining land, the person having the benefit of the development must, at the person’s own expense:

 

i)     protect and support the adjoining premises from possible damage from the excavation, and

ii)     where necessary, underpin the adjoining premises to prevent any such damage.

b)    The condition referred to in subclause a) does not apply if the person having the benefit of the development consent owns the adjoining land or the owner of the adjoining land has given consent in writing to that condition not applying.

 

33.     Prior to undertaking any demolition, excavation or building work in the following circumstances, a report must be obtained from a professional engineer which details the methods of support for the dwelling or associated structure on the adjoining land, to the satisfaction of the Principal Certifying Authority:

 

·          when undertaking excavation or building work within the zone of influence of the footings of a dwelling or associated structure that is located on the adjoining land;

·          when undertaking demolition work to a wall of a dwelling that is built to a common or shared boundary (eg. semi-detached or terrace dwelling);

·          when constructing a wall to a dwelling or associated structure that is located within 900mm of a dwelling located on the adjoining land.

 

The demolition, excavation and building work and the provision of support to the dwelling or associated structure on the adjoining land, must also be carried out in accordance with the abovementioned report, to the satisfaction of the Principal Certifying Authority.

 

Restriction on Working Hours

34.     Building, demolition and associated site works must be carried out in accordance with the following requirements:

 

Activity

Permitted working hours

All building, demolition and site work, including site deliveries (except as detailed below)

·   Monday to Friday - 7.00am to 5.00pm

·   Saturday - 8.00am to 5.00pm

·   Sunday & public holidays - No work permitted

Excavating of rock, use of jack-hammers, pile-drivers, vibratory rollers/compactors or the like

 

·   Monday to Friday - 8.00am to 5.00pm

·   Saturday - No work permitted

·   Sunday & public holidays - No work permitted

 

An application to vary the abovementioned hours may be submitted to Council’s Manager Health, Building & Regulatory Services for consideration and approval to vary the specified hours may be granted in exceptional circumstances and for limited occasions (e.g. for public safety, traffic management or road safety reasons).  Any applications are to be made on the standard application form and include payment of the relevant fees and supporting information.  Applications must be made at least 10 days prior to the date of the proposed work and the prior written approval of Council must be obtained to vary the standard permitted working hours.

 

Inspections During Construction

35.     The building works must be inspected by the Principal Certifying Authority, in accordance with sections 109 E (3) of the Environmental Planning & Assessment Act 1979 and clause 162A of the Environmental Planning & Assessment Regulation 2000, to monitor compliance with the relevant standards of construction, Council’s development consent and the construction certificate.

 

The Principal Certifying Authority must specify the relevant stages of construction to be inspected and a satisfactory inspection must be carried out, to the satisfaction of the Principal Certifying Authority, prior to proceeding to the subsequent stages of construction or finalisation of the works (as applicable).

 

Building Encroachments

36.     There must be no encroachment of any structures or building work onto Council’s road reserve, footway, nature strip or public place.

 

REQUIREMENTS PRIOR TO THE ISSUE OF AN OCCUPATION CERTIFICATE

The following conditions of consent must be complied with prior to the ‘Principal Certifying Authority’ issuing an ‘Occupation Certificate’.

 

Note:        For the purpose of this consent, any reference to ‘occupation certificate’ shall also be taken to mean ‘interim occupation certificate’ unless otherwise stated.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent and to maintain reasonable levels of public health, safety and amenity.

 

Occupation Certificate Requirements

37.     An Occupation Certificate must be obtained from the Principal Certifying Authority prior to any occupation of the building work encompassed in this development consent (including alterations and additions to existing buildings), in accordance with the relevant provisions of the Environmental Planning & Assessment Act 1979.

 

An Occupation Certificate must not be issued for the development if the development is inconsistent with the development consent.  The relevant requirements of the Environmental Planning & Assessment Act 1979 and conditions of development consent must be satisfied prior to the issuing of an occupation certificate.

 

BASIX Requirements

38.     In accordance with Clause 154B of the Environmental Planning & Assessment Regulation 2000, a Certifying Authority must not issue an Occupation Certificate for this development, unless it is satisfied that each of the required BASIX commitments have been fulfilled.

 

Relevant documentary evidence of compliance with the BASIX commitments is to be forwarded to the Council upon issuing an Occupation Certificate.

 

Occupant Safety

39.     Openable windows to a room, corridor, stairway or the like with a floor level more than 4m above the external ground/surface level, must be designed and constructed to reduce the likelihood of a child accessing and falling through the window opening.

 

Options may include one or more of the following measures:

 

·          The window having a minimum sill height of 1.5m above the internal floor level,

·          Providing a window locking device at least 1.5m above the internal floor level,

·          Fixing or securing the window (e.g. by screws or a window locking device) to restrict or to be able to secure the extent of the opening to a maximum width of 125mm,

·          Installing a fixed heavy-duty gauge metal screen over the opening (e.g. A metal security screen or metal security mesh and frame system, but not standard fly-screen material),

·          Other appropriate effective safety measures or barrier.

 

Council’s Infrastructure, Vehicular Crossings & Road Openings

40.     All external civil work to be carried out on Council property (including the installation and repair of roads, footpaths, vehicular crossings, kerb and guttering and drainage works), must be carried out in accordance with Council's Policy for "Vehicular Access and Road and Drainage Works" and the following requirements:

 

a)     All work on Council land must be carried out by Council, unless specific written approval has been obtained from Council to use non-Council contractors.

 

b)     Details of the proposed civil works to be carried out on Council land must be submitted to Council in a Pre-paid Works Application Form, prior to issuing an occupation certificate, together with payment of the relevant fees.

 

c)     If it is proposed to use non-Council contractors to carry out the civil works on Council land, the work must not commence until the written approval has been obtained from Council and the work must be carried out in accordance with the conditions of consent, Council’s design details and payment of a Council design and supervision fee.

 

d)     The civil works must be completed in accordance with Council’s conditions of consent and approved design and construction documentation, prior to occupation of the development, or as otherwise approved by Council in writing.

 

OPERATIONAL CONDITIONS

The following operational conditions must be complied with at all times, throughout the use and operation of the development.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent and to maintain reasonable levels of public health and environmental amenity.

 

Use of premises

41.     The ‘secondary dwelling’ must only be used as a single residential dwelling and must not be used for dual or multi-occupancy purposes.

 

External Lighting

42.     External lighting to the premises must be designed and located so as to minimise light-spill beyond the property boundary or cause a public nuisance.

 

Protection of the Environment Operations Act 1997 – Air Conditioners

43.     The operation of all plant and equipment shall not give rise to an ‘offensive noise’ as defined in the Protection of the Environment Operations Act 1997 and Regulations.

 

In this regard, the operation of the plant and equipment shall not give rise to an LAeq, 15 min sound pressure level at any affected premises that exceeds the background LA90, 15 min noise level, measured in the absence of the noise source/s under consideration by more than 5dB(A) in accordance with relevant NSW Department of Environment & Conservation Noise Control Guidelines.

 

Air Conditioning & Equipment

44.     Air conditioning plant and equipment shall not be operated during the following hours if the noise emitted can be heard within a habitable room in any other residential premises, or, as otherwise specified in relevant Noise Control Regulations:

 

·      before 8.00am or after 10.00pm on any Saturday, Sunday or public holiday; or

·      before 7.00am or after 10.00pm on any other day.

 

ADVISORY NOTES

The following information is provided for your assistance to ensure compliance with the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, or other relevant legislation and Council’s policies.  This information does not form part of the conditions of development consent pursuant to Section 80A of the Act.

 

·          The requirements and provisions of the Environmental Planning & Assessment Act 1979 and Environmental Planning & Assessment Regulation 2000, must be fully complied with at all times.

 

Failure to comply with these requirements is an offence, which renders the responsible person liable to a maximum penalty of $1.1 million.  Alternatively, Council may issue a penalty infringement notice (for up to $1,500) for each offence.  Council may also issue notices and orders to demolish unauthorised or non-complying building work, or to comply with the requirements of Council’s development consent.

 

·          Demolition, building or excavation work must not be commenced until;

 

§  A Construction Certificate has been obtained from Council or an Accredited Certifier

§  Council or an Accredited Certifier has been appointed as the Principal Certifying Authority for the development

§  Council and the Principal Certifying Authority have been given at least 2 days notice (in writing) prior to commencing any works.

 

Council’s Building Approvals & Certification team can issue Construction Certificates and be your Principal Certifying Authority for the development, to undertake inspections and ensure compliance with the development consent, relevant building regulations and standards of construction.  For further details contact Council’s Building Approvals & Certification team on 9399 0944.

 

·          This determination does not include an assessment of the proposed works under the Building Code of Australia (BCA) and other relevant Standards.  All new building work (including alterations and additions) must comply with the BCA and relevant Standards and you are advised to liaise with your architect, engineer and building consultant prior to lodgement of your construction certificate.

 

·          A Local Approval application must be submitted to and be approved by Council's Building Approvals & Certification team prior to commencing any of the following activities on a footpath, road, nature strip or in any public place:-

 

§  Install or erect any site fencing, hoardings or site structures

§  Operate a crane or hoist goods or materials over a footpath or road

§  Placement of a waste skip or any other container or article.

 

For further information please contact Council’s Building Approvals & Certification team on 9399 0944.

 

·          Specific details of the location of the building/s should be provided in the Construction Certificate to demonstrate that the proposed building work will not encroach onto the adjoining properties, Council’s road reserve or any public place, to the satisfaction of the Certifying Authority.

 

·          Prior to commencing any works, the owner/builder should contact Dial Before You Dig on 1100 or www.dialbeforeyoudig.com.au and relevant Service Authorities, for information on potential underground pipes and cables within the vicinity of the development site.

 

MOTION: (Andrews/Mayor, Cr Matson) CARRIED UNANIMOUSLY - SEE RESOLUTION.

 

 

 

D107/11   Development Application Report - 10-20 Anzac Parade, Kensington (DA/161/2011)

PL127/11

RESOLUTION: (Andrews/Mayor, Cr Matson) -

 

A.     That Council supports the objections under State Environmental Planning Policy No. 1 – Development Standards in respect to non-compliance with Clauses 20F(1), 20G(2) and 20G(4)  of Randwick Local Environmental Plan 1998, relating to floor space ratio, maximum height and wall height respectively, on the grounds that the proposed development complies with the objectives of the above clauses, and will not adversely affect the amenity of the locality, and that the Department of Planning be advised accordingly.

 

B.     That Council, as the consent authority, grants development consent under Sections 80 and 80A of the Environmental Planning and Assessment Act 1979, as amended, to Development Application No. DA/161/2011 for construction of a 4 storey residential flat building with 31 units, basement car parking and associated landscape works at No. 10-20 Anzac Parade, Kensington,  subject to the following conditions:

 

REFERENCED PLANS:

 

1.     The development must be implemented substantially in accordance with the following plans:

 

Plan Number

Dated

Received

Prepared By

DA-02

June 2011

17/6/11

Fox Johnston

DA-03

June 2011

17/6/11

DA-04

June 2011

17/6/11

DA-05

June 2011

17/6/11

DA-06

June 2011

17/6/11

DA-07

June 2011

17/6/11

DA-08

June 2011

17/6/11

DA-09

June 2011

17/6/11

DA-10

June 2011

17/6/11

DA-11

June 2011

17/6/11

DA-12

June 2011

17/6/11

DA-13

June 2011

17/6/11

LA01

February 2011

10/3/11

Taylor Brammer

Landscape Architects P/L

LA02

February 2011

10/3/11

 

the application form and any supporting information received with the application, except as may be amended by the following conditions and as may be shown in red on the attached plans:

 

ENVIRONMENTAL AMENTITY:

 

The following conditions are applied to satisfy the provisions of section 79C of the Environmental Planning and Assessment Act 1979 and to maintain reasonable levels of environmental amenity:

2.     The colours, materials and finishes of the external surfaces to the building are to be compatible with adjacent development to maintain the integrity and amenity of the building and the streetscape.

 

Details of the proposed colours, materials and textures 9i.e a schedule and brochure/s or sample board) are to be submitted to and approved by Council’s Director City Planning in accordance with section 80A (2) of the Environmental Planning and Assessment Act 1979 prior to a construction certificate being issued for the relevant building works.

 

3.     Any proposed fences on the side or rear boundaries of the premises shall not exceed a maximum height of 1800mm, measured above the existing ground levels.

 

On sloping sites or at changes in ground levels, the maximum height of the fence may exceed the abovementioned specified height by up to 150mm maximum adjacent to any required ‘step-downs’ or changes in ground level.

 

The applicant and owner are advised that the relevant provisions of the Dividing Fences Act 1991 are to be satisfied accordingly and any necessary approvals or agreements should be obtained from the owner/s of the adjoining land beforehand.

 

3.     The front fence on the Anzac Parade street alignment must be a maximum height of 1200mm from the level of the footpath to maintain reasonable levels of amenity to the streetscape.     

 

4.     Mail boxes for each of the proposed dwelling units shall be installed at a suitable location to enable convenient access by Australia Post.

 

5.     Ceiling fans are to be installed in each dwelling unit.

 

6.     An outdoor clothes drying area is to be provided which is adequately screened from any public place.

 

7.     Suitable security lighting is to be installed at the main pedestrian entry path to the building. The above lighting device shall be low level lighting where the light source shall not be located higher than 1.2m above the finished ground level, and is to be directed towards the ground. Details demonstrating compliance are to be incorporated in the Construction Certificate documentation.

 

8.     Lighting to the premises shall be designed in accordance with Australian Standard AS 4282-1997: Control of the Obtrusive Effects of Outdoor Lighting so as not to cause a nuisance to nearby residents or motorists and to ensure that light overspill does not affect the amenity of the area.

 

9.     The enclosure of balconies is prohibited by this consent.

 

10.   The reflectivity index of glass used in the external façade of the proposed development must not exceed 20 percent.

 

11.   Street numbering must be provided to the premises in a prominent position, to the satisfaction of Council.

         

In this regard, prior to occupation of the building, an application must be submitted to and approved by Council’s Director of City Planning, together with the required fee, for the allocation of an appropriate street number/s to the development.

 

12.   Power supply and telecommunications cabling to the development shall be underground.

 

13.   A single common television aerial, and/or satellite dish (having a maximum diameter of 700mm and not located on the front or street elevation of the building) is to be installed to serve the development.

 

14.   The finished ground levels external to the building are to be consistent with the development consent and are not to be raised (other than for the provision of paving or the like on the ground) without the written consent of Council.

 

15.   In accordance with the provisions of clauses 143A and 154A of the Environmental Planning & Assessment Regulation 2000, a ‘Design Verification Certificate’ must be provided to the Certifying Authority and the Council, prior to issuing a construction certificate and an occupation certificate, respectively.

 

The following conditions are imposed to promote ecologically sustainable development and energy efficiency:

16.   In accordance with the provisions of the Environmental Planning & Assessment Regulation 2000, a relevant BASIX Certificate and associated documentation must be submitted to the Certifying Authority with the Construction Certificate application for this development.

 

The required commitments listed and identified in the BASIX Certificate are to be included on the plans, specifications and associated documentation for the proposed development, to the satisfaction of the Certifying Authority.

 

The design of the building must not be inconsistent with the development consent and any proposed variations to the building to achieve the BASIX commitments may necessitate a new development consent or amendment to the existing consent to be obtained, prior to a construction certificate being issued.

 

The following condition is applied to meet additional demands for public facilities:

17.   In accordance with Council’s Section 94A Development Contributions Plan effective from 2 July 2007, based on the development cost of $6,053,010.00 the following applicable monetary levy must be paid to Council: $60,053.00           

 

The levy must be paid in cash, bank cheque or by credit card prior to a construction certificate being issued for the proposed development. The development is subject to an index to reflect quarterly variations in the Consumer Price Index (CPI) from the date of Council’s determination to the date of payment.

 

Council’s Section 94A Development Contribution Plans may be inspected at the Customer Service Centre, Administrative Centre, 30 Frances Street, Randwick or at www.randwick.nsw.gov.au.

 

18.   Open-able windows to a room, corridor, stairway or the like with a floor level more than 4m above the external ground/surface level, must be designed and constructed to reduce the likelihood of a child accessing and falling through the window opening.

 

Options may include one or more of the following measures:

 

i)    The window having a minimum sill height of 1.5m above the internal floor level,

ii)   Providing a window locking device at least 1.5m above the internal floor level,

iii)   Fixing or securing the window (e.g. by screws or a window locking device) to restrict or to be able to secure the extent of the opening to a maximum of 125mm,

iv)  Installing a fixed heavy-duty gauge metal screen over the opening (e.g. A metal security screen or metal security mesh and frame system, but not standard fly-screen material),

v)   Other appropriate effective safety measures or barrier.

 

The following conditions are applied to ensure that the development satisfies the provisions of the Environmental Planning and Assessment Act 1979 and Regulations:

19.   The requirements and provisions of the Environmental Planning & Assessment Act 1979 and Environmental Planning & Assessment Regulation 2000, must be fully complied with at all times.

 

Failure to comply with these legislative requirements is an offence and may result in the commencement of legal proceedings, issuing of `on-the-spot` penalty infringements or service of a notice and order by Council.

 

20.   All new building work must be carried out in accordance with the provisions of the Building Code of Australia (BCA), in accordance with Clause 98 of the Environmental Planning and Assessment Regulation 2000.

 

21.   Prior to the commencement of any building works, a construction certificate must be obtained from the Council or an accredited certifier, in accordance with the provisions of the Environmental Planning & Assessment Act 1979 and Environmental Planning & Assessment Regulation 2000.

 

A copy of the construction certificate, the approved plans & specifications and development consent conditions must be kept on the site at all times and be made available to the Council officers and all building contractors for assessment.

 

22.   Prior to the commencement of any building works, the person having the benefit of the development consent must:

 

i)    appoint a Principal Certifying Authority for the building work, and

 

ii)   appoint a principal contractor for the building work, or in relation to residential building workand notify the Principal Certifying Authority and Council accordingly in writing, and

 

iii)   notify the principal contractor of the required critical stage inspections and other inspections to be carried out, as specified by the Principal Certifying Authority, and

 

iv)  give at least two days notice to the Council, in writing, of the persons intention to commence building works.

 

In relation to residential building work, the principal contractor must be the holder of a contractor licence, in accordance with the provisions of the Home Building Act 1989.

 

23.   The building works must be inspected by the Principal Certifying Authority (or another certifying authority if the Principal Certifying Authority agrees), in accordance with sections 109 E (3) of the Environmental Planning & Assessment Act 1979 and clause 162A of the Environmental Planning & Assessment Regulation 2000, to monitor compliance with the relevant standards of construction, Council’s development consent and the construction certificate.

 

The Principal Certifying Authority must specify the relevant stages of construction to be inspected in accordance with section 81A (2) (b1) (ii) of the Environmental Planning & Assessment Regulation 2000 and a satisfactory inspection must be carried out, to the satisfaction of the Principal Certifying Authority, prior to proceeding to the subsequent stages of construction or finalisation of the works (as applicable).

 

Documentary evidence of the building inspections carried out and details of compliance with Council’s consent is to be maintained by the Principal Certifying Authority.  Details of critical stage inspections carried out and copies of certification relied upon must also be forwarded to Council with the occupation certificate.

 

The principal contractor must ensure that the required critical stage and other inspections, as specified in the Principal Certifying Authority’s “Notice of Critical Stage Inspections”, are carried out to the satisfaction of the Principal Certifying Authority and at least 48 hours notice (excluding weekends and public holidays) is to be given to the Principal Certifying Authority, to carry out the required inspection, before carrying out any further works.

 

24.   A sign must be erected and maintained in a prominent position on the site for the duration of the works, which contains the following details:

 

·    name, address, contractor licence number and telephone number of the principal contractor, including a telephone number at which the person may be contacted outside working hours,

·    name, address and telephone number of the Principal Certifying Authority,

·    a statement stating that “unauthorised entry to the work site is prohibited”.

 

25.   An Occupation Certificate must be obtained from the Principal Certifying Authority prior to any occupation of the building in accordance with the relevant provisions of the Environmental Planning & Assessment Act 1979.

 

An Occupation Certificate must not be issued for the development if the development is inconsistent with the development consent.  The relevant requirements of the Environmental Planning & Assessment Act 1979 and conditions of development consent must be satisfied prior to the issuing of an occupation certificate.

 

26.   Prior to the issuing of an interim or final occupation certificate, a statement is required to be obtained from the Principal Certifying Authority, which confirms that the development is not inconsistent with the development consent and the relevant conditions of development consent have been satisfied.

 

Details of critical stage inspections carried out by the principal certifying authority together with any other certification relied upon must also be provided to Council with the occupation certificate.

 

27.   In accordance with clause 98 of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition, that in the case of residential building work, a contract of insurance must be obtained and in force, in accordance with the provisions of the Home Building Act 1989.

 

Where the work is to be done by a licensed contractor, excavation or building work must not be carried out unless the Principal Certifying Authority (PCA):

 

·    has been informed in writing of the licensee’s name and contractor number; and

·    is satisfied that the licensee has complied with the insurance requirements of Part 6 of the Home Building Act 1989, or

 

Where the work to be done by any other person (i.e. an owner-builder), excavation or building work must not be carried out unless the Principal Certifying Authority:

 

·    has been informed of the person’s name and owner-builder permit number, or

·    has been given a declaration, signed by the owner of the land that states that the market cost of the labour and materials involved in the work does not exceed $5,000.

 

Details of the principal building contractor and compliance with the provisions of the Home Building Act 1989 (i.e. Details of the principal licensed building contractor and a copy of the Certificate of Insurance) are to be submitted to Council prior to the commencement of works, with the notice of appointment of the PCA / notice of intention to commence building work.

 

28.   The required Long Service Levy payment, under the Building and Construction Industry Long Service Payments Act 1986, is to be forwarded to the Long Service Levy Corporation or the Council, prior to the issuing of a Construction Certificate, in accordance with Section 109F of the Environmental Planning & Assessment Act 1979.

 

At the time of this development consent, Long Service Levy payment is applicable on building work having a value of $25,000 or more, at the rate of 0.35% of the cost of the works.

 

29.   A Fire Safety Certificate must be submitted to Council prior to the issuing of an Occupation Certificate, in accordance with the requirements of the Environmental Planning and Assessment Regulation 2000.

 

A single and complete Fire Safety Certificate must be provided which includes details of all of the fire safety measures contained in the building and as detailed in the fire safety schedule attached to the Construction Certificate.

 

Prior to issuing any Occupation Certificate the Principal Certifying Authority must be satisfied that all of the relevant fire safety measures have been included and are sufficiently detailed within the Fire safety Certificate.

 

A copy of the fire safety certificate must be displayed in the building near the entrance and a copy must be forwarded to the NSW Fire Brigades.

 

30.   As a minimum, the building is required to be provided with a smoke alarm system complying with Clause 3 of Specification E2.2a of the Building Code of Australia or a smoke detection system complying with Clause 4 of Specification E2.2a of the Building Code of Australia or a combination of a smoke alarm system within the sole-occupancy units and a smoke detection system in areas not within the sole-occupancy units.  The smoke detectors located within the stairway, corridors or the like must be interconnected.

 

Additional requirements regarding the design and installation of the smoke detection and alarm system may be specified in the construction certificate for the development.

 

31.   All building, plumbing and drainage work must be carried out in accordance with the requirements of the Sydney Water Corporation.

 

The approved Construction Certificate plans must be submitted to a Sydney Water Quick Check agent or Customer Centre prior to commencing any building or excavation works, to determine whether the development will affect Sydney Water’s sewer and water mains, stormwater drains and/or easements, and if any further requirements need to be met. 

 

If suitable, the plans will be appropriately stamped.  For Quick Check agent details please refer to Sydney Water’s web site at www.sydneywater.com.au and go to the Building, Developing and Plumbing, then Quick Check or Building and Renovating or telephone 13 20 92.

 

The principal certifying authority must ensure that a Quick Check Agent/Sydney Water has appropriately stamped the plans before commencing any works.

 

The following group of conditions have been applied to ensure the structural adequacy and integrity of the proposed building and adjacent premises:

 

32.   A report shall be prepared by a professional engineer and submitted to the certifying authority prior to the issuing of a construction certificate, detailing the proposed methods of excavation, shoring or pile construction, including details of potential vibration emissions. The report, must demonstrate the suitability of the proposed methods of construction to overcome any potential damage to nearby land/premises.

 

Any practices or procedures specified in the engineer’s report in relation to the avoidance or minimisation of structural damage to nearby premises, must be fully complied with and incorporated into the documentation for the construction certificate.

 

A copy of the engineers report is to be submitted to the Council, if the Council is not the certifying authority.

 

33.   Driven type piles/shoring must not be provided unless a geotechnical engineer’s report is submitted to the certifying authority, prior to the issuing of a construction certificate, which demonstrates that damage should not occur to any adjoining premises and public place as a result of the works.

 

Any practices or recommendations specified in the engineer’s report in relation to the avoidance or minimisation of structural damage to nearby premises or land must be fully complied with and incorporated into the documentation for the construction certificate.

 

34.   A dilapidation report prepared by a professional engineer or suitably qualified and experienced building surveyor shall be submitted to the certifying authority prior to the commencement of demolition, excavation or building works detailing the current condition and status of all buildings, including ancillary structures (i.e. including dwellings, residential flat buildings, commercial/industrial building, garages, carports, verandah’s, fences, retaining walls, swimming pools and driveways etc.) located upon all of the premises adjoining the subject site.

 

The report is to be supported with photographic evidence of the status and condition of the buildings and a copy of the report must also be forwarded to the Council and to the owners of each of the abovementioned premises, prior to the commencement of any works.

 

35.   The installation of ground or rock anchors underneath any adjoining premises must not be carried out without specific written consent of the owners of the affected adjoining premises (including the Council if bounding a public roadway or public place) and where applicable, details of compliance must be provided to the certifying authority prior to the commencement of any excavation or building works.

 

36.   A Certificate prepared by a professional engineer shall be submitted to the certifying authority (and the Council, if the Council is not the certifying authority) prior to occupation of the building, which certifies that the building works satisfy the relevant structural design requirements of the Building Code of Australia.

 

The following conditions are applied to ensure that the development satisfies relevant standards of construction, and to maintain adequate levels of health, safety and amenity during construction:

 

37.   All excavations and backfilling associated with the erection or demolition of a building must be executed safely in accordance with appropriate professional standards and excavations are to be properly guarded and supported to prevent them from being dangerous to life, property or buildings.

 

Retaining walls, shoring or piling must be provided to support land which is excavated in association with the erection or demolition of a building, to prevent the movement of soil and to support the adjacent land and buildings, if the soil conditions require it.  Adequate provisions are also to be made for drainage.

 

Retaining walls, shoring, or piling must be designed and installed in accordance with appropriate professional standards and the relevant requirements of the Building Code of Australia and Australian Standards.  Details of proposed retaining walls, shoring or piling are to be submitted to and approved by the Principal Certifying Authority for the development prior to commencing such excavations or works.

 

38.   The adjoining land and buildings located upon the adjoining land must be adequately supported at all times.

 

If an excavation associated with the erection or demolition of a building extends below the level of the base of the footings of any building located on an adjoining allotment of land, the person causing the excavation must:

 

·     preserve and protect the building /s on the adjoining land from damage; and

·     effectively support  the excavation and building; and

·     at least seven (7) days before excavating below the level of the base of the footings of a building on an adjoining allotment of land (including a public road or public place), give notice of the intention and particulars of the works to the owner of the adjoining land.

 

Notes

·    This consent and condition does not authorise any trespass or encroachment upon any adjoining or supported land or building whether private or public.  Where any underpinning, shoring, soil anchoring (temporary or permanent) or the like is proposed to be carried out upon any adjoining or supported land, the principal contractor or owner-builder must obtain:

a)     the consent of the owners of such adjoining or supported land to trespass or encroach, or

b)     an access order under the Access to Neighbouring Land Act 2000, or

c)     an easement under section 88K of the Conveyancing Act 1919, or

d)     an easement under section 40 of the Land & Environment Court Act 1979, as appropriate.

 

·    Section 177 of the Conveyancing Act 1919 creates a statutory duty of care in relation to support of land.  Accordingly, a person has a duty of care not to do anything on or in relation to land being developed (the supporting land) that removes the support provided by the supporting land to any other adjoining land (the supported land).

 

39.   Except with the written approval of Council’s Manager of Health, Building & Regulatory Services, all building, demolition and associated site works (including site deliveries) must only be carried out between the hours of 7.00am to 5.00pm on Monday to Friday inclusive and (except as detailed below) between 8.00am to 5.00pm on Saturdays.

 

All building, demolition and associated site works are strictly prohibited on Sundays, Public Holidays and also on Saturdays adjacent to a Public Holiday.

 

In addition, the use of any rock excavation machinery or any mechanical pile drivers or the like is restricted to the hours of 8.00am to 5.00pm (maximum) on Monday to Friday only, to minimise the noise levels during construction and loss of amenity to nearby residents.

 

40.   Noise and vibration emissions during the construction of the building and associated site works must not result in damage to nearby premises or result in an unreasonable loss of amenity to nearby residents and the relevant provisions of the Protection of the Environment Operations Act 1997 must be satisfied at all times.

 

Noise and vibration from any rock excavation machinery and pile drivers (or the like) must be minimised by using appropriate plant and equipment and silencers and a construction noise and vibration minimisation strategy, prepared by a suitably qualified consultant is to be implemented during the works, to the satisfaction of the Principal Certifying Authority.

 

41.   Public safety and convenience must be maintained at all times during demolition, excavation and construction works and the following requirements must be complied with:

 

a)     The roadway, footpath and nature strip must be maintained in a good, safe condition and free from any obstructions, materials, soils or debris at all times.  Any damage caused to the road, footway or nature strip must be repaired immediately, to the satisfaction of Council.

 

b)     Building materials, sand, soil, waste materials, construction equipment or other materials or articles must not be placed upon the footpath, roadway or nature strip at any time and the footpath, nature strip and road must be maintained in a clean condition and free from any obstructions, soil and debris at all times.

 

c)     Bulk bins, waste containers or other articles must not be located upon the footpath, roadway or nature strip at any time without the prior written approval of the Council.  Applications to place a waste container or other articles in a public place can be made to Council’s Health, Building & Regulatory Services department.

 

d)     Building operations such as brick cutting, washing tools or equipment and mixing mortar are not permitted on public footpaths, roadways, nature strips, in any public place or any location which may lead to the discharge of materials into the stormwater drainage system.

 

e)     A temporary timber, asphalt or concrete crossing is to be provided to the site entrance across the kerb and footway area, with splayed edges, to the satisfaction of Council, unless access is via an existing concrete crossover.

 

f)      A local approval application must be submitted to and be approved by Council's Building Services section prior to commencing any of the following activities on a footpath, road or nature strip or in any public place:-

 

·       Install or erect any site fencing, hoardings or site structures

·       Operate a crane or hoist goods or materials over a footpath or road

·       Placement of a waste skip or any other container or article on the road, nature strip or footpath.

 

g)     The applicant/builder is required to hold Public Liability Insurance, with a minimum liability of $10 million and a copy of the Insurance cover is to be provided to Council.

 

h)     A Road / Asset Opening Permit must be obtained from Council prior to carrying out any works within or upon a road, footpath, nature strip or in any public place, in accordance with section 138 of the Roads Act 1993 and all of the conditions and requirements contained in the Road / Asset Opening Permit must be complied with.

 

The owner/builder must ensure that all works within or upon the road reserve, footpath, nature strip or other public place are completed to the satisfaction of Council, prior to the issuing of a final occupation certificate for the development.

 

For further information, please contact Council’s Road / Asset Opening Officer on 9399 0691 or 9399 0999.

 

a)     Temporary toilet facilities are to be provided, at or in the vicinity of the work site throughout the course of demolition and construction, to the satisfaction of WorkCover NSW and the toilet facilities must be connected to a public sewer or other sewage management facility approved by Council.

 

42.   A Registered Surveyor’s check survey certificate or compliance certificate is to be forwarded to the principal certifying authority (and a copy is to be forwarded to the Council, if the Council is not the principal certifying authority), detailing compliance with Council’s approval at the following stage/s of construction:

 

a)     Prior to construction of the first completed floor/floor slab (prior to pouring of concrete), showing the area of land, building and boundary setbacks and verifying that the building is being construction at the approved levels.

 

b)     On completion of the erection of the building showing the area of the land, the position of the building and boundary setbacks and verifying the building has been constructed at the approved levels.

 

43.   A Construction Site Management Plan is to be developed and implemented prior to the commencement of demolition, excavation or building works. The site management plan must include the following measures, as applicable to the type of development:

 

·       location and construction of protective fencing / hoardings to the perimeter of the site;

·       location of site storage areas/sheds/equipment;

·       location of building materials for construction;

·       provisions for public safety;

·       dust control measures;

·       site access location and construction;

·       details and methods of disposal of demolition materials;

·       protective measures for tree preservation;

·       provisions for temporary sanitary facilities;

·       location and size of waste containers/bulk bins;

·       details of proposed sediment and erosion control measures;

·           construction noise and vibration management;

·           construction traffic management provisions.

 

The site management measures are to be implemented prior to the commencement of any site works and be maintained throughout the works, to maintain reasonable levels of public health, safety and convenience to the satisfaction of Council.  A copy of the approved Construction Site Management Plan must be maintained on site and be made available to Council officers upon request.

 

44.   During demolition excavation and construction works, dust emissions must be minimised, so as not to result in a nuisance to nearby residents or result in a potential pollution incident.

 

Adequate dust control measures must be provided to the site prior to the works commencing and the measures and practices must be maintained throughout the demolition, excavation and construction process, to the satisfaction of Council.

 

Dust control measures and practices may include:-

 

·       Provision of geotextile fabric to all perimeter site fencing (attached on the prevailing wind side of the site fencing).

·       Covering of stockpiles of sand, soil and excavated material with adequately secured tarpaulins or plastic sheeting.

·       Installation of a water sprinkling system or provision hoses or the like.

·       Regular watering-down of all loose materials and stockpiles of sand, soil and excavated material.

·       Minimisation/relocation of stockpiles of materials, to minimise potential for disturbance by prevailing winds.

·       Revegetation of disturbed areas.

 

45.   During construction stages, sediment laden stormwater run-off shall be controlled using the sediment control measures outlined in the manual for Managing Urban Stormwater – Soils and Construction, published by the NSW Department of Housing.

 

Details of the proposed sediment control measures are to be detailed in the Site Management Plan and must be submitted to and approved by the principal certifying authority prior to the commencement of any site works.  The sediment and erosion control measures must be implemented prior to the commencement of any site works and be maintained throughout construction.  A copy of the approved details must be forwarded to the Council and a copy is to be maintained on-site and be made available to Council officers upon request.

 

Details of proposed sediment and erosion control measures shall include; a site plan; indicating the slope of land, access points & access control measures, location and type of sediment & erosion controls, location of existing vegetation to be retained, location of material stockpiles and storage areas, location of building operations and equipment, methods of sediment control, details of drainage systems and details of existing and proposed vegetation.

 

Stockpiles of soil, sand, aggregate or other materials must not be located on any footpath, roadway, nature strip, drainage line or any public place and the stockpiles must be protected with adequate sediment control measures.

 

A warning sign for soil and water management must be displayed in a prominent position on the building site, visible to both the public and site workers.  The sign must be displayed throughout the construction period.  Copies of a suitable warning sign are available at Council’s Customer Service Centre for a nominal fee.

 

46.   Public safety must be maintained at all times and public access to the site and building works, materials and equipment on the site is to be restricted, when work is not in progress or the site is unoccupied.

 

A temporary safety fence is to be provided to protect the public, located to the perimeter of the site (unless the site is separated from the adjoining land by an existing structurally adequate fence, having a minimum height of 1.5 metres).  Temporary fences are to have a minimum height of 1.8 metres and be constructed of cyclone wire fencing, with geotextile fabric attached to the inside of the fence to provide dust control, or other material approved by Council.

 

If the work involved in the erection or demolition of a building is likely to cause pedestrian or vehicular traffic in a public place to be obstructed or rendered inconvenient or the building involves the enclosure of a public place, a hoarding or fence must be erected between the work site and the public place.

 

If necessary, an awning is to be erected sufficiently to prevent any substance from, or in connection with, the work from falling into the public place or adjoining premises.

 

Temporary fences or hoardings are to be structurally adequate, safe and be constructed in a professional manner and the use of poor quality materials or steel reinforcement mesh as fencing is not permissible.

 

The public safety provisions and temporary fences must be in place prior to the commencement of any demolition, excavation or building works and be maintained throughout construction.

 

If it is proposed to locate any site fencing, hoardings or amenities upon any part of the footpath, nature strip or any public place, the written consent from Council’s Building Services section must be obtained beforehand and detailed plans are to be submitted to Council for consideration, together with payment of the weekly charge in accordance with Council’s adopted fees and charges.

 

47.   The demolition, removal, storage, handling and disposal of  materials and all building work must be carried out in accordance with the following requirements (as applicable):

 

§   Australian Standard 2601 (2001) – Demolition of Structures

§   Occupational Health and Safety Act 2000

§   Occupational Health and Safety (Hazardous Substances) Regulation 2001

§   Occupational Health and Safety (Asbestos Removal Work) Regulation 2001

§   WorkCover NSW – Guidelines and Codes of Practice

§   Randwick City Council’s Asbestos Policy

§   The Protection of the Environment Operations Act 1997 and Protection of the Environment Operations (Waste) Regulation 1996.

 

48.   A Demolition Work Plan must be prepared for the development in accordance with Australian Standard AS2601-2001, Demolition of Structures.

 

The Work Plan must include the following information (as applicable):

 

§   The name, address, contact details and licence number of the Demolisher /Asbestos Removal Contractor

§   Details of hazardous materials, including asbestos

§   Method/s of demolition and removal of asbestos

§   Measures and processes to be implemented to ensure the health & safety of workers and community

§   Measures to be implemented to minimise any airborne asbestos and dust

§   Methods and location of disposal of any asbestos or other hazardous materials

§   Other relevant details, measures and requirements to be implemented as identified in the Asbestos Survey

§   Date the demolition and removal of asbestos will commence

 

The Demolition Work Plan must be submitted to the Principal Certifying Authority (PCA), not less than two (2) working days before commencing any demolition works.  A copy of the Demolition Work Plan must be forwarded to Council and a copy must also be maintained on site and be made available to Council officers upon request.

 

49.   Any work involving the demolition, storage and disposal of asbestos products and materials must be carried out in accordance with the following requirements:

 

a)     Randwick City Council’s Asbestos Policy (adopted 13 September 2005).

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development section or a copy can be obtained from Council’s Customer Service Centre.

 

b)     A WorkCover licensed demolition or asbestos removal contractor must undertake removal of more than 10m2 of bonded asbestos (or as otherwise specified by WorkCover or relevant legislation).  Removal of friable asbestos material must only be undertaken by contractor that holds a current friable asbestos removal licence.

 

c)     On sites involving the removal of asbestos, a  professionally manufactured sign must be clearly displayed in a prominent visible position at the front of the site, containing the words ‘DANGER ASBESTOS REMOVAL IN PROGRESS” and include details of the licensed contractor.  The sign shall measure not less than 400mm x 300mm and the sign is to be installed prior to demolition work commencing and is to remain in place until such time as all asbestos has been safely removed from the site.

 

d)     Asbestos waste must be stored, transported and disposed of in compliance with the Protection of the Environment Operations Act 1997 and the Protection of the Environment Operations (Waste) Regulation 1996. Asbestos waste must be disposed of at an approved waste disposal depot (refer to the DEC or Waste Service NSW for details of sites). Copies of all receipts detailing method and location of disposal must be maintained on site and be provided to Council officers upon request, as evidence of correct disposal.

 

e)     A Clearance Certificate or Statement, prepared by a suitably qualified person (i.e. an occupational hygienist, licensed asbestos removal contractor, building consultant, architect or experienced licensed building contractor), must be provided to Council upon completion of the works prior to an Occupation Certificate being issued, which confirms that the asbestos material have been removed appropriately and the relevant requirements contained in the Asbestos Survey and conditions of consent in relation to the safe removal and disposal of asbestos, have been satisfied.

 

Security Deposit Conditions

The following conditions are applied to provide adequate security against damage to Council’s infrastructure:

 

50.   The following damage/civil works security deposit requirement is to be complied with prior to a construction certificate being issued for the development, as security for making good any damage caused to the roadway, footway, verge or any public place; or as security for completing any public work; and for remedying any defect on such public works, in accordance with section 80A(6) of the Environmental Planning and Assessment Act 1979:

 

a)     $5000.00   -      Damage / Civil Works Security Deposit

 

The damage/civil works security deposit may be provided by way of a cash or cheque with the Council and is refundable upon:

 

·      A satisfactory inspection by Council that no damage has occurred to the Council assets such as roadway, kerb, guttering, drainage pits footway, or verge; and

 

·      Completion of the civil works as conditioned in this development consent by Council.

The applicant is to advise Council, in writing, of the completion of all building works and/or obtaining an occupation certificate, if required.

 

The applicant is to advise Council in writing and/or photographs of any signs of existing damage to the Council roadway, footway, or verge prior to the commencement of any building/demolition works.

 

Traffic conditions/Civil Works Conditions

The following conditions are applied to provide adequate provisions for access, transport and infrastructure:

 

51.   Prior to the issuing of an Occupation Certificate the applicant must meet the full cost for Council or a Council approved contractor to:

 

a)   Construct a full width concrete heavy duty vehicular crossing and layback at kerb opposite the vehicular entrance to the site in Abbotford Lane.

 

b)   Remove any redundant concrete vehicular crossings and laybacks and to reinstate the area to Council's specification.

 

c)   Construct kerb and gutter for the full Abbotford Lane site frontage except opposite the vehicular entrance and exit points.

 

d)   Construct kerb and gutter for the full Tay Lane site frontage.

 

e)   Carry out a full depth, minimum 1.0 metre wide, road construction in front of the new kerb and gutter along the full Abbotford Lane and Tay lane site frontages.

 

f)    Reconstruct the concrete footpath along the full Anzac Parade site frontage.  Any unpaved areas on the nature strip must be turfed and landscaped to Council’s specification.

 

52.   The applicant must meet the full cost for Council or a Council approved contractor to repair/replace any damaged sections of Council's footpath, kerb & gutter, nature strip etc which are due to building works being carried out at the above site. This includes the removal of cement slurry from Council's footpath and roadway.

 

53.   All external civil work to be carried out on Council property (including the installation and repair of roads, footpaths, vehicular crossings, kerb and guttering and drainage works), must be carried out in accordance with Council’s Policy for “Vehicular Access and Road and Drainage Works” and the following requirements:

 

a)   All work on Council land must be carried out by Council, unless specific written approval has been obtained from Council to use non-Council contractors.

 

b)   Details of the proposed civil works to be carried out on Council land must be submitted to Council in a Pre-paid Works Application Form, prior to issuing an occupation certificate, together with payment of the relevant fees.

 

c)   If it is proposed to use non-Council contractors to carry out the civil works on Council land, the work must not commence until the written approval has been obtained from Council and the work must be carried out in accordance with the conditions of consent, Council’s design details and payment of a Council design and supervision fee.

 

d)   The civil works must be completed in accordance with Council’s conditions of consent and approved design and construction documentation, prior to occupation of the development, or as otherwise approved by Council in writing.

 

54.   All new walls adjacent to vehicular crossings must be lowered to a height of 600mm above the internal driveway level for a distance of 1.50m within the site or splayed 1.5 metre by 1.5 metre to provide satisfactory sight lines. Details are to be submitted to the Certifying Authority prior to the release of the construction certificate showing compliance with this condition.

 

55.   The driveway opening at the Abbotford Lane Street frontage must be a minimum of 5.5 metres wide and located at least 1.0 metre clear of the side property.

 

56.   The internal driveway must be a minimum 5.50m wide (clear width) for the first 6 metres inside the property so as to allow entering & exiting vehicles to pass within the site. Should the driveway narrow after this point it is then to be designed with a minimum 1.5m x 1.5m splay to allow the passing to work. The Construction Certificate plans must demonstrate that 2 vehicles can pass one another whilst wholly within the site.

 

57.   The vehicular access driveways, internal circulation ramps and the carpark areas, (including, but not limited to, the ramp grades, carpark layout and height clearances) are to be in accordance with the requirements of AS2890.1:2004. All internal circulation ramps must either be designed for two way traffic flows along their entire length or alternatively a suitable signal system must be installed. The Construction Certificate plans must demonstrate compliance with these requirements.

 

58.   Full design and operational details of any signal system for one way ramps (i.e ramps 3.6 metres in width or less) must be submitted to the Certifying Authority for approval and be approved prior to the issuing of a Construction Certificate.

 

59.   Prior to the issuing of an Occupation Certificate the applicant must dedicate a strip of land to Council along the full Tay Lane and Abbotford Lane site frontages for road widening of these laneways. The width of the dedication shall be sufficient to enable a minimum 1.3 metre wide footpath to be constructed in both laneways along the full site frontages. The applicant is advised that the strip of land will be approximately 0.7 metres in width. All costs associated with dedication of the land are to be met by the applicant.

 

60.   A 3 metre by 1.5 metre splay corner must be provided at the intersection of Anzac Parade and Tay Lane. A 1.5 metre by 1.5 metre splay corner must be provided at the intersection of Abbotford Lane and Tay Lane. The splays must be to council’s satisfaction and details of the splays must be shown on the Construction Certificate plans. The splay corners must be formally dedicated to Council as public road prior to the issuing of an Occupation Certificate. The splay corners must be provided based on the Tay Lane and Abbotford Lane boundaries post dedication of the above referenced strips of land. All costs associated with dedication of the land are to be met by the applicant.

 

61.   Prior to the commencement of any works on the site, an application for a ‘Works Zone’, together with a detailed Construction Traffic Management Plan (CTMP) must be submitted to Councils Integrated Transport Department.  The CTMP must be approved by Council prior to the commencement of works on the site.

 

The ‘Works Zone’ must have a minimum length of 12m and extend for a minimum duration of three months.  The suitability of the proposed length, duration and location is to be demonstrated in the application for the Works Zone.  The application for the Works Zone must be submitted to Council at least six (6) weeks prior to the commencement of work on the site to allow for assessment and tabling of agenda for the Randwick Traffic Committee.

 

The requirement for a Works Zone may be varied or waived only if it can be demonstrated in the Construction Traffic Management Plan (to the satisfaction of Council’s Traffic Engineers) that all construction related activities (including all loading and unloading operations) can and will be undertaken wholly within the site.  The written approval of Council must be obtained to provide a Works Zone or to waive the requirement to provide a Works Zone prior to the commencement of any site work.

 

Alignment Level Conditions

The following conditions are applied to provide adequate provisions for future civil works in the road reserve:

 

62.   The Council’s Development Engineer has inspected the above site and has determined that the design alignment level (concrete/paved/tiled level) at the Anzac Parade property boundary for driveways, access ramps and pathways or the like, must be 2.5%above the top of the kerb opposite at all points along the Anzac Parade frontage.

 

63.   The design alignment levels for the Tay Lane and Abbotford Lane site frontages must be obtained in writing from Council’s Development Engineer Coordinator prior to lodgement of a Construction Certificate Application.

 

The design alignment level at the property boundary must be strictly adhered to.

 

64.   The design alignment levels (concrete/paved/tiled level) issued by Council and their relationship to the roadway/kerb/footpath must be indicated on the building plans for the construction certificate.

 

65.   The above alignment levels and the site inspection by Council’s Development Engineer has been issued at a prescribed fee of $1945 calculated at $44.00 (inclusive of GST) per metre of site frontage to Anzac Parade. This amount is to be paid prior to a construction certificate being issued for the development.

 

Service Authority Conditions

The following conditions are applied to provide adequate consideration for service authority assets:

66.   A public utility impact assessment must be carried out on all public utility services on the site, roadway, nature strip, footpath, public reserve or any public areas associated with and/or adjacent to the development/building works and include relevant information from public utility authorities and exploratory trenching or pot-holing, if necessary, to determine the position and level of service.

 

67.   The applicant must meet the full cost for telecommunication companies, gas providers, Energy Australia and Sydney Water to adjust/repair/relocate their services as required.  The applicant must make the necessary arrangements with the service authority.

 

68.   Documentary evidence from the relevant public utility authorities confirming that their requirements have been satisfied, must be submitted to the certifying authority prior to a construction certificate being issued for the development.

 

69.   A Road / Asset Opening Permit must be obtained from Council prior to carrying out any public utility service works within or upon a road, footpath, nature strip or in any public place, in accordance with section 138 of the Roads Act 1993 and all of the conditions and requirements contained in the Road / Asset Opening Permit must be complied with.

                                         

The owner/builder must ensure that all works within or upon the road reserve, footpath, nature strip or other public place are completed to the satisfaction of Council, prior to the issuing of a final occupation certificate for the development.

 

For further information, please contact Councils Road / Asset Opening Officer on 9399 0691 or 9399 0999.

 

70.   Any electricity substation required for the site as a consequence of this development shall be located within the site and shall be screened from view. The proposed location and elevation shall be shown on all detailed landscape drawings and specifications. The applicant must liaise with Energy Australia prior to lodging the construction certificate to determine whether or not an electricity substation is required for the development.

 

71.   The applicant shall meet the full cost of the overhead power lines and telecommunication cables located in the vicinity of the development site to be relocated underground and all redundant power poles to be removed. The applicant shall liaise directly with the relevant service utility authorities to organise for the wires/cables to be relocated. All wires cables must be relocated underground to the satisfaction of the relevant service utility authority prior to the issuing of an occupation certificate for the development.

 

72.   A Section 73 Compliance Certificate under the Sydney water Act 1994 must be obtained. Application must be made through an authorised Water Servicing Coordinator. Please refer to “Your Business” section of Sydney Water’s web site at www.sydneywater.com.au then the “e-developer” icon or telephone 13 20 92.

 

Following application a “Notice of Requirements” will detail water and sewer extensions to be built and charges paid. Please make early contact with the Coordinator, since building of water/sewer extensions can be time consuming and may impact on other services and building, driveway or landscape design.

 

The Notice must be issued to the Principal Certifying Authority prior to the construction certificate being issued.

 

The Section 73 Certificate must be submitted to the Principal Certifying Authority prior to occupation of the development.

 

Drainage Conditions

The following conditions are applied to provide adequate provisions for drainage and associated infrastructure:

 

Protection from flooding

73.   The floor level of all habitable and storage areas shall be at a minimum RL of 31.20 metres (AHD) or suitably waterproofed up to this same level.

 

74.   The proposed internal driveway (and any other openings into the basement carpark) must be designed with a high point at least RL 31.20 metres (AHD). The plans submitted for the construction certificate shall demonstrate compliance with this requirement.

 

75.   All windows, vents and other openings into the basement carparks must be located at least 500 mm above the determined 1 in 100 year flood level.

 

76.   All structural walls on the ground floor level shall be designed to structurally withstand hydrostatic pressure/stormwater inundation from floodwater during the probable maximum flood (PMF) event as defined in the Floodplain Development Manual (New South Wales Government, April 2005). Structural Engineering certification confirming that this condition has been complied with shall be submitted to the certifying authority prior to the issuing of a construction certificate.

 

It is noted that this requirement does not necessitate the development being flood proof/water tight up to the PMF event, rather the requirement is to ensure that the development will not be structurally damaged in manner that could endanger lives during the PMF event.

 

Internal Drainage

77.   Stormwater drainage plans have not been approved as part of this development consent. Engineering calculations and plans with levels reduced to Australian Height Datum in relation to site drainage shall be submitted to and approved by the certifying authority prior to a construction certificate being issued for the development. A copy of the engineering calculations and plans are to be forwarded to Council, prior to a construction certificate being issued, if the Council is not the certifying authority. The drawings and details shall include the following information:

 

a)   A detailed drainage design supported by a catchment area plan, at a scale of 1:100 or as considered acceptable to the Council or an accredited certifier, and drainage calculations prepared in accordance with the Institution of Engineers publication, Australian Rainfall and Run-off, 1987 edition.

 

b)   A layout of the proposed drainage system including pipe sizes, type, grade, length, invert levels, etc., dimensions and types of all drainage pipes and the connection into Council's stormwater system. 

 

c)   Generally all internal pipelines must be capable of discharging a 1 in 20 year storm flow.  However the minimum pipe size for pipes that accept stormwater from a surface inlet pit must be 150mm diameter.  The site must be graded to direct any surplus run-off (ie. above the 1 in 20 year storm) to the proposed drainage system.

 

d)   The separate catchment areas within the site, draining to each collection point or surface pit are to be classified into the following categories:

 

i.        Roof areas

ii.       Paved areas

iii.       Grassed areas

iv.      Garden areas

 

e)   Where buildings abut higher buildings and their roofs are "flashed in" to the higher wall, the area contributing must be taken as:  the projected roof area of the lower building, plus one half of the area of the vertical wall abutting, for the purpose of determining the discharge from the lower roof.

 

f)   Proposed finished surface levels and grades of car parks, internal driveways and access aisles which are to be related to Council's design alignment levels.

 

g)   The details of any special features that will affect the drainage design eg. the nature of the soil in the site and/or the presence of rock etc.

 

78.   All stormwater run-off naturally draining to the site must be collected and discharged through this property's stormwater system.  Such drainage must, if necessary, be constructed prior to the commencement of building work.

 

79.   All site stormwater must be discharged (by gravity) to the kerb and gutter or drainage system in Anzac Parade.

 

80.   Onsite stormwater detention must be provided to ensure that the maximum discharge from the above site is not to exceed that which would occur during a 1 in 10 year storm of 1 hour duration for the existing site conditions. All other stormwater run-off from the above site for all storms up to the 1 in 20 year storm is to be retained on the site for gradual release to the kerb and gutter or drainage system as required by Council.  Provision is to be made for satisfactory overland flow should a storm in excess of the above parameters occur.

 

Should no formal overland escape route be provided for storms greater than the design storm, the on-site detention system shall be sized for the 1 in 100 year storm event.

 

For small areas up to 0.5 hectares, determination of the required cumulative storage must be calculated by the mass curve technique as detailed in Technical Note 1, Chapter 14 of the Australian Rainfall and Run-off Volume 1, 1987 Edition.

 

Where possible the detention tank must have an open base to infiltrate stormwater to the groundwater. Note that the ground water and any rock stratum has to be a minimum of 2.0 metres below the base of the tank.

 

81.   The detention area must be regularly cleaned and maintained to ensure it functions as required by the design. Any onsite detention systems shall be located in areas accessible by residents of all units.

 

82.   The maximum depth of ponding in above ground detention areas shall be as follows:

 

a)   300mm in landscaped areas (where child proof fencing is not provided around the outside of the detention area and sides slopes are steeper than 1 in 10)

b)   600mm in landscaped areas where the side slopes of the detention area have a maximum grade of 1 in 10.

c)   1200mm in landscaped areas where a childproof fence is provided around the outside of the detention area

 

Notes:

§ It is noted that above ground storage will not be permitted in basement carparks or in any area which may be used for storage of goods.

§ Mulch/bark must not be used in onsite detention areas

 

83.   Any above ground stormwater detention system must be suitably signposted where required, warning people of the maximum flood level.

 

84.   The floor level of all habitable and storage areas adjacent to the detention area (and/or infiltration systems with above ground storage) must be a minimum of 300mm above the maximum water level in the detention area for the design storm or alternately a permanent 300mm high water proof barrier is to be constructed.

 

(In this regard, it must be noted that this condition must not result in any increase in the heights or levels of the building.  Any variations to the heights or levels of the building will require a new or amended development consent from the Council prior to a construction certificate being issued for the development).

 

85.   A childproof and corrosion resistant fastening system shall be installed on access grates over pits/trenches where water is permitted to be temporarily stored.

 

86.   A `V' drain is to be constructed along the perimeter of the property, where required, to direct all stormwater to the detention/infiltration area.

 

87.   A reflux valve shall be provided (within the site) over any pipelines discharging from the site into Council’s underground drainage system to ensure that stormwater from Council drainage system does not surcharge back into the site stormwater system.

 

88.   Should a pump system be required to drain any portion of the site the system must be designed with a minimum of two pumps being installed, connected in parallel (with each pump capable of discharging at the permissible discharge rate) and connected to a control board so that each pump will operate alternatively. The pump wet well shall be sized for the 1 in 100 year, 2 hour storm assuming both pumps are not working.

 

The pump system must also be designed and installed strictly in accordance with "Section 8.4 PUMP SYSTEMS" as stipulated in Randwick City Council's Private Stormwater Code.

 

89.   A sediment/silt arrester pit must be provided:-

 

a)     within the site at or near the street boundary prior to the site stormwater discharging by gravity to the kerb/street drainage system; and

b)     prior to stormwater discharging into any absorption/infiltration system.

 

The sediment/silt arrester pit shall be constructed in accordance with the following requirements:-

 

·           The base of the pit located a minimum 300mm under the invert level of the outlet pipe.

 

·           The pit constructed from cast in-situ concrete, precast concrete, double brick or equivalent.

 

·           A minimum of 4 x 90 mm diameter weep holes located in the walls of the pit at the floor level with a suitable geotextile material with a high filtration rating located over the weep holes.

 

·           A galvanised heavy-duty screen located over the outlet pipe/s (Mascot GMS multipurpose filter screen or equivalent).

 

·           The grate being a galvanised heavy-duty grate that has a provision for a child proof fastening system.

 

·           A child proof and corrosion resistant fastening system provided for the access grate (e.g. spring loaded j-bolts or similar).

 

·           A sign adjacent to the pit stating:

 

“This sediment/silt arrester pit shall be regularly inspected and cleaned.”

 

Note: Sketch details of a standard sediment/silt arrester pit may be obtained from Council’s Drainage Engineer.

 

90.   Prior to occupation of the development, a "restriction on the use of land” and “positive covenant" (under section 88E of the Conveyancing Act 1919) shall be placed on the title of the subject property to ensure that the onsite detention/infiltration system is maintained and that no works which could affect the design function of the detention/infiltration system are undertaken without the prior consent (in writing) from Council. Such restriction and positive covenant shall not be released, varied or modified without the consent of the Council.

 

Notes:

a. The “restriction on the use of land” and “positive covenant” are to be to the satisfaction of Council. A copy of Council’s standard wording/layout for the restriction and positive covenant may be obtained from Council’s Development Engineer.

b. The works as executed drainage plan and hydraulic certification must be submitted to Council prior to the “restriction on the use of land” and “positive covenant” being executed by Council.

 

91.   Two covered car washing bays shall be provided for this development.

 

a)   The car washing bays must be drained to sewer to the requirements of Sydney Water and proof of compliance is to be submitted to the certifying authority, prior to an occupation certificate being issued for the proposed development.

 

b)   The car washing bays must be located outside any required/approved stormwater detention system.

 

c)   The car washing bays may be located within the visitor parking spaces provided they are signposted with ‘Exclusive Carwash Bay Use Sat 2:00pm – 5:00pm and Sunday 10:00am – 2:00pm, Visitor parking at other times’

 

d)   The car washing bays must be constructed with a minimum 20mm bund around the perimeter of the car washing bay/s (or equivalent)

 

e)   A water tap shall be located adjacent to the car washing bays.

 

92.   Prior to the issuing of an occupation certificate, the applicant shall submit to Council, a works-as-executed drainage plan prepared by a registered surveyor and approved by a suitably qualified and experienced Hydraulic Engineer. The works-as-executed drainage plan shall be to the satisfaction of the Principal Certifying Authority (PCA) and shall include the following details:

 

a)   The location of the detention basin with finished surface levels;

b)   Finished site contours at 0.2 metre intervals;

c)   Volume of storage available in the detention areas;

d)   The location, diameter, gradient and material (i.e PVC, RC etc) of all stormwater pipes;

e)   The orifice size(s) (if applicable);

f)    Details of any infiltration/absorption systems; and

g)   Details of any pumping systems installed (including wet well volumes).

 

93.   Prior to the issuing of an occupation certificate, the applicant shall submit to the Principal Certifying Authority (PCA) and Council, certification from a suitably qualified and experienced Hydraulic Engineer confirming that the design and construction of the stormwater drainage system complies with the conditions of development consent. The certification must be provided following inspection/s of the site stormwater drainage system by the certifying engineers and shall be provided to the satisfaction of the PCA.

 

94.   As the above site will encounter groundwater within the depth of the basement excavation, the basement carpark levels are to be suitably tanked and waterproofed. A Structural Engineer/Geotechnical Engineer shall certify the tanking & waterproofing has been carried out to an acceptable standard and a copy of the certification is to be forwarded to Council.

 

Notes:

a)  Any subsoil drainage (from planter boxes etc) is to be disposed of within the site and is not to be discharged to Council’s kerb & gutter and/or underground drainage system.

 

b)  Adequate provision is to be made for the groundwater to drain around the basement carpark (to ensure that the basement will not dam or slow the movement of the ground water through the development site).

 

95.   A report must be submitted to and approved by the Certifying Authority or an accredited certifier prior to issuing the Construction Certificate, detailing the proposed method of excavation and dewatering process. Prior to the issuing of a Construction Certificate the approved report must be forwarded to Council, (if Council is not the Certifying Authority). This report is to be prepared by suitably qualified and experienced Geotechnical, Hydrological and Structural Engineers and is to include but not limited to:

 

·    The proposed method of shoring/piling and dewatering.

·    The zone of influence of any possible settlement.

·    The location of any proposed re-injection points in relation to the property boundaries (where re-injection equipment is to be located on land other than the subject premises, the written consent of the owner must also be provided to Council).

·    Monitoring of fluctuations of the water table during dewatering/construction to be undertaken by consulting engineers to ensure that the conditions of consent and other relevant requirements are satisfied.

·    The location of all proposed monitoring equipment in relation to the property boundaries (where monitoring equipment is to be located on land other than the subject premises, the written consent of the owner must also be provided to Council).

·    Details of any consultation and arrangements made with owners of any potentially affected nearby premises (ie in relation to access, monitoring and rectification of possible damage to other premises).

·    Details of groundwater quality and proposed disposal of any potentially contaminated groundwater in accordance with relevant requirements of the Department of Environment & Conservation, Council and the Protection of the Environment Operations Act 1997, in an environmentally sensitive manner.

·    The location of all pumping equipment in relation to the property boundaries.

·    The proposed method of noise attenuation for all pumping equipment, so as not to be more than 5dB (A) greater than the A – weighted L90 background sound pressure level between the hours of 7am to 10pm within any residential premises and not to be audible at all between the hours of 10pm and 7am within any residential dwelling.

·    Confirmation that the proposed methods of dewatering and excavation are appropriate and in accordance with ‘best practice’ principles and should not result in any unacceptable levels of settlement or damage of the adjoining or nearby buildings within the zone of influence.

 

The dewatering process must be monitored by the consulting Engineer/s to the satisfaction of the principal certifying authority and documentary evidence of compliance with the relevant conditions of consent and dewatering requirements must be provided to the principal certifying authority and the Council.

 

The site conditions and fluctuations in the water table are to be reviewed by the consulting Engineer prior to and during the excavation/construction process, to ensure the suitability of the excavation and dewatering process and compliance with Council's conditions of consent.

 

96.   Prior to lodgement of a Construction Certificate application the applicant must obtain from the NSW Office of Water, the general terms of approval and any specific requirements for dewatering of the site to facilitate construction of the basement carpark levels. In particular, the applicant must obtain in writing the Office of Water’s general terms of approval for the issuing of a Part V license under the Water Act 1912.

 

The Construction Certificate application must demonstrate compliance with the general terms of approval for a Part V License. No construction certificate is to be issued until such time as the applicant demonstrates to the satisfaction of the NSW Office of Water and the Certifying Authority that the proposed method for construction of the basement carpark and dewatering of the site is strictly in accordance with the NSW Office of Water’s requirements and best current engineering practice.

 

No dewatering of the site shall take place until such time as a Part V license has been obtained. A copy of the Part V license must be forwarded to Council prior to the commencement of any dewatering on the site.

 

97.   Details of any proposed connection and / or disposal of groundwater or any collected stormwater / rainwater to Council’s external stormwater drainage system must be submitted to and approved by Council’s Development Engineer, prior to commencing these works, in accordance with section 138 of the Roads Act 1993.

 

The subject details must include the following information:

 

·    Site plan

·    Hydraulic engineering details of the proposed disposal/connection of groundwater or site stormwater to Council/s drainage system

·    Volume of water to be discharged

·    Location and size of drainage pipes

·    Duration, dates and time/s for the proposed works and disposal

·    Details of water quality and compliance with the requirements of the Protection of the Environment Act 1997

·    Details of associated plant and equipment, including noise levels from the plant and equipment and compliance with the requirements of the Protection of the Environment Act 1997 and associated Regulations and Guidelines

·    Copy of any required approvals and licences from other Authorities (e.g.  A water licence from the Department of Planning/Department of Water & Energy).

·    Details of compliance with any relevant approvals and licences

 

Waste Management Conditions

The following conditions are applied to provide adequate provisions for waste management:

98.   The garbage room area will have to be redesigned so as to be able to contain a total of 28 x 240 litre bins (14 garbage bins & 14 recycle bins) whilst providing satisfactory access to these bins. Details showing compliance with this requirement are to be shown on the plans submitted to the certifying authority for the construction certificate.

 

99.   The waste storage areas are to be provided with a tap and hose and the floor is to be graded and drained to the sewer to the requirements of Sydney Water. The waste storage areas shall be clearly signposted.

 

100.  Prior to the Certifying Authority issuing an occupation certificate for the proposed development the applicant is to contact Council’s Manager of Waste in regards to meeting Council’s requirements for waste services to the additional residence/dual occupancy.

 

101.  Prior to the issuing of a construction certificate for the proposed development the applicant is to submit to Council and have approved by Council’s Manager of Waste Services, a Waste Management Plan detailing waste and recycling storage and disposal for the development site.

 

The plan shall detail the type and quantity of waste to be generated by the development; demolition waste; construction waste; materials to be re-used or recycled; facilities/procedures for the storage, collection recycling & disposal of waste and the on-going management of waste.

 

Landscape Conditions

The following conditions are applied to provide adequate provisions for landscaping and to maintain reasonable levels of environmental amenity:

102.  Landscaping at this site must be installed substantially in accordance with the Landscape Plans by Taylor Brammer Landscape Architects Pty Ltd, dwg no’s LA01 – 02, job 11-023S, issue A, dated 09.03.11, subject to the following additional requirements being shown on an amended plan, which must be submitted to, and be approved by, the PCA, prior to the commencement of site works:

 

a.   As the row of existing trees growing in the raised garden beyond the northern site boundary are to be removed as part of the re-construction of Tay Lane (refer also Tree Removals in Tay Lane condition later in this report), the row of 3 x EE (Eleaocarpus eummundii, Smooth Leaved Quondong’s) currently shown at the northwest corner of the site, shall be extended all the way to the eastern edge of the proposed building so as to assist with screening and amenity for both occupants and neighbours.

 

b.   The row of 8 x HT (Hibiscus tiliaceus) in the planter bed along the southern boundary, at the southeast corner of the site, have a low, broad spreading canopy up to 6 metres across, and so as to avoid the need for ongoing maintenance relating to overhang above the driveway/basement ramp, they shall be replaced with a more compact and upright native tree species that will achieve a similar height at maturity.

 

c.   The sandstone blocks from the garden bed in Tay Lane shall be retained, and are to be incorporated into the site landscaping where appropriate.

 

d.   Additional notation showing soil and mulch details, irrigation details, edging, paving, fencing details, surface finishes, retaining wall details, and any other landscape elements in sufficient detail to fully describe the proposed landscape works.

 

e.   All planter boxes and garden beds constructed on slab must have a minimum soil depth of 600mm and all lawn areas must have a minimum soil depth of 300mm, with construction details to be provided.

 

f.    In order to reduce the amount of storm-water generated by the site, as well as to recharge groundwater supplies, porous/permeable paving shall be used in all hard surfacing not over slab.

 

g.   To ensure satisfactory maintenance of the landscaping, an automatic drip irrigation system shall be installed throughout all planted areas. Details shall be provided showing that the system will be connected to the sites rainwater tanks, with back-up connection to the mains supply, in accordance with all current Sydney Water requirements.

 

h.   All detention tanks and below ground stormwater infiltration systems located within the landscaped areas shall have a minimum soil cover of 600mm to ensure sufficient soil depth to permit the establishment of landscaping.

 

i.    Any substation required shall be screened from view. The proposed location, elevation and screening method shall be shown on all detailed landscape drawings and specifications.

 

103.  The PCA must ensure that landscaping at this site is installed in accordance with the approved documentation, prior to issuing a Final (or any other type of Interim) Occupation Certificate/s, with the body corporate/owners corporation to implement strategies to ensure that the landscaping is maintained in a healthy and vigorous state until maturity, for the life of the development.

 

Footpath Works

104.  As part of reconstructing the Anzac Parade footpath (refer also Civil Works Conditions), squares or cut-outs measuring a minimum of 1m x 1m are to be provided for both trees, with a turfed verge using either Kikuyu or Soft Leaf Buffalo rolls (full sun variety) to be provided across the full width of the site, with the above treatments to be consistent with the existing public areas to the north and south of the site.

 

Tree Removals within site

105.  Approval is granted for the removal of all existing vegetation within the site where necessary in order to accommodate the proposed works as shown, including the single Cupressus sempervirens (Italian Cypress) in the southwest corner of the site, subject to full implementation of the approved landscaping.

 

Tree Removals within Tay Lane

106.  In order to accommodate the full re-construction of Tay Lane (refer Civil Works Conditions), the row of seven trees beyond the northern site boundary, growing in the raised garden within Tay Lane, must all be removed, stump ground and disposed of, being from west to east, a Callistemon viminalis (Weeping Bottlebrush), Cupressus macrocarpa ‘Brunniana’ (Brunnings Golden Cypress), a Syagrus romanzoffianum (Cocos Palm), a small Callistemon viminalis (Bottlebrush), a Callitris rhomboidea (Port Jackson Cypress), and two more semi-established Callistemon viminalis (Bottlebrush’s).

 

107.  The tree removals described above will be wholly at the applicants cost, and must satisfy themselves as to the location of all services prior to the commencement of any works on public property.

 

Protection of Street Trees

108.  In order to ensure retention of the two  recently planted Platanus x hybrida (London Plane Trees) growing in individual tree squares within the Anzac Parade concrete footpath, being one towards the northern boundary, near the corner of Tay Lane, and one near the southern site boundary in good health, the following measures are to be undertaken:

 

a.   All documentation submitted for the Construction Certificate application must show the retention of both trees, with their position to be clearly and accurately shown on all drawings.

 

b.   Any excavations associated with the installation of new services, pipes, stormwater systems or similar that need to be installed over public property must be setback a minimum distance of 3 metres off their trunks.

 

c.   Both street trees are to be physically protected by installing a total of four star pickets within the existing tree squares, to which safety tape/para-webbing/shade cloth or similar shall be permanently attached so as to completely enclose each tree for the duration of works.

 

d.   This fencing shall be installed prior to the commencement of works and must remain in place until all works are completed, to which signage containing the following words shall be clearly displayed and permanently attached: “TREE PROTECTION ZONE (TPZ), DO NOT REMOVE/ENTER".

 

e.   The applicant is not authorised to perform any works to either of these street trees, and shall contact Council’s Landscape Development Officer on 9399-0613 should pruning or any similar such work appear necessary, with the applicant required to cover all associated costs with such work, to Council’s satisfaction, prior to the issue of a Final Occupation Certificate.

 

f.    Within the TPZ’s, there is to be no storage of materials, machinery or site office/sheds, nor is cement to be mixed or chemicals spilt/disposed of and no stockpiling of soil or rubble, with all Site Management Plans needing to acknowledge these requirements.

 

g.   Any roots encountered that are in direct conflict with the new public footpath must be cut cleanly by hand, and the affected area backfilled with clean site soil as soon as practically possible.

 

h.   If hoardings are required/proposed during the course of works, the applicant will be required to liaise with Council’s Landscape Development Officer on 9399-0613, regarding a system that will not damage the trees in anyway, and affect their future health or condition.

 

i.    A refundable deposit in the form of cash, credit card or cheque for an amount of $1000.00 shall be paid at the Cashier on the Ground Floor of the Administrative Centre, prior to a Construction Certificate being issued for the development, in order to ensure compliance with the conditions listed in this consent, and ultimately, preservation of the street trees.

 

The refundable deposit will be eligible for refund following the issue of a Final Occupation Certificate, subject to completion and submission of Council’s ‘Security Deposit Refund Application Form’, and pending a satisfactory inspection by Council’s Landscape Development Officer (9399-0613).

 

Any contravention of Council's conditions relating to the trees at any time during the course of the works, or prior to the issue of a final occupation certificate, may result in Council claiming all or part of the lodged security in order to perform any rectification works necessary, as per the requirements of 80A (6) of the Environmental Planning and Assessment Act 1979.

 

·      Further information and details on Council's requirements for trees on development sites can be obtained from the recently adopted Tree Technical Manual, which can be downloaded from Council’s website at the following link, http://www.randwick.nsw.gov.au - Looking after our environment – Trees – Tree Management Technical Manual; which aims to achieve consistency of approach and compliance with appropriate standards and best practice guidelines.

 

Advisory Conditions

The applicant is to advise Council in writing and/or photographs of any signs of existing damage to the Council roadway, footway, or verge prior to the commencement of any building/demolition works.

 

Requirements of Sydney Airport Corporation LTd (SACL)

109.  The development is not to exceed a maximum height of 44.9m AHD inclusive of lift over-runs, vents, chimneys, aerials, TV antennae, construction cranes etc. A new application to SACL must be made to exceed these heights.

 

110.  SACL advises that approval to operate construction equipment (i.e cranes) should be obtained prior to any commitment to construct. Information required by SACL prior to any such approval is to include:

·       The location of any temporary structure or equipment, i.e         construction cranes, planned to be used during construction        relative to Mapping Grid of Australia (MGA94).

·       The swing circle of any temporary structure, equipment used    during construction.

·       The maximum height, relative to Australian Height Datum   (AHD), of any temporary structure or equipment i.e      construction cranes, intended to be used in the erection of the    proposed activity.

·       The period of the proposed operation (i.e construction cranes) and desired operating hours for any temporary structures.

 

Any application for approval containing the above information should be submitted to SACL at least 35 days prior to commencement of works in accordance with the Airports (protection of Airspace) Regulations Statutory Rules 1996 No. 293. For further information on Height Restrictions contact Ms Lynne Barrington on (02) 9667 9217.

 

The following conditions are applied to maintain reasonable levels of environmental amenity and public health safety.

111.  Any new information which comes to light during construction works which has the potential to alter previous conclusions about site contamination shall be notified to the Council and the Principal Certifying Authority immediately.

 

112.  The works shall not give rise to environmental pollution or public nuisance or, result in an offence under the Protection of the Environment 1997 or NSW Occupational Health & Safety Act (2000) & Regulations (2001).

 

113.  A Health and Safety Plan shall be prepared by a suitably environmental consultant to address the residual contamination remaining on site and be submitted to the certifying Authority prior to a construction certificate being issued. The plan shall address health and safety issues during the construction phase of the proposal. The health and safety plan is to be implemented during the construction phase of the proposal.

 

The following conditions have been applied to ensure that noise emissions from the development satisfy legislative requirements and maintain reasonable levels of amenity to the area:

114.  The proposed use of the premises and the operation of all plant and equipment shall not give rise to an ‘offensive noise’ as defined in the Protection of the Environment Operations Act 1997 and Regulations.

 

In this regard, the operation of the premises and plant and equipment      shall not give rise to a sound pressure level at any affected premises that exceeds the background (LA90), 15 min noise level, measured in the absence of the noise source/s under consideration by more than 5dB(A). The source noise level shall be assessed as an LAeq, 15 min and adjusted in accordance with the NSW Environmental Protection Authority’ s Industrial Noise Policy 2000 and Environmental Noise Control Manual (sleep disturbance).

 

115.  The residential units are to achieve the following internal acoustic amenity criteria:

 

a)   In naturally ventilated residential units; the repeatable maximum LAeq (1 hour) shall not exceed:

 

·       35 dB(A) between 10pm and 7am in sleeping areas when the windows are closed;

·       45 dB(A) in sleeping areas when windows are open;

·       45 dB(A) in living areas (24 hours) when the windows are closed, and

·       55 dB(A) in living areas when the windows are open.

 

b)   In residential units provided with mechanical ventilation, air conditioning or other complying means of ventilation, when doors and windows are shut, the repeatable maximum LAeq (1 hour) shall not exceed:

 

·       38 dB(A) between 10pm and 7am in sleeping areas;

·       46 dB(A) in living areas (24 hours).

 

Details of compliance with the relevant criteria is to be included in the construction certificate application and written confirmation of compliance is to be provided to the Certifying Authority, by the Acoustic consultant.

 

116.  The use of the premises and the operation of plant and equipment shall not give rise to the transmission of a vibration nuisance or damage to other premises.

 

117.  A report, prepared by a suitably qualified and experienced consultant in acoustics, shall be submitted to the Council prior to a Occupation Certificate being issued for the development, which demonstrates and certifies that noise and vibration emissions from the development comply with the relevant provisions of the Protection of the Environment Operations Act 1997, NSW Environmental Protection Authority Noise Control Manual & Industrial Noise Policy and conditions of Council’s approval, to the satisfaction of Council’s Manager Environmental Health & Building Services.

 

The following conditions are applied to satisfy the relevant pollution control criteria and to maintain reasonable levels of health, safety and amenity to the locality:

118.  The applicant is to engage the services of a suitably qualified to respond to enquiries and complaints made by the community, the general public or Council in relation to Noise, excavation and construction site management matters.

 

A specific contact number is to be made available for such enquiries and complaints (including an after hours emergency contact number). A complaints register is to be maintained to record all such enquiries, complaints and actions taken in response to these enquiries and complaints. This register shall be made available to council officers upon a reasonable request.

 

119.  The use and operation of the plant and equipment within the building shall not give rise to an environmental health or public nuisance and there are to be no emissions or discharges from the premises, which will give rise to a public nuisance or result in an offence under the Protection of the Environment Operations Act 1997 and Regulations.

 

The following conditions are applied to satisfy the relevant pollution control criteria and to maintain reasonable levels of health, safety and amenity to the locality:

120.  Any hazardous and/or intractable wastes arising from any excavation, building  and any works are to be managed and disposed of in accordance with the requirements of Work Cover NSW and the Department of Environment and Climate Change (formerly EPA), including the provisions of:

 

·        New South Wales Occupational Health and Safety Act, 2000

·        Hazardous Materials Survey Report No. EMS08 6177 prepared by Environmental Monitoring Services

·        The Occupational Health and Safety (Hazardous Substances) Regulation 2001

·        The Occupational Health and Safety (Asbestos Removal Work) Regulation 2001

·        Protection Of the Environment Operations Act 1997 (NSW)

·        Environment Protection Authority's Environmental Guidelines; Assessment, Classification and Management of Liquid and Non Liquid Wastes (1999)

·        Randwick City Council’s Asbestos Policy

 

Office of Water

121.  General and Administrative Issues.

 

a.     Groundwater shall not be pumped or extracted for any purpose other than temporary construction dewatering.

b.     Pumped water (tailwater) shall not be allowed to discharge off-site (eg adjoining roads, stormwater system, sewerage system, etc) without the controlling authorities approval and/or owners consent.

c.     The licensee shall allow (subject to Occupational Health and Safety Provisions) the NSW Office of Water or any person authorised by it, full and free access to the works (excavation or bore/borefield), either during or after construction, for the purpose of carrying out inspection or test of the works and its fittings and shall carry out any work or alterations deemed necessary by the NSW Office of Water for the protection and proper maintenance of the works, or the control of the water extracted to prevent wastage and for the protection of the quality and prevention from pollution or contamination of the groundwater.

d.     If a work is abandoned at any time the licensee shall notify the NSW Office of Water that the work has been abandoned and seal off the aquifer by such methods as agreed to or directed by the NSW Office of Water.

e.     Suitable documents are to be supplied to the NSW Office of Water of the following:

•  A report of prediction of the impacts of pumping on any licensed groundwater users or groundwater dependent ecosystems in the vicinity of the site.  Any adverse impacts will not be allowed and the project will need to be modified.

•  A report of assessment of the potential for salt water intrusion to occur as a result of the dewatering.  This report is only required for sites within 250m of any marine or estuarine foreshore area.  The generation of conditions leading to salt water intrusion will not be allowed, and the proposal will need to be modified.

•  Descriptions of the methods used and actual volume of groundwater to be pumped (kilolitres/megalitres) from the dewatering works, the works locations, the discharge rate (litres per second), duration of pumping (number of days/weeks), the amount of lowering of the water table and the anticipated quality of the pumped water.

•  Descriptions of the actual volume of pumped water (tailwater) to be reinjected (kilolitres/megalitres), the reinjection locations, the disposal rate (litres per second), duration of operation (number of days/weeks) and anticipated quality of treated water to be reinjected.

•  Monitoring of groundwater levels (minimum of 3 weekly measurements of depth to water at a minimum of 3 locations broadly distributed across the site) beneath the proposed development site prior to construction.  This requirement is only for sites where the proposed structure shall extend greater than one floor level into the existing ground level.

 

122.  Specific Conditions.

 

a.   The design and construction of the structure must preclude the need for permanent dewatering.

b.   The design and construction of the structure that may be impacted by any watertable must include a water proof retention system (i.e. a fully tanked structure) with adequate provision for future fluctuations of water table levels.  (It is recommended that a minimum allowance for a water table variation of at least +/-1.0 metre beyond any expected fluctuation be provided).  The actual water table fluctuation and fluctuation safety margin must be determined by a suitably qualified professional.

c.   Construction methods and material used in and for construction are not to cause pollution of the groundwater.

d.   Monitoring of groundwater levels is to be continued at least weekly during the construction stage and at least weekly over a period of at least 2 months following cessation of dewatering, with all records being provided to the NSW Office of Water on expiration of the licence.  This requirement is only for sites where the proposed structure shall extend greater than one floor level into the existing ground level.

e.   Groundwater quality testing must be conducted (and report supplied to the NSW Office of Water).  Samples must be taken prior to the commencement of dewatering, (and ongoing to the satisfaction of the NSW Office of Water for any extraction and reinjection activities).  Collection and testing and interpretation of results must be done by suitably qualified persons and NATA certified laboratory identifying the presence of any contaminants and comparison of the data against accepted water quality objectives or criteria.

f.    Discharge of any contaminated pumped water (tailwater) that is not to be reinjected, must comply with the provisions of the Protection of the Environment Operations Act 1997 and any requirements of the relevant controlling authority.  The method of disposal of pumped water (i.e. street drainage to the stormwater system or discharge to sewer) and written permission from the relevant controlling authority must be presented to the NSW Office of Water in support of the licence application.

g.   Discharge of any contaminated pumped water (tailwater) that is to be reinjected, must comply with the provisions of the Protection of the Environment Operations Act 1997.  The quality of any pumped water (tailwater) that is to be reinjected must be compatible with, or improve the intrinsic or ambient groundwater in the vicinity of the reinjection site.  Contaminated groundwater is not to be reinjected into any aquifer.  The following must be demonstrated in writing:

•  The treatment to be applied to the pumped water (tailwater) to remove any contamination.

•  The measures to be adopted to prevent redistribution of any contamination in the groundwater system.  Any reinjection proposal that is likely to further spread contamination within the groundwater system will not be allowed and the project will need to be modified.

•  The means to avoid degrading impacts on the identified beneficial use of the groundwater.  Any reinjection proposal that is likely to lower the identified beneficial use of a groundwater system will not be allowed and the project will need to be modified.

 

h.   Written advice be provided from the Certifying Authority to the NSW Office of Water to certify that the following ground settlement issues have been addressed in reports submitted by the proponent:

•  Assessment by a suitably qualified geotechnical professional that the proposed dewatering activity does not pose an unacceptable risk of off-site impacts such as damage to surrounding buildings or infrastructure as a result of differential sediment compaction and surface settlement during and following pumping of groundwater.

•  Settlement monitoring activities to be undertaken prior to, during and for the required period of time following the dewatering pumping to confirm the impact predictions.

•  Locations of settlement monitoring points, and schedules of measurement.

 

123.  Formal Application Issues

a.   An application must be completed on the prescribed form for the specific purpose of temporary construction dewatering and a licence obtained from the NSW Office of Water prior to the installation of the groundwater extraction works.  A plan drawn to scale will be required with the application clearly identifying the location of the dewatering installations.

 

b.   Upon receipt of a Development Consent from , a fully completed licence application form, unambiguous documentation of the means by which the below-ground areas of the development will be designed and constructed to prevent any groundwater seepage inflows (and therefore preclude any need for permanent or semi-permanent pumping), together with all other required supporting information, the NSW Office of Water will issue a Water Licence under Part 5 of the Water Act, 1912.

 

c.   A licence application under Part 5 of the Water Act 1912 must be accompanied by a $151.00 fee and must specify the proposed volume of groundwater to be pumped in total (megalitres).  The licence is also subject to administrative charges as determined from time to time by the Independent Pricing and Regulatory Tribunal (IPART).

 

NSW Police Requirements

124.  The development must incorporate the recommendations of the Safer By Design Crime Risk Evaluation report prepared by the NSW Police Force and received by Council on 13 May 2011.

 

Advisory Conditions:

A1.   The applicant is advised that the Construction Certificate plans and specification must comply with the provisions of the Building Code of Australia (BCA).

 

Details of compliance with the relevant provisions of the Building Code of Australia and conditions of development consent are to be provided in the plans and specifications for the construction certificate.

 

The applicant/developer is advised to ensure that the development is not inconsistent with Council's consent and if necessary consult with Council’s Building Certification Services or your accredited certifier (as applicable) prior to submitting your construction certificate application to enable these matters to be addressed accordingly.

 

A2.   The applicant/owner is advised that this approval does not guarantee compliance with the provisions of the Disability Discrimination Act 1992 and the applicant should therefore consider their liability under the Act.  In this regard, the applicant is advised that compliance with the requirements of the Building Code of Australia and Australian Standard 1428.1 - Design for Access and Mobility does not necessarily satisfy the objectives of the Disability Discrimination Act 1992.

 

The applicant/owner is requested to give consideration to providing access and facilities for people with disabilities in accordance with Australian Standard 1428 Parts 1, 2, 3 and 4 - Design for Access and Mobility, which may be necessary to satisfy the objectives of the Disability Discrimination Act 1992.

 

A3.   The applicant is to advise Council in writing and/or photographs of any signs of existing damage to the Council roadway, footway, or verge prior to the commencement of any building/demolition works.

 

MOTION: (Andrews/Mayor, Cr Matson) CARRIED UNANIMOUSLY - SEE RESOLUTION.

 

 

 

D108/11   Development Application Report - 155 Clovelly Road, Randwick (DA/309/2011)

PL128/11

RESOLUTION: (Andrews/Mayor, Cr Matson) -

 

A.     That Council supports the objections under State Environmental Planning Policy No. 1 – Development Standards in respect to non-compliance with Clauses 20E and 20F of Randwick Local Environmental Plan 1998, relating to Landscaped area and Floor space ratios respectively, on the grounds that the proposed development complies with the objectives of the above clauses, and will not adversely affect the amenity of the locality, and that the Department of Planning be advised accordingly.

 

B.     That Council, as the consent authority, grants development consent under Sections 80 and 80A of the Environmental Planning and Assessment Act 1979, as amended, to Development Application No. DA/309/2011 for permission to carry out alterations to existing ground floor retail tenancy including new shop front & alterations & additions to residential component of site at ground and first floor (maintaining only one residence on site) & construction of rollerdoor on laneway frontage at 155 Clovelly Road, Randwick, subject to the following conditions:

 

1.       The development must be implemented substantially in accordance with the plans numbered B00, B01, B02, B03, B04, dated 29 June 2011 and received by Council on 15 July 2011, the BASIX Certificate numbered A117948, dated 20 July 2011 and received by Council on 20 July 2011, the application form and on any supporting information received with the application, except as may be amended  by the following conditions and as may be shown in red on the attached plans:

 

The following conditions are applied to satisfy the provisions of section 79C of the Environmental Planning and Assessment Act 1979 and to maintain reasonable levels of environmental amenity:

2.       The colours, materials and finishes of the external surfaces to the building are to be consistent with the details received by Council on 2 May 2011.

 

3.       The finished ground levels external to the building are to be consistent with the development consent and are not to be raised (other than for the provision of paving or the like on the ground) without the written consent of Council.

 

4.       The windows to the stair well are to be fixed and provided with translucent, obscured, frosted or sandblasted glazing. If required, the BASIX certificate shall be amended accordingly. Details of compliance shall be submitted with the Construction Certificate to the satisfaction of the Certifying Authority.

 

5.       The sill height of the west facing window to the first floor bathroom is to be increased to be a minimum height of 1.6m above floor level, or alternatively, the window is to be fixed and provided with translucent, obscured, frosted or sandblasted glazing below 1.6m above floor level. The BASIX certificate shall be amended accordingly. Details of compliance shall be submitted with the Construction Certificate to the satisfaction of the Certifying Authority.

 

6.       Privacy screens having a height of 1.8m are to be provided to eastern and western sides of the rear upper level balcony and details of compliance are to be provided in the Construction Certificate plans.  The total area of any openings within the privacy screen must not exceed 25% of the area of the screen and the screens must be in place prior to use of the upper level balcony.

 

7.       Lighting to the premises shall be designed so as not to cause a nuisance to nearby residents or motorists and to ensure that light overspill does not affect the amenity of the area.

 

The following conditions are imposed to promote ecologically sustainable development and energy efficiency.

8.       In accordance with the provisions of the Environmental Planning & Assessment Regulation 2000, a relevant BASIX Certificate and associated documentation must be submitted to the Certifying Authority with the Construction Certificate application for this development.

 

The required commitments listed and identified in the BASIX Certificate are to be included on the plans, specifications and associated documentation for the proposed development, to the satisfaction of the Certifying Authority.

 

The design of the building must not be inconsistent with the development consent and any proposed variations to the building to achieve the BASIX commitments may necessitate a new development consent or amendment to the existing consent to be obtained, prior to a construction certificate being issued.

 

The following condition is applied to meet additional demands for public facilities;

9.       In accordance with Council’s Section 94A Development Contributions Plan effective from 2 July 2007, based on the development cost of $180,000, the following applicable monetary levy must be paid to Council: $900.00.

 

The levy must be paid in cash, bank cheque or by credit card prior to a construction certificate being issued for the proposed development. The development is subject to an index to reflect quarterly variations in the Consumer Price Index (CPI) from the date of Council’s determination to the date of payment.

 

Council’s Section 94A Development Contribution Plans may be inspected at the Customer Service Centre, Administrative Centre, 30 Frances Street, Randwick or at www.randwick.nsw.gov.au.

The following conditions are applied to provide adequate provisions for access, transport and infrastructure:

10.     The applicant must meet the full cost for Council or a Council approved contractor to repair/replace any damaged sections of Council's footpath, kerb & gutter, nature strip etc which are due to building works being carried out at the above site. This includes the removal of cement slurry from Council's footpath and roadway.

 

11.     All external civil work to be carried out on Council property (including the installation and repair of roads, footpaths, vehicular crossings, kerb and guttering and drainage works), must be carried out in accordance with Council’s Policy for “Vehicular Access and Road and Drainage Works” and the following requirements:

 

a)       All work on Council land must be carried out by Council, unless specific written approval has been obtained from Council to use non-Council contractors.

 

b)       Details of the proposed civil works to be carried out on Council land must be submitted to Council in a Pre-paid Works Application Form, prior to issuing an occupation certificate, together with payment of the relevant fees.

 

c)       If it is proposed to use non-Council contractors to carry out the civil works on Council land, the work must not commence until the written approval has been obtained from Council and the work must be carried out in accordance with the conditions of consent, Council’s design details and payment of a Council design and supervision fee.

 

d)       The civil works must be completed in accordance with Council’s conditions of consent and approved design and construction documentation, prior to occupation of the development, or as otherwise approved by Council in writing.

 

12.     The minimum clear distance from the existing footpath in Clovelly Road to the underside of the proposed awning shall be 3.00 metres. The plans submitted for the construction certificate shall demonstrate compliance with this requirement.

 

13.     All new awnings shall be set back a minimum of 600mm from the face of kerb. The plans submitted for the construction certificate shall demonstrate compliance with this requirement.

 

14.     Upon completion of the construction of the awning, certification of the structural adequacy of the awning must be provided to the Council.

 

The following conditions are applied to provide adequate provisions for future civil works in the road reserve:

15.     The Council’s Development Engineer has inspected the above site and have determined that the design alignment level (concrete/paved/tiled level) at the property boundary for driveways, access ramps and pathways or the like, must match the back of the existing footpath along the full site frontage.

 

16.     The above alignment levels and the site inspection by Council’s Development Engineer have been issued at a prescribed fee of $135.00 (inclusive of GST). This amount is to be paid prior to a construction certificate being issued for the development.

 

The following conditions are applied to provide adequate consideration for service authority assets:

17.     The applicant must meet the full cost for telecommunication companies, gas providers, Energy Australia and Sydney Water to adjust/repair/relocate their services as required.  The applicant must make the necessary arrangements with the service authority.

 

The following conditions are applied to provide adequate provisions for drainage and associated infrastructure:

18.     Stormwater runoff from the site shall be discharged to the Council kerb and gutter along the site frontage by gravity.

 

The following conditions are applied to ensure that the development satisfies the provisions of the Environmental Planning and Assessment Act 1979 and Regulations:

19.     The requirements and provisions of the Environmental Planning & Assessment Act 1979 and Environmental Planning & Assessment Regulation 2000, must be fully complied with at all times.

 

Failure to comply with these legislative requirements is an offence and may result in the commencement of legal proceedings, issuing of `on-the-spot` penalty infringements or service of a notice and order by Council.

 

20.     All new building work must be carried out in accordance with the provisions of the Building Code of Australia (BCA), in accordance with Clause 98 of the Environmental Planning and Assessment Regulation 2000.

 

21.     Prior to the commencement of any building works, a construction certificate must be obtained from the Council or an accredited certifier, in accordance with the provisions of the Environmental Planning & Assessment Act 1979 and Environmental Planning & Assessment Regulation 2000.

 

22.     Prior to the commencement of any building works, the person having the benefit of the development consent must:

 

i)     appoint a Principal Certifying Authority for the building work; and

 

ii)     appoint a principal contractor for the building work and notify the Principal Certifying Authority and Council accordingly in writing; and

                                        

iii)    notify the principal contractor of the required critical stage inspections and other inspections to be carried out, as specified by the Principal Certifying Authority; and

 

iv)    give at least two days notice to the Council, in writing, of the persons intention to commence building works.

 

In relation to residential building work, the principal contractor must be the holder of a contractor licence, in accordance with the provisions of the Home Building Act 1989.

23.     The building works must be inspected by the Principal Certifying Authority (or another certifying authority if the Principal Certifying Authority agrees), in accordance with sections 109 E (3) of the Environmental Planning & Assessment Act 1979 and clause 162A of the Environmental Planning & Assessment Regulation 2000, to monitor compliance with the relevant standards of construction, Council’s development consent and the construction certificate.

 

The Principal Certifying Authority must specify the relevant stages of construction to be inspected in accordance with section 81A (2) (b1) (ii) of the Environmental Planning & Assessment Regulation 2000 and a satisfactory inspection must be carried out, to the satisfaction of the Principal Certifying Authority, prior to proceeding to the subsequent stages of construction or finalisation of the works (as applicable).

 

Documentary evidence of the building inspections carried out and details of compliance with Council’s consent is to be maintained by the Principal Certifying Authority.  Details of critical stage inspections carried out and copies of certification relied upon must also be forwarded to Council with the occupation certificate.

 

The principal contractor must ensure that the required critical stage and other inspections, as specified in the Principal Certifying Authority’s “Notice of Critical Stage Inspections”, are carried out to the satisfaction of the Principal Certifying Authority and at least 48 hours notice (excluding weekends and public holidays) is to be given to the Principal Certifying Authority, to carry out the required inspection, before carrying out any further works.

 

24.     A sign must be erected and maintained in a prominent position on the site, which contains the following details:

 

·          name, address, contractor licence number and telephone number of the principal contractor, including a telephone number at which the person may be contacted outside working hours;

·          name, address and telephone number of the Principal Certifying Authority; and

·          a statement stating that “unauthorised entry to the work site is prohibited”.

 

25.     An Occupation Certificate must be obtained from the Principal Certifying Authority prior to any occupation of the building work encompassed in this development consent (including alterations and additions to existing buildings), in accordance with the relevant provisions of the Environmental Planning & Assessment Act 1979.

 

An Occupation Certificate must not be issued for the development if the development is inconsistent with the development consent.  The requirements of the Environmental Planning & Assessment Act 1979 and conditions of development consent must be satisfied prior to the issuing of an occupation certificate.

26.     Prior to the issuing of an interim or final occupation certificate, a statement is required to be obtained from the Principal Certifying Authority, which confirms that the development is not inconsistent with the development consent and the relevant conditions of development consent have been satisfied.

 

Details of critical stage inspections carried out by the principal certifying authority together with any other certification relied upon and must also be provided to Council with the occupation certificate.

 

27.     In accordance with clause 98 of the Environmental Planning and Assessment Regulation 2000, it is a prescribed condition, that in the case of residential building work, a contract of insurance must be obtained and in force, in accordance with the provisions of the Home Building Act 1989.

 

Where the work is to be done by a licensed contractor, excavation or building work must not be carried out unless the Principal Certifying Authority (PCA): -

·          has been informed in writing of the licensee’s name and contractor number; and

·          is satisfied that the licensee has complied with the insurance requirements of Part 6 of the Home Building Act 1989, or

 

Where the work to be done by any other person (i.e. an owner-builder), excavation or building work must not be carried out unless the Principal Certifying Authority: -

·          has been informed of the person’s name and owner-builder permit number; or

·          has been given a declaration, signed by the owner of the land that states that the market cost of the labour and materials involved in the work does not exceed $5,000.

 

Details of the principal building contractor and compliance with the provisions of the Home Building Act 1989 (i.e. Details of the principal licensed building contractor and a copy of the Certificate of Insurance) are to be submitted to Council prior to the commencement of works, with the notice of appointment of the PCA / notice of intention to commence building work.

 

28.     The required Long Service Levy payment, under the Building and Construction Industry Long Service Payments Act 1986, is to be forwarded to the Long Service Levy Corporation or the Council, prior to the issuing of a Construction Certificate, in accordance with Section 109F of the Environmental Planning & Assessment Act 1979.

 

At the time of this development consent, Long Service Levy payment is applicable on building work having a value of $25,000 or more, at the rate of 0.35% of the cost of the works.

29.     The building is required to be provided with a smoke alarm system complying with Clause 3 of Specification E2.2a of the Building Code of Australia or a smoke detection system complying with Clause 4 of Specification E2.2a of the Building Code of Australia or a combination of a smoke alarm system within the sole-occupancy units and a smoke detection system in areas not within the sole-occupancy units.  The smoke detectors located within the Class 5 and 4 portions must be interconnected.

 

The office and meeting room at ground floor level are required to be fire separated from the remainder of the premises in accordance with the relevant provisions of the Building Code of Australia if the area is to be leased as a separate occupancy and not used in conjunction with the residence.  details are to be included with the plans/specification for the construction certificate.

 

Additional requirements regarding the design and installation of the smoke detection and alarm system may be specified in the construction certificate for the development.

 

Details of compliance with the provisions of the Building Code of Australia must be included in the plans/specification for the construction certificate.

 

The following conditions are applied to ensure that the development satisfies relevant standards of construction, and to maintain adequate levels of health, safety and amenity during construction:

30.     The demolition, removal, storage, handling and disposal of building products and materials must be carried out in accordance with the relevant requirements of WorkCover NSW, the NSW Department of Environment & Conservation (formerly the Environment Protection Authority) and Randwick City Council policies and conditions, including:

 

·       Occupational Health and Safety Act 2000

·       Occupational Health and Safety (Hazardous Substances) Regulation 2001

·       Occupational Health and Safety (Asbestos Removal Work) Regulation 2001

·       WorkCover NSW Code of Practice for the Safe Removal of Asbestos

·           Australian Standard 2601 (2001) – Demolition of Structures

·           The Protection of the Environment Operations Act 1997 and Protection of the Environment Operations (Waste) Regulation 1996.

·           Relevant Department of Environment & Conservation (DEC) / Environment Protection Authority (EPA) and WorkCover NSW Guidelines.

·           Randwick City Council Asbestos Policy (adopted 13 September 2005)

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development section or a copy can be obtained from Council’s Customer Service Centre.

 

31.     A copy of the construction certificate, the approved plans & specifications and development consent conditions must be kept on the site at all times and be made available to the Council officers and all building contractors for assessment.

 

32.     Except with the written approval of Council’s Manager of Health, Building & Regulatory Services, all building, demolition and associated site works (including site deliveries) must only be carried out between the hours of 7.00am to 5.00pm on Monday to Friday inclusive and between 8.00am to 5.00pm on Saturdays and all building activities are strictly prohibited on Sundays and Public Holidays.

 

33.     Noise and vibration emissions during the construction of the building and associated site works must not result in damage to nearby premises or result in an unreasonable loss of amenity to nearby residents and the relevant provisions of the Protection of the Environment Operations Act 1997 must be satisfied at all times.

       

34.     Public safety and convenience must be maintained at all times during demolition, excavation and construction works.

 

The roadway, footpath and nature strip must be maintained in a good, safe condition and free from any obstructions, materials, soils or debris at all times.  Any damage caused to the road, footway or nature strip must be repaired immediately, to the satisfaction of Council.

 

A Road Opening Permit must be obtained from the Council and other relevant Authorities prior to excavating or opening-up the road or footway for services or the like.

 

35.     Building materials, sand, soil, waste materials or construction equipment must not be placed upon the footpath, roadway or nature strip at any time and the footpath, nature strip and road must be maintained in a clean condition and free from any obstructions, soil and debris at all times.

 

Bulk bins/waste containers must not be located upon the footpath, roadway or nature strip at any time without the prior written approval of the Council, unless the waste container is located upon the road in accordance with the Roads & Traffic Authority Guidelines and Requirements, and the container is exempt from an approval under Development Control Plan for Exempt & Complying Development and Council’s Local Approvals Policy.  Applications to place a waste container in a public place can be made to Council’s Building Services section.

 

36.     During construction stages, sediment laden stormwater run-off shall be controlled using the sediment control measures outlined in the manual for Managing Urban Stormwater – Soils and Construction, published by the NSW Department of Housing.

 

Stockpiles of soil, sand, aggregate or other materials must not be located on any footpath, roadway, nature strip, drainage line or any public place and the stockpiles must be protected with adequate sediment control measures.

 

Building operations such as brick cutting, washing tools or equipment and mixing mortar are not permitted on public footpaths, roadways, nature strips, in any public place or any location which may lead to the discharge of materials into the stormwater drainage system.

 

A warning sign for soil and water management must be displayed in a prominent position on the building site, visible to both the public and site workers.  The sign must be displayed throughout the construction period.  Copies of a suitable warning sign are available at Council’s Customer Service Centre for a nominal fee.

 

37.     Public safety must be maintained at all times and public access to the site and building works, materials and equipment on the site is to be restricted, when work is not in progress or the site is unoccupied.

 

A temporary safety fence is to be provided to protect the public, located to the perimeter of the site (unless the site is separated from the adjoining land by an existing structurally adequate fence, having a minimum height of 1.5 metres).  Temporary fences are to have a minimum height of 1.8 metres and be constructed of cyclone wire fencing, with geotextile fabric attached to the inside of the fence to provide dust control, or other material approved by Council.

 

Temporary site fences are to be structurally adequate, safe and be constructed in a professional manner and the use of poor quality materials or steel reinforcement mesh as fencing is not permissible.

 

The public safety provisions and temporary fences must be in place prior to the commencement of any demolition, excavation or building works and be maintained throughout construction.

 

If it is proposed to locate any site fencing, hoardings or amenities upon a footpath or public place, the written consent from Council’s Building Services section must be obtained beforehand and detailed plans are to be submitted to Council for consideration, together with payment of the weekly charge in accordance with Council’s adopted fees and charges.

 

38.     A local approval application must be submitted to and be approved by Council's Building Services section prior to commencing any of the following activities on a footpath, road, nature strip or in any public place:

 

·          Install or erect any site fencing, hoardings or site structures

·          Operate a crane or hoist goods or materials over a footpath or road

·          Placement of a waste skip (grater than 3m in length) or any container or other article.

 

The following group of conditions have been applied to ensure the structural adequacy and integrity of the proposed building and adjacent premises:

39.     A Certificate of Adequacy supplied by a professional engineer shall be submitted to the certifying authority (and the Council, if the Council is not the certifying authority) prior to a construction certificate being issued for the development, certifying the structural adequacy of the existing structure to support the additional storey.

 

40.     A Certificate prepared by a professional engineer shall be submitted to the certifying authority (and the Council, if the Council is not the certifying authority) prior to issuing an occupation certificate, which certifies the structural adequacy of the building and compliance with the relevant structural requirements of the Building Code of Australia.

 

The following conditions are applied to maintain reasonable levels of public health, amenity and safety:

41.     The demolition, removal, storage, handling and disposal of products and materials containing asbestos must be carried out in accordance with Randwick City Council’s Asbestos Policy and the relevant requirements of WorkCover NSW and the NSW Department of Environment & Conservation (formerly the Environment Protection Authority), including:

 

·      Occupational Health and Safety Act 2000

·      Occupational Health and Safety (Hazardous Substances) Regulation 2001

·      Occupational Health and Safety (Asbestos Removal Work) Regulation 2001

·      WorkCover NSW Code of Practice for the Safe Removal of Asbestos

·      Australian Standard 2601 (2001) – Demolition of Structures

·      The Protection of the Environment Operations Act 1997 and Protection of the Environment Operations (Waste) Regulation 1996.

·      Relevant Department of Environment & Conservation (DEC) / Environment Protection Authority (EPA) and WorkCover NSW Guidelines.

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development section or a copy can be obtained from Council’s Customer Service Centre.

 

42.     A Demolition Work Plan must be prepared for the development in accordance with Australian Standard AS2601-2001, Demolition of Structures.

 

The Work Plan must include the following information (as applicable):

 

·      The name, address, contact details and licence number of the Demolisher /Asbestos Removal Contractor

·      Details of hazardous materials, including asbestos

·      Method/s of demolition and removal of asbestos

·      Measures and processes to be implemented to ensure the health & safety of workers and community

·      Measures to be implemented to minimise any airborne asbestos and dust

·      Methods and location of disposal of any asbestos or other hazardous materials

·      Other relevant details, measures and requirements to be implemented as identified in the Asbestos Survey

·      Date the demolition and removal of asbestos will commence

 

The Demolition Work Plan must be submitted to Council and the Principal Certifying Authority (PCA) if the Council is not the PCA, not less than two (2) working days before commencing any demolition works involving asbestos products or materials.  A copy of the Demolition Work Plan must also be maintained on site and be made available to Council officers upon request.

 

Note it is the responsibility of the persons undertaking demolition work to obtain the relevant WorkCover licences and permits.

 

43.     A WorkCover licensed demolition or asbestos removal contractor must undertake removal of more than 10m of bonded asbestos (or as otherwise specified by WorkCover or relevant legislation). Removal of friable asbestos material must only be undertaken by contractor that holds a current friable asbestos removal licence.

 

44.     On demolition sites involving the removal of asbestos, a  professionally manufactured sign must be clearly displayed in a prominent visible position at the front of the site, containing the words ‘DANGER ASBESTOS REMOVAL IN PROGRESS” and include details of the licensed contractor. The sign shall measure not less than 400mm x 300mm and the sign is to be installed prior to demolition work commencing and is to remain in place until such time as all asbestos has been safely removed from the site.

 

45.     Asbestos waste must be stored, transported and disposed of in compliance with the Protection of the Environment Operations Act 1997 and the Protection of the Environment Operations (Waste) Regulation 1996.

 

Asbestos waste must be disposed of at an approved waste disposal depot (refer to the DEC or Waste Service NSW for details of sites). Copies of all receipts detailing method and location of disposal must be maintained on site and be provided to Council officers upon request, as evidence of correct disposal.

 

The following conditions are applied to provide adequate provisions for infrastructure and services:

46.     Any openings within or upon the road, footpath, nature strip or in any public place (i.e. for proposed drainage works or installation of services), must be carried out in accordance with the following requirements, to the satisfaction of Council:

 

a)       A Road / Asset Opening Permit must be obtained from Council prior to carrying out any works within or upon a road, footpath, nature strip or in any public place, in accordance with section 138 of the Roads Act 1993 and all of the conditions and requirements contained in the Road / Asset Opening Permit must be complied with.

 

b)       The owner/developer must ensure that all works within or upon the road reserve, footpath, nature strip or other public place are completed to the satisfaction of Council, prior to the issuing of a final occupation certificate for the development.

 

c)       Relevant Road / Asset Opening Permit fees, construction fees, inspection fees and security deposits, must be paid to Council prior to commencing any works within or upon the road, footpath, nature strip or other public place,

 

d)       The work and area must be maintained in a clean, safe and tidy condition at all times and the area must be thoroughly cleaned at the end of each days activities and upon completion.

 

e)       Public and vehicular safety must be maintained at all times and any related directions issued by Council officers must be complied with.

 

f)       The work can only be carried out in accordance with approved hours of building work as specified in the development consent, unless the express written approval of Council has been obtained beforehand.

 

g)       All work, including the provision of barricades, fencing, lighting, signage and traffic control, must be carried out in accordance with the NSW Roads and Traffic Authority publication - ‘Traffic Control at Work Sites’ and Australian Standard AS 1742.3 – Traffic Control Devices for Works on Roads, at all times.

 

h)       Sediment control measures must be implemented in accordance with the conditions of development consent and soil, sand or any other material must not be allowed to enter the stormwater drainage system or cause a pollution incident.

 

i)        The owner/developer must have a Public Liability Insurance Policy in force, with a minimum cover of $10 million and a copy of the insurance policy must be provided to Council prior to carrying out any works within or upon the road, footpath, nature strip or in any public place.

 

j)        Council’s Road / Asset Opening Officer must be notified at least 48 hours in advance of commencing any excavation works and also immediately upon completing the works (on 9399 0691 or 0409 033 921 during business hours), to enable any necessary inspections or works to be carried out.

 

ADVISORY MATTERS:

·      The applicant is advised that the Construction Certificate plans and specification must comply with the provisions of the Building Code of Australia (BCA) and the construction certificate must not be inconsistent with the development consent.

 

In this regard, the development consent plans do not show compliance with the deemed-to-satisfy provisions of the BCA.

 

Details of compliance with the relevant provisions of the Building Code of Australia and conditions of development consent are to be provided in the plans and specifications for the construction certificate.

 

The applicant/developer is advised to ensure that the development is not inconsistent with Council's consent and if necessary consult with Council’s Building Certification Services or your accredited certifier (as applicable) prior to submitting your construction certificate application to enable these matters to be addressed accordingly.

 

·      Building works must not be commenced until a construction certificate has been obtained from Council's Building Certification Services or an Accredited Certifier and either Council's Building Certification Services or an Accredited Certifier has been appointed as the Principal Certifying Authority (PCA) for this development.

 

Failure to obtain a Construction Certificate and appoint a PCA before commencing works is an offence, which renders the responsible person liable to a maximum penalty of $1.1 million under the Environmental Planning & Assessment Act 1979.

 

·      The applicant/owner is advised that this approval does not guarantee compliance with the provisions of the Disability Discrimination Act 1992 and the applicant should therefore consider their liability under the Act.  In this regard, the applicant is advised that compliance with the requirements of the Building Code of Australia and Australian Standard 1428.1 - Design for Access and Mobility does not necessarily satisfy the objectives of the Disability Discrimination Act 1992.

 

The applicant/owner is requested to give consideration to providing access and facilities for people with disabilities in accordance with Australian Standard 1428 Parts 1, 2, 3 and 4 - Design for Access and Mobility, which may be necessary to satisfy the objectives of the Disability Discrimination Act 1992.

 

·      The applicant is to advise Council in writing and/or photographs of any signs of existing damage to the Council roadway, footway, or verge prior to the commencement of any building/demolition works.

 

MOTION: (Andrews/Mayor, Cr Matson) CARRIED UNANIMOUSLY - SEE RESOLUTION.

 

 

 

D109/11   Development Application Report - 7-9 Creer Street, Randwick (DA/528/2011)

PL129/11

RESOLUTION: (Andrews/Mayor, Cr Matson) -

 

A.     That Council supports the objections under State Environmental Planning Policy No. 1 – Development Standards in respect to non-compliance with Clauses Clause 20B(1) of Randwick Local Environmental Plan 1998 (Consolidation), relating to minimum allotment sizes, on the grounds that the proposed development complies with the objectives of the above clauses, and will not adversely affect the amenity of the locality, and that the Department of Planning be advised accordingly.

 

B.     That Council, as the consent authority, grants development consent under Sections 80 and 80A of the Environmental Planning and Assessment Act 1979, as amended, to Development Application No. DA/528/2011 for the subdivision of the land into two Torrens Title allotments, at No. 7-9 Creer Street, Randwick, subject to the following conditions:

 

1.     The development must be implemented substantially in accordance with the plan numbered Sheet 1 of 1 prepared by Andrew Richard Thomas Surveyors reference 078-11, dated 4 April 2011. and received by Council on 21 July 2011, the application form and on any supporting information received with the application, except as may be amended  by the following conditions and as may be shown in red on the attached plans:

 

REQUIREMENTS PRIOR TO THE ISSUE OF SUBDIVISION CERTIFICATE

2.     The relevant requirements of the Sydney Water Act 1994 must be complied with and a Section 73 Compliance Certificate under the Sydney Water Act 1994 must be obtained from Sydney Water.

 

An Application for a Section 73 Certificate must be made through an authorised Water Servicing Coordinator. For details please refer to the Building Developing and Plumbing section of the website www.sydneywater.com.au then refer to “Water Servicing Coordinator” under Developing Your Land” or telephone 13 20 92 for assistance.

 

Following the application a “Notice of Requirements” will advise of water and sewer infrastructure to be built and charges to be paid. Please make early contact with the Coordinator, since building of water/sewer infrastructure can be time consuming and may impact on other services and building, driveway or landscape design.

The Section 73 Certificate must be submitted to the Principal Certifying Authority prior to the issuing of a subdivision certificate.

 

3.     The applicant shall create suitable rights of carriageway, easements for services, support and stormwater lines, etc as required. The applicant shall be advised that the minimum easement width for any stormwater line is 0.9 metres.

 

4.     A formal Subdivision Certificate application is required to be submitted to and approved by the Council and all conditions of this development consent are required to be satisfied prior to the release of the subdivision plans.

 

ADVISORY NOTES

§ Any proposal for a hardstand car space for lot 2 shall be the subject of a separate development application.

 

MOTION: (Andrews/Mayor, Cr Matson) CARRIED UNANIMOUSLY - SEE RESOLUTION.

 

 

 

D110/11   Development Application Report - 16 Greenwood Street, South Coogee (DA/522/2011)

PL130/11

RESOLUTION: (Andrews/Mayor, Cr Matson) -

 

A.     That Council supports the objections under State Environmental Planning Policy No. 1 – Development Standards in respect to non-compliance with Clauses 20F of Randwick Local Environmental Plan 1998, relating to Floor space ratio on the grounds that the proposed development complies with the objectives of the above clauses, and will not adversely affect the amenity of the locality, and that the Department of Planning be advised accordingly.

 

B.     That Council, as the consent authority, grants development consent under Sections 80 and 80A of the Environmental Planning and Assessment Act 1979, as amended, to Development Application No. 23/2011 for alterations and additions to the existing dwelling at 16 Greenwood Street, South Coogee subject to the following conditions:

 

GENERAL CONDITIONS

The development must be carried out in accordance with the following conditions of consent.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of environmental amenity.

 

Approved Plans & Supporting Documentation

1.       The development must be implemented substantially in accordance with the plans and supporting documentation listed below and endorsed with Council’s approved stamp, except where amended by Council in red and/or by other conditions of this consent:

 

Plan

Drawn by

Dated

Received

001 Issue A

Lombardo Mears

08.07.11

12th July 2011

100 Issue A

Lombardo Mears

08.07.11

12th July 2011

101 Issue A

Lombardo Mears

08.07.11

12th July 2011

102 Issue A

Lombardo Mears

08.07.11

12th July 2011

103 Issue A

Lombardo Mears

08.07.11

12th July 2011

201 Issue A Section A/B

Lombardo Mears

08.07.11

12th July 2011

201 Issue A Section CC

Lombardo Mears

08.07.11

12th July 2011

301 Issue A

Lombardo Mears

08.07.11

12th July 2011

302 Issue A

Lombardo Mears

08.07.11

12th July 2011

303 Issue A

Lombardo Mears

08.07.11

12th July 2011

 

REQUIREMENTS PRIOR TO THE ISSUE OF A CONSTRUCTION CERTIFICATE

The following conditions of consent must be complied with prior to the issue of a ‘Construction Certificate’ by either Randwick City Council or an Accredited Certifier.  All necessary information to demonstrate compliance with the following conditions of consent must be submitted with the construction certificate application.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent conditions and to achieve reasonable levels of environmental amenity.

 

Consent Requirements

2.       The requirements and amendments detailed in the ‘General Conditions’ must be complied with and be included in the construction certificate plans and associated documentation.

 

External Colours, Materials & Finishes

3.       The colours, materials and finishes of the external surfaces are to be compatible with the existing building and adjacent development to maintain the integrity and amenity of the building and the streetscape.

 

4.       The Council’s Development Engineer has inspected the above site and have determined that the design alignment level (concrete/paved/tiled level) at the property boundary for driveways, access ramps and pathways or the like,  must match the back of the existing footpath along the site frontage.

 

5.       The above alignment levels and the site inspection by Council’s Development Engineer have been issued at a prescribed fee of $135.00 (inclusive of GST). This amount is to be paid prior to a construction certificate being issued for the development.

 

 

REQUIREMENTS PRIOR TO THE COMMENCEMENT OF ANY WORKS

The following conditions of consent must be complied with prior to the commencement of any works on the site.  The necessary documentation and information must be provided to the Council or the ‘Principal Certifying Authority’, as applicable.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of public health, safety and environmental amenity.

 

Construction Certificate, Principal Certifying Authority & Commencement of Works

6.       Prior to the commencement of any building works, the following requirements       must be complied with:

 

a)       a Construction Certificate must be obtained from the Council or an accredited certifier, in accordance with the provisions of the Environmental Planning & Assessment Act 1979.

 

A copy of the construction certificate, the approved development consent plans and consent conditions must be kept on the site at all times and be made available to the Council officers and all building contractors for assessment.

 

b)       a Principal Certifying Authority (PCA) must be appointed to carry out the necessary building inspections and to issue an occupation certificate; and

 

c)       a principal contractor must be appointed for the building work, or in relation to residential building work, an owner-builder permit may be obtained in accordance with the requirements of the Home Building Act 1989, and the PCA and Council are to be notified accordingly; and

 

d)       the principal contractor must be advised of the required critical stage inspections and other inspections to be carried out, as specified by the Principal Certifying Authority; and

 

e)       at least two days notice must be given to the Council, in writing, prior to commencing any works.

 

In relation to residential building work, the principal contractor must be the holder of a contractor licence, in accordance with the provisions of the Home Building Act 1989.

 

Home Building Act 1989

7.       In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, the requirements of the Home Building Act 1989 must be complied with.

 

Details of the Licensed Building Contractor and a copy of the relevant Certificate of Home Warranty Insurance or a copy of the Owner-Builder Permit (as applicable) must be provided to the Principal Certifying Authority and Council, in writing.

 

Construction Noise & Vibration Management Plan

8.       Noise and vibration emissions during the construction of the building and associated site works must not result in damage to nearby premises or result in an unreasonable loss of amenity to nearby residents and the relevant requirements of the Protection of the Environment Operations Act 1997 and NSW DECC Guidelines must be satisfied at all times.

 

Noise and vibration from any rock excavation machinery, pile drivers and all plant and equipment must be minimised, by using appropriate plant and equipment, silencers and the implementation of noise management strategies.

 

A Construction Noise Management Plan, prepared in accordance with the NSW DECC Construction Noise Guideline by a suitably qualified person, is to be implemented throughout the works.  A copy of the strategy must be provided to the Principal Certifying Authority and Council prior to the commencement of works.

 

Temporary Site Fencing

9.         Temporary site safety fencing must be provided to the perimeter of the site (unless the site is separated from the adjoining land by an existing structurally adequate fence, having a minimum height of 1.5 metres). Temporary site fences are to have a minimum height of 1.8 metres and be constructed of cyclone wire fencing, with geotextile fabric attached to the inside of the fence to     provide dust control, or other material approved by Council.

 

Temporary site fences are to be structurally adequate, safe and be constructed in a professional manner and the use of poor quality materials or steel reinforcement mesh as fencing is not permissible.

 

Temporary fences must be in place prior to the commencement of any demolition, excavation or building works and be maintained throughout construction.

 

If it is proposed to locate any site fencing, hoardings or amenities upon any part of the footpath, nature strip or public place, a Local Approval application must be submitted to and approved by Council’s Health, Building & Regulatory Services before placing any item or article on the road, footpath or nature strip.

 

Construction Site Management Plan

10.     A Construction Site Management Plan must be developed and implemented prior to the commencement of any works. The construction site management plan must include the following measures, as applicable to the type of development:

 

·          location and construction of protective fencing / hoardings to the perimeter of the site;

·          location of site storage areas/sheds/equipment;

·          location of building materials for construction;

·          provisions for public safety;

·          dust control measures;

·          site access location and construction

·          details of methods of disposal of demolition materials;

·          protective measures for tree preservation;

·          provisions for temporary sanitary facilities;

·          location and size of waste containers/bulk bins;

·          details of proposed sediment and erosion control measures;

·          provisions for temporary stormwater drainage;

·          construction noise and vibration management;

·          construction traffic management details.

 

The site management measures must be implemented prior to the commencement of any site works and be maintained throughout the works, to the satisfaction of Council.

 

A copy of the Construction Site Management Plan must be provided to the Principal Certifying Authority and Council prior to commencing site works.  A copy must also be maintained on site and be made available to Council officers upon request.

 

REQUIREMENTS DURING CONSTRUCTION & SITE WORK

The following conditions of consent must be complied with during the demolition, excavation and construction of the development.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of public health, safety and environmental amenity during construction.

 

Demolition Work Requirements

11.     The demolition of buildings and the removal, storage, handling and disposal of building materials must be carried out in accordance with the relevant requirements of WorkCover NSW, the NSW Department of Environment, Climate Change & Water and Randwick City Council policies, including:

 

·          Occupational Health & Safety Act 2000 & Regulations

·          WorkCover NSW Code of Practice for the Safe Removal of Asbestos

·          WorkCover NSW Guidelines and Codes of Practice

·          Australian Standard 2601 (2001) – Demolition of Structures

·          The Protection of the Environment Operations Act 1997 and Protection of the Environment Operations (Waste) Regulation 2005

·          Relevant DECCW/EPA Guidelines

·          Randwick City Council Asbestos Policy

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development section or a copy can be obtained from Council’s Customer Service Centre.

 

Site Signage

12.     A sign must be erected and maintained in a prominent position on the site for the duration of the works, which contains the following details:

 

·          name, address, contractor licence number and telephone number of the principal contractor, including a telephone number at which the person may be contacted outside working hours, or owner-builder permit details (as applicable)

·          name, address and telephone number of the Principal Certifying                  Authority,

·          a statement stating that “unauthorised entry to the work site is prohibited”.

 

Sediment & Erosion Control

13.     Sediment and erosion control measures, must be implemented throughout the site works in accordance with the manual for Managing Urban Stormwater – Soils and Construction, published by Landcom, to Council’s satisfaction.  Details are to be included in the Construction Site Management Plan.

 

Public Safety & Site Management

14.     Public safety and convenience must be maintained at all times during demolition, excavation and construction works and the following requirements must be complied with:

 

a)   Building materials, sand, soil, waste materials, construction equipment or other activities must not be placed upon the footpath, roadway or nature strip at any time and the footpath, nature strip and road must be maintained in a clean condition and free from any obstructions, soil and debris at all times.

 

b)   Stockpiles of soil, sand, aggregate or other materials must not be located on any footpath, roadway, nature strip, drainage line or any public place and the stockpiles must be protected with adequate sediment control measures.

 

c)   Building operations such as brick cutting, washing tools or equipment and mixing mortar are not permitted on public footpaths, roadways, nature strips, in any public place or any location which may lead to the discharge of materials into the stormwater drainage system.

 

d)   Bulk bins/waste containers must not be located upon the footpath, roadway or nature strip at any time without the prior written approval of the Council.  Applications to place a waste container in a public place can be made to Council’s Health, Building and Regulatory Services department.

 

e)   Any part of Council’s road, footway or nature strip which is damaged as a result of the work must be repaired or replaced to Council’s satisfaction.

 

f)    Temporary safety fencing is to be provided to any swimming pools under construction, pending the completion of all building work and the pool must not be filled until a fencing inspection has been carried out and approved by the principal certifying authority.

 

Excavations, Back-filling & Retaining Walls

15.     All excavations and backfilling associated with the erection or demolition of a building must be executed safely in accordance with appropriate professional standards and excavations must be properly guarded and supported to prevent them from being dangerous to life, property or buildings.

 

Retaining walls, shoring or piling must be provided to support land which is excavated in association with the erection or demolition of a building, to prevent the movement of soil and to support the adjacent land and buildings, if the soil conditions require it.  Adequate provisions are also to be made for drainage.

 

Details of proposed retaining walls, shoring or piling are to be submitted to and approved by the Principal Certifying Authority for the development prior to commencing such excavations or works.

 

Support of Adjoining Land

16.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 E of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that the adjoining land and buildings located upon the adjoining land must be adequately supported at all times.

 

a)    If the development involves an excavation that extends below the level of the base of the footings of a building on adjoining land, the person having the benefit of the development must, at the person’s own expense:

 

i)     protect and support the adjoining premises from possible damage from the excavation, and

ii)     where necessary, underpin the adjoining premises to prevent any such damage.

 

b)    The condition referred to in subclause a) does not apply if the person having the benefit of the development consent owns the adjoining land or the owner of the adjoining land has given consent in writing to that condition not applying.

 

17.     Prior to undertaking any demolition, excavation or building work in the following       circumstances, a report must be obtained from a professional engineer which details the methods of support for the dwelling or associated structure on the adjoining land, to the satisfaction of the Principal Certifying Authority:

 

·       when undertaking excavation or building work within the zone of influence of the footings of a dwelling or associated structure that is located on the adjoining land;

·       when undertaking demolition work to a wall of a dwelling that is built to a common or shared boundary (eg. semi-detached or terrace dwelling);

·       when constructing a wall to a dwelling or associated structure that is located within 900mm of a dwelling located on the adjoining land.

 

The demolition, excavation and building work and the provision of support to the dwelling or associated structure on the adjoining land, must also be carried out in accordance with the abovementioned report, to the satisfaction of the Principal Certifying Authority.

 

  Restriction on Working Hours

18.     Building, demolition and associated site works must be carried out in accordance with the following requirements:

 

Activity

Permitted working hours

All building, demolition and site work, including site deliveries (except as detailed below)

·   Monday to Friday - 7.00am to 5.00pm

·   Saturday - 8.00am to 5.00pm

·   Sunday & public holidays - No work permitted

Excavating of rock, use of jack-hammers, pile-drivers, vibratory rollers/compactors or the like

 

·   Monday to Friday - 8.00am to 5.00pm

·   Saturday - No work permitted

·   Sunday & public holidays - No work permitted

 

An application to vary the abovementioned hours may be submitted to Council’s Manager Health, Building & Regulatory Services for consideration and approval to vary the specified hours may be granted in exceptional circumstances and for limited occasions (e.g. for public safety, traffic management or road safety reasons).  Any applications are to be made on the standard application form and include payment of the relevant fees and supporting information.  Applications must be made at least 10 days prior to the date of the proposed work and the prior written approval of Council must be obtained to vary the standard permitted working hours.

 

  Inspections During Construction

19.     The building works must be inspected by the Principal Certifying Authority, in accordance with sections 109 E (3) of the Environmental Planning & Assessment Act 1979 and clause 162A of the Environmental Planning & Assessment Regulation 2000, to monitor compliance with the relevant standards of construction, Council’s development consent and the construction certificate.

 

The Principal Certifying Authority must specify the relevant stages of construction to be inspected and a satisfactory inspection must be carried out, to the satisfaction of the Principal Certifying Authority, prior to proceeding to the subsequent stages of construction or finalisation of the works (as applicable).

 

            Building Encroachments

20.     There must be no encroachment of any structures or building work onto Council’s road reserve, footway, nature strip or public place.

 

21.     The applicant must meet the full cost for Council or a Council approved contractor to repair/replace any damaged sections of Council's footpath, kerb & gutter, nature strip etc which are due to building works being carried out at the above site. This includes the removal of cement slurry from Council's footpath and roadway.

 

22.     All external civil work to be carried out on Council property (including the installation and repair of roads, footpaths, vehicular crossings, kerb and guttering and drainage works), must be carried out in accordance with Council’s       Policy for “Vehicular Access and Road and Drainage Works” and the following requirements:

 

a)       All work on Council land must be carried out by Council, unless specific written approval has been obtained from Council to use non-Council contractors.

 

b)       Details of the proposed civil works to be carried out on Council land must be submitted to Council in a Pre-paid Works Application Form, prior to issuing an occupation certificate, together with payment of the relevant fees.

 

c)       If it is proposed to use non-Council contractors to carry out the civil works on Council land, the work must not commence until the written approval has been obtained from Council and the work must be carried out in accordance with the conditions of consent, Council’s design details and payment of a Council design and supervision fee.

 

d)       The civil works must be completed in accordance with Council’s conditions of consent and approved design and construction documentation, prior to occupation of the development, or as otherwise approved by Council in writing.

 

23.     A public utility impact assessment must be carried out on all public utility services on the site, roadway, nature strip, footpath, public reserve or any public areas associated with and/or adjacent to the development/building works and include relevant information from public utility authorities and exploratory trenching or pot-holing, if necessary, to determine the position and level of service.

       

24.     The applicant must meet the full cost for telecommunication companies, gas providers, Energy Australia and Sydney Water to adjust/repair/relocate their services as required.  The applicant must make the necessary arrangements with the service authority.

 

25.     That part of the naturestrip upon Council's footway which is damaged during the construction of the proposed works shall be excavated to a depth of 150mm, backfilled with topsoil equivalent with 'Organic Garden Mix' as supplied by Australian Native Landscapes, and re-turfed with Kikuyu turf or similar. Such works shall be completed at the applicants expense prior to the issue of a final       Occupation Certificate.

 

REQUIREMENTS PRIOR TO THE ISSUE OF AN OCCUPATION CERTIFICATE

The following conditions of consent must be complied with prior to the ‘Principal Certifying Authority’ issuing an ‘Occupation Certificate’.

 

Note:        For the purpose of this consent, any reference to ‘occupation certificate’ shall also be taken to mean ‘interim occupation certificate’ unless otherwise stated.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent and to maintain reasonable levels of public health, safety and amenity.

 

Occupation Certificate Requirements

26.     An Occupation Certificate must be obtained from the Principal Certifying Authority prior to any occupation of the building work encompassed in this development consent (including alterations and additions to existing buildings), in accordance with the relevant provisions of the Environmental Planning & Assessment Act 1979.

 

An Occupation Certificate must not be issued for the development if the development is inconsistent with the development consent.  The relevant requirements of the Environmental Planning & Assessment Act 1979 and conditions of development consent must be satisfied prior to the issuing of an occupation certificate.

 

ADVISORY NOTES

The following information is provided for your assistance to ensure compliance with the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, or other relevant legislation and Council’s policies.  This information does not form part of the conditions of development consent pursuant to Section 80A of the Act.

 

·          The requirements and provisions of the Environmental Planning & Assessment Act 1979 and Environmental Planning & Assessment Regulation 2000, must be fully complied with at all times.

 

Failure to comply with these requirements is an offence, which renders the responsible person liable to a maximum penalty of $1.1 million.  Alternatively, Council may issue a penalty infringement notice (for up to $1,500) for each offence.  Council may also issue notices and orders to demolish unauthorised or non-complying building work, or to comply with the requirements of Council’s development consent.

 

·          Demolition, building or excavation work must not be commenced until;

 

§  A Construction Certificate has been obtained from Council or an Accredited Certifier

§  Council or an Accredited Certifier has been appointed as the Principal Certifying Authority for the development

§  Council and the Principal Certifying Authority have been given at least 2 days notice (in writing) prior to commencing any works.

 

Council’s Building Approvals & Certification team can issue Construction Certificates and be your Principal Certifying Authority for the development, to undertake inspections and ensure compliance with the development consent, relevant building regulations and standards of construction.  For further details contact Council’s Building Approvals & Certification team on 9399 0944.

 

·          This determination does not include an assessment of the proposed works under the Building Code of Australia (BCA) and other relevant Standards.  All new building work (including alterations and additions) must comply with the BCA and relevant Standards and you are advised to liaise with your architect, engineer and building consultant prior to lodgement of your construction certificate.

 

·          A Local Approval application must be submitted to and be approved by Council's Building Approvals & Certification team prior to commencing any of the following activities on a footpath, road, nature strip or in any public place:-

 

§  Install or erect any site fencing, hoardings or site structures

§  Operate a crane or hoist goods or materials over a footpath or road

§  Placement of a waste skip or any other container or article.

 

For further information please contact Council’s Building Approvals & Certification team on 9399 0944.

 

·          Specific details of the location of the building/s should be provided in the Construction Certificate to demonstrate that the proposed building work will not encroach onto the adjoining properties, Council’s road reserve or any public place, to the satisfaction of the Certifying Authority.

 

·          Prior to commencing any works, the owner/builder should contact Dial Before You Dig on 1100 or www.dialbeforeyoudig.com.au and relevant Service Authorities, for information on potential underground pipes and cables within the vicinity of the development site.

 

●      The applicant is to advise Council in writing and/or photographs of any signs of existing damage to the Council roadway, footway, or verge prior to the commencement of any building/demolition works.

 

MOTION: (Andrews/Mayor, Cr Matson) CARRIED UNANIMOUSLY - SEE RESOLUTION.

 

 

 

D111/11   Development Application Report - 43 Oswald Street, Randwick (DA/270/2011)

PL131/11

RESOLUTION: (Andrews/Mayor, Cr Matson) -

 

A.     That Council support the objections under State Environmental Planning Policy No. 1 – Development Standards in respect to non-compliance with Clauses 20F & 20G of the Randwick Local Environmental Plan 1988 relating to Floor Space Ratios and Building Heights respectively, on the grounds that the proposed development complies with the objectives of the above clauses, and will not adversely affect the amenity of the locality, and that the Department of Planning be advised accordingly.

 

B.     That Council, as the consent authority, grants development consent under Sections 80 and 80A of the Environmental Planning and Assessment Act 1979, as amended, to Development Application No. DA/270/2011 for alterations and additions to the existing dwelling including new attic addition with dormer window facing Oswald Street, at No. 43 Oswald Street, Randwick, subject to the following conditions:

 

DEVELOPMENT CONSENT CONDITIONS

 

GENERAL CONDITIONS

The development must be carried out in accordance with the following conditions of consent.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of environmental amenity.

 

Approved Plans & Supporting Documentation

1.       The development must be implemented substantially in accordance with the plans and supporting documentation listed below and endorsed with Council’s approved stamp, except where amended by Council in red and/or by other conditions of this consent:

 

Plan

Drawn by

Dated

Received

1/-

Absolute Attics

Mar 2011

15 April 2011

2/-

Absolute Attics

Nov/Dec 2010

15 April 2011

3/-

Absolute Attics

Nov/Dec 2010

15 April 2011

4/A

Absolute Attics

17/03/11

15 April 2011

5/A

Absolute Attics

20/12/10

15 April 2011

6/-

Absolute Attics

Mar 2011

15 April 2011

7/A

Absolute Attics

21/12/10

15 April 2011

8/-

Absolute Attics

Mar 2011

15 April 2011

9/-

Absolute Attics

Mar 2011

15 April 2011

10/-

Absolute Attics

Mar 2011

15 April 2011

 

BASIX Certificate

No.

Dated

Received

 

A108279

6 April 2011

15 April 2011

 

REQUIREMENTS BEFORE A CONSTRUCTION CERTIFICATE CAN BE ISSUED

The following conditions of consent must be complied with before a ‘Construction Certificate’ is issued by either Randwick City Council or an Accredited Certifier.  All necessary information to demonstrate compliance with the following conditions of consent must be included in the documentation for the construction certificate.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent conditions and to achieve reasonable levels of environmental amenity.

 

Consent Requirements

2.       The requirements and amendments detailed in the ‘General Conditions’ must be complied with and be included in the construction certificate plans and associated documentation.

 

External Colours, Materials & Finishes

3.       a)     The colours, materials and finishes of the external surfaces are to be compatible with the existing building and adjacent development to maintain the integrity and amenity of the building and the streetscape.

 

External materials, finishes and colours of the building are required to match, as closely as possible, the existing building and any metal roof sheeting is to be pre-painted (e.g. Colourbond) to limit the level of reflection and glare.

 

b)     Details of the proposed colours, materials and textures (i.e. a schedule and brochure/s or sample board) are to be submitted to and approved by Council’s Manager Development Assessments prior to issuing a construction certificate for the development.

 

Section 94A Development Contributions

4.       In accordance with Council’s Section 94A Development Contributions Plan effective from 2 July 2007, based on the development cost of $100,400, the following applicable monetary levy must be paid to Council: $502.

       

The levy must be paid in cash, bank cheque or by credit card prior to a construction certificate [or subdivision certificate] being issued for the proposed development.  The development is subject to an index to reflect quarterly variations in the Consumer Price Index (CPI) from the date of Council’s determination to the date of payment.

 

Council’s Section 94A Development Contribution Plans may be inspected at the Customer Service Centre, Administrative Centre, 30 Frances Street, Randwick or at www.randwick.nsw.gov.au.

 

Long Service Levy Payments

5.       The required Long Service Levy payment, under the Building and Construction Industry Long Service Payments Act 1986, must be forwarded to the Long Service Levy Corporation or the Council, in accordance with Section 109F of the Environmental Planning & Assessment Act 1979.

 

      At the time of this development consent, Long Service Levy payment is applicable on building work having a value of $25,000 or more, at the rate of 0.35% of the cost of the works.

 

REQUIREMENTS TO BE INCLUDED IN THE CONSTRUCTION CERTIFICATE

The requirements contained in the following conditions of consent must be complied with and details of compliance must be included in the construction certificate for the development.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Councils development consent conditions and to achieve reasonable levels of environmental amenity.

 

Compliance with the Building Code of Australia

6.       In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that all building work must be carried out in accordance with the provisions of the Building Code of Australia (BCA).  Details of compliance with the BCA are to be included in the construction certificate application.

 

Structural Adequacy

7.       Certificate of Adequacy supplied by a professional engineer shall be submitted to the certifying authority (and the Council, if the Council is not the certifying authority), certifying the structural adequacy of the existing structure to support the additional attic level.

 

Smoke Alarms

8.       Smoke alarms are required to be installed in accordance with the relevant provisions of the Building Code of Australia (volume 2) smoke alarms must comply with AS3786.  Smoke alarms must be connected to the consumer mains electric power supply and provided with a battery back-up.  Details of compliance are to be included in the construction certificate.

 

BASIX Requirements

9.       In accordance with section 80A(11) of the Environmental Planning & Assessment Act 1979 and clause 97A of the Environmental Planning & Assessment Regulation 2000, the requirements and commitments contained in the relevant BASIX Certificate must be complied with.

 

The required commitments listed and identified in the BASIX Certificate must be included on the construction certificate plans, specifications and associated documentation, to the satisfaction of the Certifying Authority.

 

The design of the building must not be inconsistent with the development consent and any proposed variations to the building to achieve the BASIX commitments may necessitate a new development consent or amendment to the existing consent to be obtained, prior to a construction certificate being issued.

 

Stormwater Drainage

10.     A surface water/stormwater drainage system must be provided in accordance with the following requirements, to the satisfaction of the Certifying Authority and details are to be included in the construction certificate:-

 

a)     Surface water/stormwater drainage systems must be provided in accordance with the relevant requirements of the Building Code of Australia (Volume 2);

 

b)     The surface water/stormwater must be drained and discharged to the street gutter or, subject to site suitability, the stormwater may be drained to a suitably designed absorption pit;

 

c)     Any absorption pits or soaker wells should be located not less than 3m from any adjoining premises and the stormwater must not be directed to any adjoining premises or cause a nuisance;

 

d)     External paths and ground surfaces are to be constructed at appropriate levels and be graded and drained away from the building and adjoining premises, so as not to result in the entry of water into the building, or cause a nuisance or damage to the adjoining premises;

 

e)     Details of any proposed drainage systems or works to be carried out in the road, footpath or nature strip must be submitted to and approved by Council before commencing these works.

 

REQUIREMENTS PRIOR TO THE COMMENCEMENT OF ANY WORKS

The following conditions of consent must be complied with prior to the commencement of any works on the site.  The necessary documentation and information must be provided to the Council or the ‘Principal Certifying Authority’, as applicable.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of public health, safety and environmental amenity.

 

Construction Certificate, Principal Certifying Authority & Commencement of Works

11.     Prior to the commencement of any building works, the following requirements must be complied with:

 

a)     a Construction Certificate must be obtained from the Council or an accredited certifier, in accordance with the provisions of the Environmental Planning & Assessment Act 1979.

 

A copy of the construction certificate, the approved development consent plans and consent conditions must be kept on the site at all times and be made available to the Council officers and all building contractors for assessment.

 

b)     a Principal Certifying Authority (PCA) must be appointed to carry out the necessary building inspections and to issue an occupation certificate; and

 

c)     a principal contractor must be appointed for the building work, or in relation to residential building work, an owner-builder permit may be obtained in accordance with the requirements of the Home Building Act 1989, and the PCA and Council are to be notified accordingly; and

 

d)     the principal contractor must be advised of the required critical stage inspections and other inspections to be carried out, as specified by the Principal Certifying Authority; and

 

e)     at least two days notice must be given to the Council, in writing, prior to commencing any works.

 

In relation to residential building work, the principal contractor must be the holder of a contractor licence, in accordance with the provisions of the Home Building Act 1989.

 

Home Building Act 1989

12.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, the requirements of the Home Building Act 1989 must be complied with.

 

Details of the Licensed Building Contractor and a copy of the relevant Certificate of Home Warranty Insurance or a copy of the Owner-Builder Permit (as applicable) must be provided to the Principal Certifying Authority and Council.

 

Dilapidation Reports

13.     A dilapidation report prepared by a professional engineer, building surveyor or other suitably qualified independent person must be submitted to the satisfaction of the Principal Certifying Authority prior to commencement of any demolition, excavation or building works, in the following cases:

 

·        excavations for new dwellings, additions to dwellings, swimming pools or the like which are proposed to be located within the zone of influence of the footings of any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

·        new dwellings or additions to dwellings sited up to shared property boundaries (e.g.  additions to a semi-detached dwelling or terraced dwellings),

·        excavations for new dwellings, additions to dwellings, swimming pools or the like which are within rock and may result in vibration and or potential damage to any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

·            as otherwise may be required by the Principal Certifying Authority.

 

The report (including photographs) are required to detail the current condition and status of any dwelling, associated garage or other substantial structure located upon the adjoining premises, which may be affected by the subject works.  A copy of the dilapidation report is to be given to the owners of the premises encompassed in the report/s before commencing any works.

 

Construction Noise & Vibration Management Plan

14.     Noise and vibration emissions during the construction of the building and associated site works must not result in damage to nearby premises or result in an unreasonable loss of amenity to nearby residents and the relevant requirements of the Protection of the Environment Operations Act 1997 and NSW DECC Guidelines must be satisfied at all times.

 

Noise and vibration from any rock excavation machinery, pile drivers and all plant and equipment must be minimised, by using appropriate plant and equipment, silencers and the implementation of noise management strategies.

 

A Construction Noise Management Plan, prepared in accordance with the NSW DECC Construction Noise Guideline by a suitably qualified person, is to be implemented throughout the works.  A copy of the strategy must be provided to the Principal Certifying Authority and Council prior to the commencement of works on site.

 

Temporary Site Fencing

15.     Temporary site safety fencing must be provided to the perimeter of the site (unless the site is separated from the adjoining land by an existing structurally adequate fence, having a minimum height of 1.5 metres).  Temporary site fences are to have a minimum height of 1.8 metres and be constructed of cyclone wire fencing, with geotextile fabric attached to the inside of the fence to provide dust control, or other material approved by Council.

 

Temporary site fences are to be structurally adequate, safe and be constructed in a professional manner and the use of poor quality materials or steel reinforcement mesh as fencing is not permissible.

 

Temporary fences must be in place prior to the commencement of any demolition, excavation or building works and be maintained throughout construction.

 

If it is proposed to locate any site fencing, hoardings or amenities upon any part of the footpath, nature strip or public place, a Local Approval application must be submitted to and approved by Council’s Health, Building & Regulatory Services before placing any item or article on the road, footpath or nature strip.

 

Construction Site Management Plan

16.     A Construction Site Management Plan must be developed and implemented prior to the commencement of any works. The construction site management plan must include the following measures, as applicable to the type of development:

 

·            location and construction of protective fencing / hoardings to the perimeter of the site;

·            location of site storage areas/sheds/equipment;

·            location of building materials for construction;

·            provisions for public safety;

·            dust control measures;

·            site access location and construction

·            details of methods of disposal of demolition materials;

·            protective measures for tree preservation;

·            provisions for temporary sanitary facilities;

·            location and size of waste containers/bulk bins;

·            details of proposed sediment and erosion control measures;

·            provisions for temporary stormwater drainage;

·            construction noise and vibration management;

·            construction traffic management details.

 

The site management measures must be implemented prior to the commencement of any site works and be maintained throughout the works, to the satisfaction of Council.

 

A copy of the Construction Site Management Plan must be provided to the Principal Certifying Authority and Council prior to commencing site works.  A copy must also be maintained on site and be made available to Council officers upon request.

 

Demolition Work Plan

17.     A Demolition Work Plan must be prepared for the development in accordance with Australian Standard AS2601-2001, Demolition of Structures and relevant environmental/occupational health and safety requirements.

 

The Demolition Work Plan must include the following information (as applicable):

 

·        The name, address, contact details and licence number of the Demolisher /Asbestos Removal Contractor

·        Details of hazardous materials (including asbestos)

·        Method/s of demolition (including removal of any asbestos)

·        Measures and processes to be implemented to ensure the health & safety of workers and community

·        Measures to be implemented to minimise any airborne dust and asbestos

·        Methods and location of disposal of any hazardous materials (including asbestos)

·        Other relevant details, measures and requirements to be implemented

·        Details of re-use, recycling and disposal of waste demolition/building materials

·        Date the demolition works will commence

 

The Demolition Work Plan must be submitted to the Principal Certifying Authority (PCA), not less than two (2) working days before commencing any demolition work.  A copy of the Demolition Work Plan must be maintained on site and be made available to Council officers upon request.

 

If the work involves asbestos products or materials, a copy of the Demolition Work Plan must also be provided to Council not less than 2 days before commencing those works.

 

    Notes

§  It is the responsibility of the persons undertaking demolition work to obtain the relevant WorkCover licences and permits.

§  Refer to the conditions within the “Requirements During Construction & Site Work”, for further details and requirements relating to demolition work, removal of any asbestos and public safety.

 

Sydney Water

18.     All building, plumbing and drainage work must be carried out in accordance with the requirements of the Sydney Water Corporation.

 

Prior to the commencement of excavation or building works, the approved Construction Certificate plans must be submitted to a Sydney Water Quick Check agent or Customer Centre, to determine whether the development will affect Sydney Water’s sewer and water mains, stormwater drains and/or easements, and if any further requirements need to be met. 

 

If suitable, the plans will be appropriately stamped.  For Quick Check agent details please refer to Sydney Water’s web site at www.sydneywater.com.au and go to the Building, Developing and Plumbing, then Quick Check or Building and Renovating or telephone 13 20 92.

 

The principal certifying authority must ensure that a Quick Check Agent/Sydney Water has appropriately stamped the plans before commencing works.

 

Public Utilities

19.     A Public Utility Impact Assessment must be carried out to identify all public utility services located on the site, roadway, nature strip, footpath, public reserve or any public areas associated with and/or adjacent to the building works.

 

Documentary evidence from the relevant public utility authorities confirming that their requirements have been or are able to be satisfied, must be submitted to the Principal Certifying Authority prior to the commencement of any works.

 

The owner/builder must make the necessary arrangements and meet the full cost for telecommunication companies, gas providers, Energy Australia, Sydney Water and other authorities to adjust, repair or relocate their services as required.

 

REQUIREMENTS DURING CONSTRUCTION & SITE WORK

The following conditions of consent must be complied with during the demolition, excavation and construction of the development.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of public health, safety and environmental amenity during construction.

 


Inspections During Construction

20.     The building works must be inspected by the Principal Certifying Authority, in accordance with sections 109 E (3) of the Environmental Planning & Assessment Act 1979 and clause 162A of the Environmental Planning & Assessment Regulation 2000, to monitor compliance with the relevant standards of construction, Council’s development consent and the construction certificate.

 

The Principal Certifying Authority must specify the relevant stages of construction to be inspected and a satisfactory inspection must be carried out, to the satisfaction of the Principal Certifying Authority, prior to proceeding to the subsequent stages of construction or finalisation of the works (as applicable).

 

Site Signage

21.     A sign must be erected and maintained in a prominent position on the site for the duration of the works, which contains the following details:

 

·        name, address, contractor licence number and telephone number of the principal contractor, including a telephone number at which the person may be contacted outside working hours, or owner-builder permit details (as applicable)

·        name, address and telephone number of the Principal Certifying Authority,

·        a statement stating that “unauthorised entry to the work site is prohibited”.

 

Restriction on Working Hours

22.     Building, demolition and associated site works must be carried out in accordance with the following requirements:

 

Activity

Permitted working hours

All building, demolition and site work, including site deliveries (except as detailed below)

·   Monday to Friday - 7.00am to 5.00pm

·   Saturday - 8.00am to 5.00pm

·   Sunday & public holidays - No work permitted

Excavating of rock, use of jack-hammers, pile-drivers, vibratory rollers/compactors or the like

 

·   Monday to Friday - 8.00am to 5.00pm

·   Saturday - No work permitted

·   Sunday & public holidays - No work permitted

 

An application to vary the abovementioned hours may be submitted to Council’s Manager Health, Building & Regulatory Services for consideration and approval to vary the specified hours may be granted in exceptional circumstances and for limited occasions (e.g. for public safety, traffic management or road safety reasons).  Any applications are to be made on the standard application form and include payment of the relevant fees and supporting information.  Applications must be made at least 10 days prior to the date of the proposed work and the prior written approval of Council must be obtained to vary the standard permitted working hours.

 

Demolition Work Requirements

23.     The demolition of buildings and the removal, storage, handling and disposal of building materials must be carried out in accordance with the relevant requirements of WorkCover NSW, the NSW Department of Environment, Climate Change & Water and Randwick City Council policies, including:

 

·            Occupational Health & Safety Act 2000 & Regulations

·            WorkCover NSW Code of Practice for the Safe Removal of Asbestos

·            WorkCover NSW Guidelines and Codes of Practice

·            Australian Standard 2601 (2001) – Demolition of Structures

·            The Protection of the Environment Operations Act 1997 and Protection of the Environment Operations (Waste) Regulation 2005

·            Relevant DECCW/EPA Guidelines

·            Randwick City Council Asbestos Policy

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development section or a copy can be obtained from Council’s Customer Service Centre.

 

Removal of Asbestos Materials

24.     Work involving the demolition, storage or disposal of asbestos products and materials must be carried out in accordance with the following requirements:

 

·            Relevant Occupational Health & Safety legislation and WorkCover NSW requirements

 

·            Randwick City Council’s Asbestos Policy

 

·            A WorkCover licensed demolition or asbestos removal contractor must undertake removal of more than 10m2 of bonded asbestos (or as otherwise specified by WorkCover or relevant legislation).  Removal of friable asbestos material must only be undertaken by contractor that holds a current friable asbestos removal licence.  A copy of the relevant licence must be provided to the Principal Certifying Authority.

 

·            On sites involving the removal of asbestos, a sign must be clearly displayed in a prominent visible position at the front of the site, containing the words ‘DANGER ASBESTOS REMOVAL IN PROGRESS’ and include details of the licensed contractor.

 

·            Asbestos waste must be stored, transported and disposed of in compliance with the Protection of the Environment Operations Act 1997 and the Protection of the Environment Operations (Waste) Regulation 2005.  Details of the landfill site (which must be lawfully able to receive asbestos materials) must be provided to the Principal Certifying Authority.

 

·            A Clearance Certificate or Statement, prepared by a suitably qualified person (i.e. an occupational hygienist, licensed asbestos removal contractor, building consultant, architect or experienced licensed building contractor), must be provided to Council and the Principal certifying authority upon completion of the asbestos related works which confirms that the asbestos material have been removed appropriately and the relevant conditions of consent have been satisfied.

 

A copy of Council’s Asbestos Policy is available on Council’s web site at www.randwick.nsw.gov.au in the Building & Development Section or a copy can be obtained from Council’s Customer Service Centre.

 

Sediment & Erosion Control

25.     Sediment and erosion control measures, must be implemented throughout the site works in accordance with the manual for Managing Urban Stormwater – Soils and Construction, published by Landcom, to Council’s satisfaction.  Details are to be included in the Construction Site Management Plan.

 

Public Safety & Site Management

26.     Public safety and convenience must be maintained at all times during demolition, excavation and construction works and the following requirements must be complied with:

 

·           Building materials, sand, soil, waste materials, construction equipment or other articles must not be placed upon the footpath, roadway or nature strip at any time.

 

·           The road, footpath, vehicular crossing and nature strip must be maintained in a good, safe, clean condition and free from any excavations, obstructions, trip hazards, goods, materials, soils or debris at all times.  Any damage caused to the road, footway, vehicular crossing, nature strip or any public place must be repaired immediately, to the satisfaction of Council.

 

·           Building operations such as brick cutting, washing tools or equipment and mixing mortar are not permitted on public footpaths, roadways, nature strips, in any public place or any location which may lead to the discharge of materials into the stormwater drainage system.

 

·           Bulk bins/waste containers must not be located upon the footpath, roadway or nature strip at any time without the prior written approval of the Council.  Applications to place a waste container in a public place can be made to Council’s Health, Building and Regulatory Services department.

 

·           Temporary safety fencing is to be provided to any swimming pools under construction, pending the completion of all building work and the pool must not be filled until a fencing inspection has been carried out and approved by the principal certifying authority.

 

Support of Adjoining Land, Excavations & Retaining Walls

27.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 E of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that the adjoining land and buildings located upon the adjoining land must be adequately supported at all times.

 

28.     All excavations and backfilling associated with the erection or demolition of a building must be executed safely in accordance with appropriate professional standards and excavations must be properly guarded and supported to prevent them from being dangerous to life, property or buildings.

 

29.     Prior to undertaking any demolition, excavation or building work in the following circumstances, a report must be obtained from a professional engineer which details the methods of support for the dwelling or associated structure on the adjoining land, to the satisfaction of the Principal Certifying Authority:

 

·      when undertaking excavation or building work within the zone of influence of the footings of a dwelling or associated structure that is located on the adjoining land;

·      when undertaking demolition work to a wall of a dwelling that is built to a common or shared boundary (eg. semi-detached or terrace dwelling);

·      when constructing a wall to a dwelling or associated structure that is located within 900mm of a dwelling located on the adjoining land.

 

The demolition, excavation and building work and the provision of support to the dwelling or associated structure on the adjoining land, must also be carried out in accordance with the abovementioned report, to the satisfaction of the Principal Certifying Authority.

 

Building Encroachments

30.     There must be no encroachment of any structures or building work onto Council’s road reserve, footway, nature strip or public place.

 

Road/Asset Opening Permit

31.     A Road / Asset Opening Permit must be obtained from Council prior to commencing any excavations or works within or upon a road, footpath, nature strip or in any public place, in accordance with section 138 of the Roads Act 1993 and all of the conditions and requirements contained in the Road / Asset Opening Permit must be complied with.

 

For further information, please contact Council’s Road / Asset Opening Officer on 9399 0691 or 9399 0999.

 

REQUIREMENTS PRIOR TO THE ISSUE OF AN OCCUPATION CERTIFICATE

The following conditions of consent must be complied with prior to the ‘Principal Certifying Authority’ issuing an ‘Occupation Certificate’.

 

Note:  For the purpose of this consent, any reference to ‘occupation certificate’ shall also be taken to mean ‘interim occupation certificate’ unless otherwise stated.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent and to maintain reasonable levels of public health, safety and amenity.

 

Occupation Certificate Requirements

32.     An Occupation Certificate must be obtained from the Principal Certifying Authority prior to any occupation of the building work encompassed in this development consent (including alterations and additions to existing buildings), in accordance with the relevant provisions of the Environmental Planning & Assessment Act 1979.

 

An Occupation Certificate must not be issued for the development if the development is inconsistent with the development consent.  The relevant requirements of the Environmental Planning & Assessment Act 1979 and conditions of development consent must be satisfied prior to the issuing of an occupation certificate.

 

BASIX Requirements

33.     In accordance with Clause 154B of the Environmental Planning & Assessment Regulation 2000, a Certifying Authority must not issue an Occupation Certificate for this development, unless it is satisfied that each of the required BASIX commitments have been fulfilled.

 

Relevant documentary evidence of compliance with the BASIX commitments is to be forwarded to the Council upon issuing an Occupation Certificate.

 

Occupant Safety

34.     Openable windows to a room, corridor, stairway or the like with a floor level more than 4m above the external ground/surface level, must be designed and constructed to reduce the likelihood of a child accessing and falling through the window opening.

 

Options may include one or more of the following measures:

 

·            The window having a minimum sill height of 1.5m above the internal floor level,

·            Providing a window locking device at least 1.5m above the internal floor level,

·            Fixing or securing the window (e.g. by screws or a window locking device) to restrict or to be able to secure the extent of the opening to a maximum width of 125mm,

·            Installing a fixed heavy-duty gauge metal screen over the opening (e.g. A metal security screen or metal security mesh and frame system, but not standard fly-screen material),

·            Other appropriate effective safety measures or barrier.

 

The relevant measures must be implemented prior to the issue of an occupation certificate.

 

Council’s Infrastructure, Vehicular Crossings & Road Openings

35.     All external civil work to be carried out on Council property (including the installation and repair of roads, footpaths, vehicular crossings, kerb and guttering and drainage works), must be carried out in accordance with Council's Policy for "Vehicular Access and Road and Drainage Works" and the following requirements:

 

a)     All work on Council land must be carried out by Council, unless specific written approval has been obtained from Council to use non-Council contractors.

 

b)     Details of the proposed civil works to be carried out on Council land must be submitted to Council in a Pre-paid Works Application Form, prior to issuing an occupation certificate, together with payment of the relevant fees.

 

c)     If it is proposed to use non-Council contractors to carry out the civil works on Council land, the work must not commence until the written approval has been obtained from Council and the work must be carried out in accordance with the conditions of consent, Council’s design details and payment of a Council design and supervision fee.

 

d)     The civil works must be completed in accordance with Council’s conditions of consent and approved design and construction documentation, prior to occupation of the development, or as otherwise approved by Council in writing.

 

 

OPERATIONAL CONDITIONS

The following operational conditions must be complied with at all times, throughout the use and operation of the development.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent and to maintain reasonable levels of public health and environmental amenity.

 

Use of premises

36.     The premises must only be used as a single residential dwelling and must not be used for dual or multi-occupancy purposes.

 

External Lighting

37.     External lighting to the premises must be designed and located so as to minimise light-spill beyond the property boundary or cause a public nuisance.

 

ADVISORY NOTES

The following information is provided for your assistance to ensure compliance with the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, or other relevant legislation and Council’s policies.  This information does not form part of the conditions of development consent pursuant to Section 80A of the Act.

 

A1      The requirements and provisions of the Environmental Planning & Assessment Act 1979 and Environmental Planning & Assessment Regulation 2000, must be fully complied with at all times.

 

Failure to comply with these requirements is an offence, which renders the responsible person liable to a maximum penalty of $1.1 million.  Alternatively, Council may issue a penalty infringement notice (for up to $1,500) for each offence.  Council may also issue notices and orders to demolish unauthorised or non-complying building work, or to comply with the requirements of Council’s development consent.

 

A2      Demolition, building or excavation work must not be commenced until;

 

§  A Construction Certificate has been obtained from Council or an Accredited Certifier

§  Council or an Accredited Certifier has been appointed as the Principal Certifying Authority for the development

§  Council and the Principal Certifying Authority have been given at least 2 days notice (in writing) prior to commencing any works.

 

A3      This determination does not include an assessment of the proposed works under the Building Code of Australia (BCA) and other relevant Standards.  All new building work (including alterations and additions) must comply with the BCA and relevant Standards and you are advised to liaise with your architect, engineer and building consultant prior to lodgement of your construction certificate.

 

A4      Council’s Building Approvals & Certification team can issue Construction Certificates and be your Principal Certifying Authority for the development, to undertake inspections and ensure compliance with the development consent, relevant building regulations and standards of construction.  For further details contact Council’s Building Approvals & Certification team on 9399 0944.

 

A5      A Local Approval application must be submitted to and be approved by Council's Building Approvals & Certification team prior to commencing any of the following activities on a footpath, road, nature strip or in any public place:-

 

§  Install or erect any site fencing, hoardings or site structures

§  Operate a crane or hoist goods or materials over a footpath or road

§  Placement of a waste skip or any other container or article.

 

For further information please contact Council’s Building Approvals & Certification team on 9399 0944.

 

A6      Specific details of the location of the building/s should be provided in the Construction Certificate to demonstrate that the proposed building work will not encroach onto the adjoining properties, Council’s road reserve or any public place, to the satisfaction of the Certifying Authority.

 

A7      Prior to commencing any works, the owner/builder should contact Dial Before You Dig on 1100 or www.dialbeforeyoudig.com.au and relevant Service Authorities, for information on potential underground pipes and cables within the vicinity of the development site.

 

A8      This consent does not authorise any trespass or encroachment upon any adjoining or supported land or building whether private or public.  Where any underpinning, shoring, soil anchoring (temporary or permanent) or the like is proposed to be carried out upon any adjoining or supported land, the land owner or principal contractor must obtain:

 

§  the consent of the owners of such adjoining or supported land to trespass or encroach, or

§  an access order under the Access to Neighbouring Land Act 2000, or

§  an easement under section 88K of the Conveyancing Act 1919, or

§  an easement under section 40 of the Land & Environment Court Act 1979, as appropriate.

 

Section 177 of the Conveyancing Act 1919 creates a statutory duty of care in relation to support of land.  Accordingly, a person has a duty of care not to do anything on or in relation to land being developed (the supporting land) that removes the support provided by the supporting land to any other adjoining land (the supported land).

 

MOTION: (Andrews/Mayor, Cr Matson) CARRIED UNANIMOUSLY - SEE RESOLUTION.

 

 

 

D112/11   Development Application Report - 155-157 Arden Street, Coogee (DA/58/2008/D)

PL132/11

RESOLUTION: (White/Matthews) that Council, as the consent authority, grants its consent under Section 96 of the Environmental Planning and Assessment Act 1979, as amended, to modify Development Consent No. 58/2008 for reconfiguration of the living/dining area of Apartment 7, installation of bi-folding screens to southern terraces of Apartments 7 and 8, installation of new skylight and awnings and associated changes, at No. 155-157 Arden Street, Coogee, in the following manner:

 

(a) Amendment of Condition No. 1 to read as follows:

1.       The development must be implemented substantially in accordance with the following plans: 

 

Dwg No.

Title

Revision

Date

DA101

Basement Plan

C

2/7/08

DA102

Floor plan ground level

C

2/7/08

DA103

Floor plan level 1

C

2/7/08

DA104

Floor plan level 2 & 3

D

26/2/10

DA105

Roof plan

B

2/7/08

DA106

Sections sheet 1

B

29/5/08

DA107

Sections sheet 2

B

29/5/08

DA108

North & west elevation

C

14/7/09

DA109

South & east elevation

C

2/7/08

DA118

Sections sheet 3

A

29/5/08

DA119

Sections sheet 4

A

29/5/08

DA134

Sandstone wall alignment

C

26/2/10

DA136

Sandstone wall and stair details

C

22/2/10

DA137

Sandstone wall details

B

26/2/10

 

the application form and on any supporting information received with the application, as amended by the following: -

 

·      Section 96 ‘A’ application dated 4 May 2010 and received by Council on 5 May 2010,

·      Section 96 ‘B’ application dated 3 November 2010 and received by Council on 4 November 2010,

·      Section 96 ‘C’  plans numbered SK01 through to SK09, dated 17 January 2011 and received by Council on 25 February 2011, and

·      The following Section 96 ‘D” plans:

 

Plan Number

Dated

Received

Prepared By

SK004A

17.08.2011

19 August 2011

MacKenzie Architects

SK005A

SK006A

SK007A

SK008A

SK009A

SK010A

 

only in so far as they relate to the modifications highlighted on the Section 96 plans and detailed in the Section 96 applications, except as may be amended  by the following conditions and as may be shown in red on the attached plans:

 

(b) Amendment of Conditions 15 and 16 to make reference to the updated BASIX Certificate:

15.     In accordance with Section 80A (11) of the Environmental Planning and Assessment Act 1979 and Clause 97A of the Environmental Planning and Assessment Regulation 2000, it is a prescribed condition that all of the required commitments listed in BASIX Certificate No. 382638M_02 (dated 24 August 2011) for this development are fulfilled.

 

The BASIX Certificate is to be submitted to the Certifying Authority with the Construction Certificate application for this development.

 

16.     In accordance with the provisions of the Environmental Planning & Assessment Regulation 2000, BASIX Certificate No. 382638M_02 (dated 24 August 2011) and associated documentation must be submitted to the Certifying Authority with the Construction Certificate application for this development.

 

The required commitments listed and identified in the BASIX Certificate are to be included on the plans, specifications and associated documentation for the proposed development, to the satisfaction of the Certifying Authority.

 

The design of the building must not be inconsistent with the development consent and any proposed variations to the building to achieve the BASIX commitments may necessitate a new development consent or amendment to the existing consent to be obtained, prior to a construction certificate being issued.

 

(c) Deletion of Condition No. 114.

 

MOTION: (White/Matthews) CARRIED – SEE RESOLUTION.

 

A DIVISION was taken and the names of the Councillors voting FOR and AGAINST were as follows:

 

FOR

AGAINST

Councillor Andrews

Councillor Smith

Councillor Belleli

Councillor Woodsmith

Councillor Bowen

 

Councillor Hughes

 

Councillor Matson

 

Councillor Matthews

 

Councillor Nash

 

Councillor Notley-Smith

 

Councillor Procopiadis

 

Councillor White

 

Total (10)

Total (2)

 

 

 

D113/11   Development Application Report - 28 Benvenue Street, Maroubra (DA/319/2011)

PL133/11

RESOLUTION: (Andrews/Mayor, Cr Matson) -

 

A.     That Council supports the objections under State Environmental Planning Policy No. 1 – Development Standards in respect to non-compliance with Clause 20F(1) of Randwick Local Environmental Plan 1998 (Consolidation), relating to Floor Space Ratio, on the grounds that the proposed development complies with the objectives of the above clauses, and will not adversely affect the amenity of the locality, and that the Department of Planning be advised accordingly.

 

B.     That Council, as the consent authority, grants development consent under Sections 80 and 80A of the Environmental Planning and Assessment Act 1979, as amended, to Development Application No. DA/319/2011 for alterations and additions to the existing semi detached dwelling house including new first floor level, at No. 28 Benvenue Street, Maroubra, subject to the following conditions:

 

DEVELOPMENT CONSENT CONDITIONS

 

GENERAL CONDITIONS

The development must be carried out in accordance with the following conditions of consent.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of environmental amenity.

 

Approved Plans & Supporting Documentation

1.       The development must be implemented substantially in accordance with the plans and supporting documentation listed below and endorsed with Council’s approved stamp, except where amended by Council in red and/or by other conditions of this consent:

 

Plan

Drawn by

Dated

Received

3138 (Sheets no. A1- 1/1, Revision C)

Extendahome

19 July 2011

25 July 2011

 

BASIX Certificate

No.

Dated

Received

 

A118301

20 July 2011

25 July 2011

 

Amendment of Plans & Documentation

2.       The approved plans and documents must be amended in accordance with the following requirements:

 

a.     Window No’s. W3 & W4 on the northern elevation of the proposed first floor addition must be fixed to a height of 1.5m and be provided with translucent, obscured, frosted or sandblasted glazing below this specified height.  Alternatively, external louvers angled in an upward direction to prevent overlooking to neighbouring properties shall be provided to these windows. The BASIX certificate is to be amended to reflect the above changes. Details of compliance are to be provided in the construction certificate plans.

 

REQUIREMENTS BEFORE A CONSTRUCTION CERTIFICATE CAN BE ISSUED

The following conditions of consent must be complied with before a ‘Construction Certificate’ is issued by either Randwick City Council or an Accredited Certifier.  All necessary information to demonstrate compliance with the following conditions of consent must be included in the documentation for the construction certificate.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Council’s development consent conditions and to achieve reasonable levels of environmental amenity.

 

Consent Requirements

3.       The requirements and amendments detailed in the ‘General Conditions’ must be complied with and be included in the construction certificate plans and associated documentation.

 

External Colours, Materials & Finishes

4.       a)     The colours, materials and finishes of the external surfaces are to be compatible with the existing building and adjacent development to maintain the integrity and amenity of the building and the streetscape.

 

External materials, finishes and colours of the building are required to match, as closely as possible, the existing building and any metal roof sheeting is to be pre-painted (e.g. Colourbond) to limit the level of reflection and glare.

 

b)     Details of the proposed colours, materials and textures (i.e. a schedule and brochure/s or sample board) are to be submitted to and approved by Council’s Manager Development Assessments prior to issuing a construction certificate for the development.

 

Section 94A Development Contributions

5.       In accordance with Council’s Section 94A Development Contributions Plan effective from 2 July 2007, based on the development cost of $158,182, the following applicable monetary levy must be paid to Council: $790.91.

       

The levy must be paid in cash, bank cheque or by credit card prior to a construction certificate [or subdivision certificate] being issued for the proposed development.  The development is subject to an index to reflect quarterly variations in the Consumer Price Index (CPI) from the date of Council’s determination to the date of payment.

 

Council’s Section 94A Development Contribution Plans may be inspected at the Customer Service Centre, Administrative Centre, 30 Frances Street, Randwick or at www.randwick.nsw.gov.au.

 

Long Service Levy Payments

6.       The required Long Service Levy payment, under the Building and Construction Industry Long Service Payments Act 1986, must be forwarded to the Long Service Levy Corporation or the Council, in accordance with Section 109F of the Environmental Planning & Assessment Act 1979.

 

At the time of this development consent, Long Service Levy payment is applicable on building work having a value of $25,000 or more, at the rate of 0.35% of the cost of the works.

 

REQUIREMENTS TO BE INCLUDED IN THE CONSTRUCTION CERTIFICATE

The requirements contained in the following conditions of consent must be complied with and details of compliance must be included in the construction certificate for the development.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000, Councils development consent conditions and to achieve reasonable levels of environmental amenity.

 

Compliance with the Building Code of Australia

7.       In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, it is a prescribed condition that all building work must be carried out in accordance with the provisions of the Building Code of Australia (BCA).  Details of compliance with the BCA are to be included in the construction certificate application.

 

Structural Adequacy

8.       Certificate of Adequacy supplied by a professional engineer shall be submitted to the certifying authority (and the Council, if the Council is not the certifying authority), certifying the structural adequacy of the existing structure to support the additional storey.

 

Smoke Alarms

9.       Smoke alarms are required to be installed in accordance with the relevant provisions of the Building Code of Australia (volume 2) smoke alarms must comply with AS3786.  Smoke alarms must be connected to the consumer mains electric power supply and provided with a battery back-up.  Details of compliance are to be included in the construction certificate.

 

BASIX Requirements

10.     In accordance with section 80A(11) of the Environmental Planning & Assessment Act 1979 and clause 97A of the Environmental Planning & Assessment Regulation 2000, the requirements and commitments contained in the relevant BASIX Certificate must be complied with.

 

The required commitments listed and identified in the BASIX Certificate must be included on the construction certificate plans, specifications and associated documentation, to the satisfaction of the Certifying Authority.

 

The design of the building must not be inconsistent with the development consent and any proposed variations to the building to achieve the BASIX commitments may necessitate a new development consent or amendment to the existing consent to be obtained, prior to a construction certificate being issued.

 

Stormwater Drainage

11.     A surface water/stormwater drainage system must be provided in accordance with the following requirements, to the satisfaction of the Certifying Authority and details are to be included in the construction certificate:-

 

a)     Surface water/stormwater drainage systems must be provided in accordance with the relevant requirements of the Building Code of Australia (Volume 2);

 

b)     The surface water/stormwater must be drained and discharged to the street gutter or, subject to site suitability, the stormwater may be drained to a suitably designed absorption pit;

 

c)     Any absorption pits or soaker wells should be located not less than 3m from any adjoining premises and the stormwater must not be directed to any adjoining premises or cause a nuisance;

 

d)     External paths and ground surfaces are to be constructed at appropriate levels and be graded and drained away from the building and adjoining premises, so as not to result in the entry of water into the building, or cause a nuisance or damage to the adjoining premises;

 

e)     Details of any proposed drainage systems or works to be carried out in the road, footpath or nature strip must be submitted to and approved by Council before commencing these works.

 

REQUIREMENTS PRIOR TO THE COMMENCEMENT OF ANY WORKS

The following conditions of consent must be complied with prior to the commencement of any works on the site.  The necessary documentation and information must be provided to the Council or the ‘Principal Certifying Authority’, as applicable.

 

These conditions have been applied to satisfy the relevant requirements of the Environmental Planning & Assessment Act 1979, Environmental Planning & Assessment Regulation 2000 and to provide reasonable levels of public health, safety and environmental amenity.

 

Construction Certificate, Principal Certifying Authority & Commencement of Works

12.     Prior to the commencement of any building works, the following requirements must be complied with:

 

a)     a Construction Certificate must be obtained from the Council or an accredited certifier, in accordance with the provisions of the Environmental Planning & Assessment Act 1979.

 

A copy of the construction certificate, the approved development consent plans and consent conditions must be kept on the site at all times and be made available to the Council officers and all building contractors for assessment.

 

b)     a Principal Certifying Authority (PCA) must be appointed to carry out the necessary building inspections and to issue an occupation certificate; and

 

c)     a principal contractor must be appointed for the building work, or in relation to residential building work, an owner-builder permit may be obtained in accordance with the requirements of the Home Building Act 1989, and the PCA and Council are to be notified accordingly; and

 

d)     the principal contractor must be advised of the required critical stage inspections and other inspections to be carried out, as specified by the Principal Certifying Authority; and

 

e)     at least two days notice must be given to the Council, in writing, prior to commencing any works.

 

In relation to residential building work, the principal contractor must be the holder of a contractor licence, in accordance with the provisions of the Home Building Act 1989.

 

Home Building Act 1989

13.     In accordance with section 80 A (11) of the Environmental Planning & Assessment Act 1979 and clause 98 of the Environmental Planning & Assessment Regulation 2000, the requirements of the Home Building Act 1989 must be complied with.

 

Details of the Licensed Building Contractor and a copy of the relevant Certificate of Home Warranty Insurance or a copy of the Owner-Builder Permit (as applicable) must be provided to the Principal Certifying Authority and Council.

 

Dilapidation Reports

14.     A dilapidation report prepared by a professional engineer, building surveyor or other suitably qualified independent person must be submitted to the satisfaction of the Principal Certifying Authority prior to commencement of any demolition, excavation or building works, in the following cases:

 

·        excavations for new dwellings, additions to dwellings, swimming pools or the like which are proposed to be located within the zone of influence of the footings of any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

·        new dwellings or additions to dwellings sited up to shared property boundaries (e.g.  additions to a semi-detached dwelling or terraced dwellings),

·        excavations for new dwellings, additions to dwellings, swimming pools or the like which are within rock and may result in vibration and or potential damage to any dwelling, associated garage or other substantial structure located upon an adjoining  premises,

·        as otherwise may be required by the Principal Certifying Authority.

 

The report (including photographs) are required to detail the current condition and status of any dwelling, associated garage or other substantial structure located upon the adjoining premises, which may be affected by the subject works.  A copy of the dilapidation report is to be given to the owners of the premises encompassed in the report/s before commencing any works.

 

Construction Noise & Vibration Management Plan

15.     Noise and vibration emissions during the construction of the building and associated site works must not result in damage to nearby premises or result in an unreasonable loss of amenity to nearby residents and the relevant requirements of the Protection of the Environment Operations Act 1997 and NSW DECC Guidelines must be satisfied at all times.

 

Noise and vibration from any rock excavation machinery, pile drivers and all plant and equipment must be minimised, by using appropriate plant and equipment, silencers and the implementation of noise management strategies.

 

A Construction Noise Management Plan, prepared in accordance with the NSW DECC Construction Noise Guideline by a suitably qualified person, is to be implemented throughout the works.  A copy of the strategy must be provided to the Principal Certifying Authority and Council prior to the commencement of works on site.

 

Temporary Site Fencing

16.     Temporary site safety fencing must be provided to the perimeter of the site (unless the site is separated from the adjoining land by an existing structurally adequate fence, having a minimum height of 1.5 metres).  Temporary site fences are to have a minimum height of 1.8 metres and be constructed of cyclone wire fencing, with geotextile fabric attached to the inside of the fence to provide dust control, or other material approved by Council.

 

Temporary site fences are to be structurally adequate, safe and be constructed in a professional manner and the use of poor quality materials or steel reinforcement mesh as fencing is not permissible.

 

Temporary fences must be in place prior to the commencement of any demolition, excavation or building works and be maintained throughout construction.

 

If it is proposed to locate any site fencing, hoardings or amenities upon any part of the footpath, nature strip or public place, a Local Approval application must be submitted to and approved by Council’s Health, Building & Regulatory Services before placing any item or article on the road, footpath or nature strip.

 

Construction Site Management Plan

17.     A Construction Site Management Plan must be developed and implemented prior to the commencement of any works. The construction site management plan must include the following measures, as applicable to the type of development:

 

·           location and construction of protective fencing / hoardings to the perimeter of the site;

·            location of site storage areas/sheds/equipment;

·            location of building materials for construction;

·            provisions for public safety;

·            dust control measures;

·            site access location and construction

·            details of methods of disposal of demolition materials;

·            protective measures for tree preservation;

·            provisions for temporary sanitary facilities;

·            location and size of waste containers/bulk bins;

·            details of proposed sediment and erosion control measures;

·            provisions for temporary stormwater drainage;

·            construction noise and vibration management;

·            construction traffic management details.

 

The site management measures must be implemented prior to the commencement of any site works and be maintained throughout the works, to the satisfaction of Council.

 

A copy of the Construction Site Management Plan must be provided to the Principal Certifying Authority and Council prior to commencing site works.  A copy must also be maintained on site and be made available to Council officers upon request.

 

Demolition Work Plan

18.     A Demolition Work Plan must be prepared for the development in accordance with Australian Standard AS2601-2001, Demolition of Structures and relevant environmental/occupational health and safety requirements.

 

The Demolition Work Plan must include the following information (as applicable):

 

·           The name, address, contact details and licence number of the Demolisher /Asbestos Removal Contractor

·           Details of hazardous materials (including asbestos)

·           Method/s of demolition (including removal of any asbestos)

·           Measures and processes to be implemented to ensure the health & safety of workers and community

·           Measures to be implemented to minimise any airborne dust and asbestos

·           Methods and location of disposal of any hazardous materials (including asbestos)

·           Other relevant details, measures and requirements to be implemented

·           Details of re-use, recycling and disposal of waste demolition/building materials